Each of the following accurately describes total float in a schedule EXCEPT:

  1. The amount of time an activity can be delayed without delaying the overall project completion time.
  2. Can be positive or negative.
  3. The amount of time an activity can be delayed without delaying the start or occurrence of any other activity or event in the network.
  4. Computed for an activity by subtracting its early finish from its late finish, or its early start from its late start.

Answer(s): C

Explanation:

Total float measures the flexibility in an activity’s timing within a schedule. It is defined as the amount of time an activity can be delayed without affecting the project’s overall completion date or the completion date of any of its successors.
Option A, B, and D accurately describe total float: it is calculated as the difference between early and late start/finish dates, can be positive or negative, and is associated with project completion.
Option C describes free float, not total float, and thus is incorrect.



The amount of time that an activity can be delayed from its early start date without delaying project completion is called:

  1. Negative float.
  2. Free float.
  3. Total float.
  4. Interfering float.

Answer(s): C

Explanation:

The time an activity can be delayed from its early start without impacting the overall project completion date is called total float.
Option A (negative float) refers to delays beyond permissible limits.
Option B (free float) refers to delays without affecting the early start of any successor.
Option D (interfering float) is a lesser-used term denoting the time available without delaying the project completion but affecting a successor’s float.



In its simplest form, what is the main drawback of critical path method scheduling?

  1. It requires a backward pass to calculate late dates.
  2. It assumes that resources are unlimited.
  3. It doesn't account for interdependent between activities.
  4. It allows for Precedence Diagramming Method to be used in place of Arrow Diagramming Method.

Answer(s): B

Explanation:

A fundamental limitation of Critical Path Method (CPM) scheduling is its assumption of unlimited resources, meaning it does not account for resource constraints when calculating schedules.
Option A (backward pass) is a standard part of the CPM process.
Option C is incorrect as CPM considers activity dependencies.
Option D refers to flexibility in diagramming methods, not a drawback.
The PSP Study Guide highlights resource constraints as a significant challenge in CPM application.



If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity

  1. Is a milestone.
  2. It is on the critical path.
  3. Was completed in the past.
  4. Has yet to be completed.

Answer(s): D

Explanation:

Negative total float occurs when an activity’s scheduled completion date extends beyond the project deadline due to constraints. This condition indicates that the activity is still pending and needs immediate attention to avoid further delays.
Option A (milestone) is unrelated.
Option B (critical path) is not necessarily true, as activities with negative float can exist off the critical path under certain constraints.
Option C (completed in the past) is incorrect as negative float applies only to future or ongoing activities.



Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

  1. Multiple calendars.
  2. Start and finish constraints.
  3. Preferential logic.
  4. Front end loading.

Answer(s): D

Explanation:

Total float is influenced by factors like multiple calendars, start/finish constraints, and preferential logic because these directly affect the calculation of early and late dates.
Option D (front end loading), which involves distributing work to earlier project phases, does not inherently affect float calculations as it primarily pertains to resource or phase management strategies.



You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay.
Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

  1. Not suitable for complicated projects with multiple planned critical paths.
  2. Accuracy is increased by inserting delaying events into the as-planned schedule.
  3. Not suitable for projects with long durations.
  4. Less accurate as the analysis advances through the project.

Answer(s): B

Explanation:

As-Planned vs. As-Built (APAB) Analysis:
A simple APAB compares the planned schedule to the actual schedule to identify deviations.
It does not involve inserting delaying events or re-forecasting the schedule, which makes it unsuitable for detailed analysis.
Limitations of APAB:
Unsuitable for complex projects (A).
Inserting delays is not part of APAB (B).
Accuracy diminishes for long projects (C) or those requiring granular mid-project analyses (D).
Conclusion: The correct answer is B, as inserting delays into the as-planned schedule is not a feature of simple APAB analysis.



Which statement is true?

  1. Where compensability cannot be established, excusability is assumed.
  2. Where compensability can be established, excusabltity cannot be assumed.
  3. Where compensability cannot be established, excusability is a given.
  4. Where compensability can be established, excusability is assumed.

