AACE International Planning & Scheduling Professional (PSP) AACE-PSP Dumps in PDF

Free AACE International AACE-PSP Real Questions (page: 22)

Each of the following accurately describes total float in a schedule EXCEPT:

  1. The amount of time an activity can be delayed without delaying the overall project completion time.
  2. Can be positive or negative.
  3. The amount of time an activity can be delayed without delaying the start or occurrence of any other activity or event in the network.
  4. Computed for an activity by subtracting its early finish from its late finish, or its early start from its late start.

Answer(s): C

Explanation:

Total float measures the flexibility in an activity’s timing within a schedule. It is defined as the amount of time an activity can be delayed without affecting the project’s overall completion date or the completion date of any of its successors.
Option A, B, and D accurately describe total float: it is calculated as the difference between early and late start/finish dates, can be positive or negative, and is associated with project completion.
Option C describes free float, not total float, and thus is incorrect.



The amount of time that an activity can be delayed from its early start date without delaying project completion is called:

  1. Negative float.
  2. Free float.
  3. Total float.
  4. Interfering float.

Answer(s): C

Explanation:

The time an activity can be delayed from its early start without impacting the overall project completion date is called total float.
Option A (negative float) refers to delays beyond permissible limits.
Option B (free float) refers to delays without affecting the early start of any successor.
Option D (interfering float) is a lesser-used term denoting the time available without delaying the project completion but affecting a successor’s float.



In its simplest form, what is the main drawback of critical path method scheduling?

  1. It requires a backward pass to calculate late dates.
  2. It assumes that resources are unlimited.
  3. It doesn't account for interdependent between activities.
  4. It allows for Precedence Diagramming Method to be used in place of Arrow Diagramming Method.

Answer(s): B

Explanation:

A fundamental limitation of Critical Path Method (CPM) scheduling is its assumption of unlimited resources, meaning it does not account for resource constraints when calculating schedules.
Option A (backward pass) is a standard part of the CPM process.
Option C is incorrect as CPM considers activity dependencies.
Option D refers to flexibility in diagramming methods, not a drawback.
The PSP Study Guide highlights resource constraints as a significant challenge in CPM application.



If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity

  1. Is a milestone.
  2. It is on the critical path.
  3. Was completed in the past.
  4. Has yet to be completed.

Answer(s): D

Explanation:

Negative total float occurs when an activity’s scheduled completion date extends beyond the project deadline due to constraints. This condition indicates that the activity is still pending and needs immediate attention to avoid further delays.
Option A (milestone) is unrelated.
Option B (critical path) is not necessarily true, as activities with negative float can exist off the critical path under certain constraints.
Option C (completed in the past) is incorrect as negative float applies only to future or ongoing activities.



Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

  1. Multiple calendars.
  2. Start and finish constraints.
  3. Preferential logic.
  4. Front end loading.

Answer(s): D

Explanation:

Total float is influenced by factors like multiple calendars, start/finish constraints, and preferential logic because these directly affect the calculation of early and late dates.
Option D (front end loading), which involves distributing work to earlier project phases, does not inherently affect float calculations as it primarily pertains to resource or phase management strategies.



You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay.
Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

  1. Not suitable for complicated projects with multiple planned critical paths.
  2. Accuracy is increased by inserting delaying events into the as-planned schedule.
  3. Not suitable for projects with long durations.
  4. Less accurate as the analysis advances through the project.

Answer(s): B

Explanation:

As-Planned vs. As-Built (APAB) Analysis:
A simple APAB compares the planned schedule to the actual schedule to identify deviations.
It does not involve inserting delaying events or re-forecasting the schedule, which makes it unsuitable for detailed analysis.
Limitations of APAB:
Unsuitable for complex projects (A).
Inserting delays is not part of APAB (B).
Accuracy diminishes for long projects (C) or those requiring granular mid-project analyses (D).
Conclusion: The correct answer is B, as inserting delays into the as-planned schedule is not a feature of simple APAB analysis.



Which statement is true?

  1. Where compensability cannot be established, excusability is assumed.
  2. Where compensability can be established, excusabltity cannot be assumed.
  3. Where compensability cannot be established, excusability is a given.
  4. Where compensability can be established, excusability is assumed.

Answer(s): D

Explanation:

Compensability and Excusability:
Excusable delays are those beyond the contractor’s control, while compensable delays are excusable delays for which the owner bears responsibility.
If a delay is compensable, it inherently qualifies as excusable.
PSP Study Guide Reference:
The relationship between excusability and compensability is clarified in delay analysis discussions.
Conclusion: The correct answer is D, as compensability implies excusability.



