Each of the following accurately describes total float in a schedule EXCEPT:
Answer(s): C
Total float measures the flexibility in an activity’s timing within a schedule. It is defined as the amount of time an activity can be delayed without affecting the project’s overall completion date or the completion date of any of its successors.Option A, B, and D accurately describe total float: it is calculated as the difference between early and late start/finish dates, can be positive or negative, and is associated with project completion.Option C describes free float, not total float, and thus is incorrect.
The amount of time that an activity can be delayed from its early start date without delaying project completion is called:
The time an activity can be delayed from its early start without impacting the overall project completion date is called total float.Option A (negative float) refers to delays beyond permissible limits.Option B (free float) refers to delays without affecting the early start of any successor.Option D (interfering float) is a lesser-used term denoting the time available without delaying the project completion but affecting a successor’s float.
In its simplest form, what is the main drawback of critical path method scheduling?
Answer(s): B
A fundamental limitation of Critical Path Method (CPM) scheduling is its assumption of unlimited resources, meaning it does not account for resource constraints when calculating schedules.Option A (backward pass) is a standard part of the CPM process.Option C is incorrect as CPM considers activity dependencies.Option D refers to flexibility in diagramming methods, not a drawback.The PSP Study Guide highlights resource constraints as a significant challenge in CPM application.
If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity
Answer(s): D
Negative total float occurs when an activity’s scheduled completion date extends beyond the project deadline due to constraints. This condition indicates that the activity is still pending and needs immediate attention to avoid further delays.Option A (milestone) is unrelated.Option B (critical path) is not necessarily true, as activities with negative float can exist off the critical path under certain constraints.Option C (completed in the past) is incorrect as negative float applies only to future or ongoing activities.
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?
Total float is influenced by factors like multiple calendars, start/finish constraints, and preferential logic because these directly affect the calculation of early and late dates.Option D (front end loading), which involves distributing work to earlier project phases, does not inherently affect float calculations as it primarily pertains to resource or phase management strategies.
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay.Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
As-Planned vs. As-Built (APAB) Analysis:A simple APAB compares the planned schedule to the actual schedule to identify deviations.It does not involve inserting delaying events or re-forecasting the schedule, which makes it unsuitable for detailed analysis.Limitations of APAB:Unsuitable for complex projects (A).Inserting delays is not part of APAB (B).Accuracy diminishes for long projects (C) or those requiring granular mid-project analyses (D).Conclusion: The correct answer is B, as inserting delays into the as-planned schedule is not a feature of simple APAB analysis.
Which statement is true?
Compensability and Excusability:Excusable delays are those beyond the contractor’s control, while compensable delays are excusable delays for which the owner bears responsibility.If a delay is compensable, it inherently qualifies as excusable.PSP Study Guide Reference:The relationship between excusability and compensability is clarified in delay analysis discussions.Conclusion: The correct answer is D, as compensability implies excusability.
Which of the following phases does NOT describe the commonly accepted construction life cycle?
Answer(s): A
Construction Life Cycle Phases:Common phases: planning and design, installation (execution), and turnover/start-up.Claims and disputes may arise during the project but are not a defined phase of the construction life cycle.PSP Study Guide Reference:The study guide outlines standard phases without including claims and disputes as a formal phase.Conclusion: The correct answer is A, as claims and disputes are not an inherent phase of the construction life cycle.
Share your comments for AACE International AACE-PSP exam with other users:
awesome training material
where is dump
q. 289 - the correct answer should be b not d, since the question asks for the most secure way to provide access to a s3 bucket (a single one), and by principle of the least privilege you should not be giving access to all buckets.
please i need if possible h12-831,
good collection of questions and solution for pl500 certification
i would like to appear the exam.
i am very happy as i cleared my comptia a+ 220-1101 exam. i studied from as it has all exam dumps and mock tests available. i got 91% on the test.
need this dump
its really good to eventuate knowledge before appearing for the actual exam.
this is great
please i want the questions to pass the exam
i need to pass exam
great, i appreciate it.
please could you upload (isc)2 certified in cybersecurity (cc) exam questions
good questions, wrong answers
im preparing for exams
question no: 42 isnt azure vm an iaas solution? so, shouldnt the answer be "no"?
im study azure
i need this now
i took the aws saa-c03 test and scored 935/1000. it has all the exam dumps and important info.
good questions
well explained
i got the full version and it helped me pass the exam. pdf version is very good.
provide the download link, please
please upload thank.
please can you share 1z0-1055-22 dump pls
i will wait impatiently. thank youu
is it possible to clear the exam if we focus on only these 156 questions instead of 623 questions? kindly help!
really helped with preparation of my scrum exam
very informative and through explanations
prep for exam
thanks for helping us
i prepared for the eccouncil 350-401 exam. i scored 92% on the test.
aba questions to practice
Keeping this site free takes real effort. We constantly battle automated scraping and unauthorized content copying. A quick account helps us protect the community and keep the site free.
To continue studying for your AACE-PSP, please sign in or create a free account.