Answer(s): D

Explanation:

Compensability and Excusability:
Excusable delays are those beyond the contractor’s control, while compensable delays are excusable delays for which the owner bears responsibility.
If a delay is compensable, it inherently qualifies as excusable.
PSP Study Guide Reference:
The relationship between excusability and compensability is clarified in delay analysis discussions.
Conclusion: The correct answer is D, as compensability implies excusability.



Which of the following phases does NOT describe the commonly accepted construction life cycle?

  1. Claims and disputes phase.
  2. Installation phase.
  3. Planning and design phase.
  4. Turnover and start-up phase.

Answer(s): A

Explanation:

Construction Life Cycle Phases:
Common phases: planning and design, installation (execution), and turnover/start-up.
Claims and disputes may arise during the project but are not a defined phase of the construction life cycle.
PSP Study Guide Reference:
The study guide outlines standard phases without including claims and disputes as a formal phase.
Conclusion: The correct answer is A, as claims and disputes are not an inherent phase of the construction life cycle.



Share your comments for AACE International AACE-PSP exam with other users:

D
Dan
8/10/2023 4:19:00 PM

question 129 is completely wrong.

G
gayathiri
7/6/2023 12:10:00 AM

i need dump

D
Deb
8/15/2023 8:28:00 PM

love the site.

M
Michelle
6/23/2023 4:08:00 AM

can you please upload it back?

A
Ajay
10/3/2023 12:17:00 PM

could you please re-upload this exam? thanks a lot!

H
him
9/30/2023 2:38:00 AM

great about shared quiz

S
San
11/14/2023 12:46:00 AM

goood helping

W
Wang
6/9/2022 10:05:00 PM

pay attention to questions. they are very tricky. i waould say about 80 to 85% of the questions are in this exam dump.

M
Mary
5/16/2023 4:50:00 AM

wish you would allow more free questions

T
thomas
9/12/2023 4:28:00 AM

great simulation

S
Sandhya
12/9/2023 12:57:00 AM

very g inood

A
Agathenta
12/16/2023 1:36:00 PM

q35 should be a

M
MD. SAIFUL ISLAM
6/22/2023 5:21:00 AM

sap c_ts450_2021

S
Satya
7/24/2023 3:18:00 AM

nice questions

S
sk
5/13/2023 2:10:00 AM

ecellent materil for unserstanding

G
Gerard
6/29/2023 11:14:00 AM

good so far

L
Limbo
10/9/2023 3:08:00 AM

this is way too informative

T
Tejasree
8/26/2023 1:46:00 AM

very helpfull

Y
Yolostar Again
10/12/2023 3:02:00 PM

q.189 - answers are incorrect.

S
Shikha Bakra
9/10/2023 5:16:00 PM

awesome job in getting these questions

K
Kevin
10/20/2023 2:01:00 AM

i cant find aws certified practitioner clf-c01 exam in aws website but i found aws certified practitioner clf-c02 exam. can everyone please verify the difference between the two clf-c01 and clf-c02? thank you

D
D Mario
6/19/2023 10:38:00 PM

grazie mille. i got a satisfactory mark in my exam test today because of this exam dumps. sorry for my english.

B
Bharat Kumar Saraf
10/31/2023 4:36:00 AM

some of the answers are incorrect. need to be reviewed.

J
JP
7/13/2023 12:21:00 PM

so far so good

K
Kiky V
8/8/2023 6:32:00 PM

i am really liking it

T
trying
7/28/2023 12:37:00 PM

thanks good stuff

E
exampei
10/4/2023 2:40:00 PM

need dump c_tadm_23

E
Eman Sawalha
6/10/2023 6:18:00 AM

next time i will write a full review

J
johnpaul
11/15/2023 7:55:00 AM

first time using this site

O
omiornil@gmail.com
7/25/2023 9:36:00 AM

please sent me oracle 1z0-1105-22 pdf

J
John
8/29/2023 8:59:00 PM

very helpful

K
Kvana
9/28/2023 12:08:00 PM

good info about oml

C
Checo Lee
7/3/2023 5:45:00 PM

very useful to practice

D
dixitdnoh@gmail.com
8/27/2023 2:58:00 PM

this website is very helpful.

AI Tutor 👋 I’m here to help!