Which of the following phases does NOT describe the commonly accepted construction life cycle?

  1. Claims and disputes phase.
  2. Installation phase.
  3. Planning and design phase.
  4. Turnover and start-up phase.

Answer(s): A

Explanation:

Construction Life Cycle Phases:
Common phases: planning and design, installation (execution), and turnover/start-up.
Claims and disputes may arise during the project but are not a defined phase of the construction life cycle.
PSP Study Guide Reference:
The study guide outlines standard phases without including claims and disputes as a formal phase.
Conclusion: The correct answer is A, as claims and disputes are not an inherent phase of the construction life cycle.



Share your comments for AACE International AACE-PSP exam with other users:

M
mohamed abdo
9/1/2023 4:59:00 AM

very useful

T
Tom
3/18/2022 8:00:00 PM

i purchased this exam dumps from another website with way more questions but they were all invalid and outdate. this exam dumps was right to the point and all from recent exam. it was a hard pass.

E
Edrick GOP
10/24/2023 6:00:00 AM

it was a good experience and i got 90% in the 200-901 exam.

A
anonymous
8/10/2023 2:28:00 AM

hi please upload this

B
Bakir
7/6/2023 7:24:00 AM

please upload it

A
Aman
6/18/2023 1:27:00 PM

really need this dump. can you please help.

N
Neela Para
1/8/2024 6:39:00 PM

really good and covers many areas explaining the answer.

K
Karan Patel
8/15/2023 12:51:00 AM

yes, can you please upload the exam?

N
NISHAD
11/7/2023 11:28:00 AM

how many questions are there in these dumps?

P
Pankaj
7/3/2023 3:57:00 AM

hi team, please upload this , i need it.

D
DN
9/4/2023 11:19:00 PM

question 14 - run terraform import: this is the recommended best practice for bringing manually created or destroyed resources under terraform management. you use terraform import to associate an existing resource with a terraform resource configuration. this ensures that terraform is aware of the resource, and you can subsequently manage it with terraform.

Z
Zhiguang
8/19/2023 11:37:00 PM

please upload dump. thanks in advance.

D
deedee
12/23/2023 5:51:00 PM

great great

A
Asad Khan
11/1/2023 3:10:00 AM

answer 16 should be b your organizational policies require you to use virtual machines directly

S
Sale Danasabe
10/24/2023 5:21:00 PM

the question are kind of tricky of you didnt get the hnag on it.

L
Luis
11/16/2023 1:39:00 PM

can anyone tell me if this is for rhel8 or rhel9?

H
hik
1/19/2024 1:47:00 PM

good content

B
Blessious Phiri
8/15/2023 2:18:00 PM

pdb and cdb are critical to the database

Z
Zuned
10/22/2023 4:39:00 AM

till 104 questions are free, lets see how it helps me in my exam today.

M
Muhammad Rawish Siddiqui
12/3/2023 12:11:00 PM

question # 56, answer is true not false.

A
Amaresh Vashishtha
8/27/2023 1:33:00 AM

i would be requiring dumps to prepare for certification exam

A
Asad
9/8/2023 1:01:00 AM

very helpful

B
Blessious Phiri
8/13/2023 3:10:00 PM

control file is the heart of rman backup

S
Senthil
9/19/2023 5:47:00 AM

hi could you please upload the ibm c2090-543 dumps

H
Harry
6/27/2023 7:20:00 AM

appriciate if you could upload this again

A
Anonymous
7/10/2023 4:10:00 AM

please upload the dump

R
Raja
6/20/2023 5:30:00 AM

i found some questions answers mismatch with explanation answers. please properly update

D
Doora
11/30/2023 4:20:00 AM

nothing to mention

D
deally
1/19/2024 3:41:00 PM

knowable questions

S
Sonia
7/23/2023 4:03:00 PM

very helpfull

B
binEY
10/6/2023 5:15:00 AM

good questions

N
Neha
9/28/2023 1:58:00 PM

its helpful

D
Desmond
1/5/2023 9:11:00 PM

i just took my oracle exam and let me tell you, this exam dumps was a lifesaver! without them, iam not sure i would have passed. the questions were tricky and the answers were obscure, but the exam dumps had everything i needed. i would recommend to anyone looking to pass their oracle exams with flying colors (and a little bit of cheating) lol.

D
Davidson OZ
9/9/2023 6:37:00 PM

22. if you need to make sure that one computer in your hot-spot network can access the internet without hot-spot authentication, which menu allows you to do this? answer is ip binding and not wall garden. wall garden allows specified websites to be accessed with users authentication to the hotspot

AI Tutor 👋 I’m here to help!