Each of the following accurately describes total float in a schedule EXCEPT:
Answer(s): C
Total float measures the flexibility in an activity’s timing within a schedule. It is defined as the amount of time an activity can be delayed without affecting the project’s overall completion date or the completion date of any of its successors.Option A, B, and D accurately describe total float: it is calculated as the difference between early and late start/finish dates, can be positive or negative, and is associated with project completion.Option C describes free float, not total float, and thus is incorrect.
The amount of time that an activity can be delayed from its early start date without delaying project completion is called:
The time an activity can be delayed from its early start without impacting the overall project completion date is called total float.Option A (negative float) refers to delays beyond permissible limits.Option B (free float) refers to delays without affecting the early start of any successor.Option D (interfering float) is a lesser-used term denoting the time available without delaying the project completion but affecting a successor’s float.
In its simplest form, what is the main drawback of critical path method scheduling?
Answer(s): B
A fundamental limitation of Critical Path Method (CPM) scheduling is its assumption of unlimited resources, meaning it does not account for resource constraints when calculating schedules.Option A (backward pass) is a standard part of the CPM process.Option C is incorrect as CPM considers activity dependencies.Option D refers to flexibility in diagramming methods, not a drawback.The PSP Study Guide highlights resource constraints as a significant challenge in CPM application.
If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity
Answer(s): D
Negative total float occurs when an activity’s scheduled completion date extends beyond the project deadline due to constraints. This condition indicates that the activity is still pending and needs immediate attention to avoid further delays.Option A (milestone) is unrelated.Option B (critical path) is not necessarily true, as activities with negative float can exist off the critical path under certain constraints.Option C (completed in the past) is incorrect as negative float applies only to future or ongoing activities.
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?
Total float is influenced by factors like multiple calendars, start/finish constraints, and preferential logic because these directly affect the calculation of early and late dates.Option D (front end loading), which involves distributing work to earlier project phases, does not inherently affect float calculations as it primarily pertains to resource or phase management strategies.
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay.Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
As-Planned vs. As-Built (APAB) Analysis:A simple APAB compares the planned schedule to the actual schedule to identify deviations.It does not involve inserting delaying events or re-forecasting the schedule, which makes it unsuitable for detailed analysis.Limitations of APAB:Unsuitable for complex projects (A).Inserting delays is not part of APAB (B).Accuracy diminishes for long projects (C) or those requiring granular mid-project analyses (D).Conclusion: The correct answer is B, as inserting delays into the as-planned schedule is not a feature of simple APAB analysis.
Which statement is true?
Compensability and Excusability:Excusable delays are those beyond the contractor’s control, while compensable delays are excusable delays for which the owner bears responsibility.If a delay is compensable, it inherently qualifies as excusable.PSP Study Guide Reference:The relationship between excusability and compensability is clarified in delay analysis discussions.Conclusion: The correct answer is D, as compensability implies excusability.
Which of the following phases does NOT describe the commonly accepted construction life cycle?
Answer(s): A
Construction Life Cycle Phases:Common phases: planning and design, installation (execution), and turnover/start-up.Claims and disputes may arise during the project but are not a defined phase of the construction life cycle.PSP Study Guide Reference:The study guide outlines standard phases without including claims and disputes as a formal phase.Conclusion: The correct answer is A, as claims and disputes are not an inherent phase of the construction life cycle.
Share your comments for AACE International AACE-PSP exam with other users:
huawei is ok
good one nice
please continue
this exam dumps just did the job. i donot want to ruffle your feathers but your exam dumps and mock test engine is amazing.
nice questions
the explanation are really helpful
just passed my exam yesterday on my first attempt. these dumps were extremely helpful in passing first time. the questions were very, very similar to these questions!
cosmos db is paas not saas
what is the percentage of common questions in gcp exam compared to 197 dump questions? are they 100% matching with real gcp exam?
not able to see questions
by far one of the best sites for free questions. i have pass 2 exams with the help of this website.
excellent question bank.
it really helped
excelent material
the new versoin of this exam which i downloaded has all the latest questions from the exam. i only saw 3 new questions in the exam which was not in this dump.
question 8 - can cloudtrail be used for storing jobs? based on aws - aws cloudtrail is used for governance, compliance and investigating api usage across all of our aws accounts. every action that is taken by a user or script is an api call so this is logged to [aws] cloudtrail. something seems incorrect here.
question 13 tda - c01 answer : quick table calculation -> percentage of total , compute using table down
pls share teh dump
question 44 answer is user risk
please post the questions for preparation
thanks for the questions
please reopen it now ..its really urgent
these practice exam questions were exactly what i needed. the variety of questions and the realistic exam-like environment they created helped me assess my strengths and weaknesses. i felt more confident and well-prepared on exam day, and i owe it to this exam dumps!
thank u it very instructuf
its helpful?
is this dump still valid???
question 205 answer is b
question 39, should be answer b, directions stated is being sudneted from /21 to a /23. a /23 has 512 ips so 510 hosts. and can make 4 subnets out of the /21
beautiful test engine software and very helpful. questions are same as in the real exam. i passed my paper.
the questions are exactly the same in real exam. just make sure not to answer all them correct or else they suspect you are cheating.
question: 78 the right answer i think is d not a
very helpful
i am writing this exam tomorrow and have dumps
can i have the icdl excel exam
Keeping this site free takes real effort. We constantly battle automated scraping and unauthorized content copying. A quick account helps us protect the community and keep the site free.
To continue studying for your AACE-PSP, please sign in or create a free account.