US Green Building Council LEED-AP-BD-C Exam (page: 6)
US Green Building Council LEED AP Building Design + Construction
Updated on: 15-Feb-2026

Viewing Page 6 of 62

A newly constructed school has installed solar thermal systems and wind turbines on site. To achieve the maximum number of Energy and Atmosphere points, which team members must be included?

  1. Energy Modeler and Contractor
  2. Construction Manager and Energy Modeler
  3. Energy Modeler and Commissioning (Cx) Agent
  4. Commissioning (Cx) Agent and Facilities Manager

Answer(s): C

Explanation:

To achieve the maximum number of Energy and Atmosphere points, the project team must include an energy modeler and a commissioning agent. The energy modeler is responsible for performing the whole-building energy simulation that demonstrates the energy performance improvement over the baseline building, which is required for Energy and Atmosphere Prerequisite 2 and Credit 11. The commissioning agent is responsible for verifying that the building's energy systems are installed, calibrated, and perform according to the owner's project requirements, basis of design, and construction documents, which is required for Energy and Atmosphere Prerequisite 1 and Credit 31. The commissioning agent also ensures that the renewable energy systems are properly integrated and functioning. The contractor and the construction manager are not directly involved in the energy modeling or commissioning process, although they must follow the design specifications and coordinate with the commissioning agent. The facilities manager is not required for achieving the Energy and Atmosphere points, although they may benefit from the training and documentation provided by the commissioning agent.


Reference:

LEED v4 for Building Design and Construction, p. 361
Understanding Integrative Design in LEED v4, p. 92



When using the Integrative Process, what is the best way for the LEED AP to assess the impact of indoor and outdoor water consumption in a Building Design and Construction project?

  1. Perform a preliminary water budget analysis before the completion of schematic design
  2. Install permanent metering on both the water sources and the waste water leaving the site
  3. At the completion of schematic design, count the fixtures and apply the maximum flow rate
  4. Estimate consumption by using 20 gal. per day (76 I per day) for each Full Time Equivalent (FTE) scheduled to occupy the building

Answer(s): A

Explanation:

When using the Integrative Process, the best way for the LEED AP to assess the impact of indoor and outdoor water consumption in a Building Design and Construction project is to perform a preliminary water budget analysis before the completion of schematic design. This analysis should include the following steps1:
Identify the project's water sources and uses, such as potable water, reclaimed water, rainwater, graywater, blackwater, irrigation, cooling towers, etc. Estimate the baseline water consumption for each use based on the applicable codes, standards, and benchmarks.
Identify potential water conservation strategies that can reduce the demand or increase the supply of water, such as low-flow fixtures, native landscaping, rainwater harvesting, graywater reuse, etc. Evaluate the feasibility, cost-effectiveness, and environmental benefits of each strategy using a life- cycle approach.
Select the most appropriate strategies and document how they inform the design decisions and meet the project goals.
Compare the projected water consumption with the baseline and calculate the percentage reduction.
Performing a preliminary water budget analysis before the completion of schematic design allows the LEED AP to identify opportunities for water efficiency and innovation early in the design process. It also helps to optimize the integration of water systems with other building and site systems, such as energy, materials, indoor environmental quality, etc. Moreover, it supports the achievement of other LEED credits related to water efficiency, such as WE Prerequisite 1: Outdoor Water Use Reduction, WE Prerequisite 2: Indoor Water Use Reduction, WE Credit 1: Outdoor Water Use Reduction, WE Credit 2: Indoor Water Use Reduction, WE Credit 3: Cooling Tower Water Use.


Reference:

Understanding Integrative Design in LEED v41
LEED v4 for Building Design and Construction2



In the step-by-step guidance for Location and Transportation Credit, Bicycle Facilities, which of the following requirements can define a bicycle network?

  1. One-way streets
  2. Bike share
  3. Slow speed roadways
  4. Traffic lights

Answer(s): C

Explanation:

According to the LEED Reference Guide for Building Design and Construction1, the Location and Transportation Credit, Bicycle Facilities, requires the project to provide short-term and long-term bicycle storage and a functional entry or bicycle storage within 200 yards of a bicycle network. The bicycle network is defined as any one of the following:
Off-street bicycle paths or on-street bicycle lanes that are physically marked and separated from motor traffic
Streets designed for a target speed of 25 mph (40 km/h) or less, with traffic calming features such as curb extensions, speed humps, raised crossings, narrowed traffic lanes, median islands, tight corner radii, roundabouts, or landscaping
Streets with a legal speed limit of 25 mph (40 km/h) or less that connect to a larger bicycle network Therefore, among the given options, only slow speed roadways can define a bicycle network, as they can provide a safer and more comfortable environment for cyclists. One-way streets, bike share, and traffic lights are not sufficient to define a bicycle network, as they do not necessarily indicate the presence of bicycle paths, lanes, or low-speed streets.


Reference:

LEED Reference Guide for Building Design and Construction v4 Bicycle facilities | U.S. Green Building Council
CI-v4.1 LTc4: Bicycle facilities | LEEDuser
Understanding bikeability: a methodology to assess urban networks Bicycle Network | Making bike riding easier for everyone



Which approach will contribute to maintaining compliance with Sustainable Sites Credit, Rainwater Management?

  1. Installing bioretention area
  2. Installing on-site renewable power generation facility
  3. Substituting impervious surface area with high-albedo paving materials
  4. Increase artificial turf on the roof

Answer(s): A

Explanation:

Installing a bioretention area is an example of a low-impact development (LID) practice that can reduce runoff volume and improve water quality by replicating the natural hydrology and water balance of the site. This approach will contribute to maintaining compliance with Sustainable Sites Credit, Rainwater Management, which requires designing the site to retain the runoff from the developed site for at least the 80th percentile of rainfall events.


Reference:

Credit: Rainwater management | U.S. Green Building Council Achieving SSc Rainwater Management in LEED v4.1



Which of the following strategies would be considered an acceptable minor improvement within the wetland buffer for Location and Transportation Credit, Sensitive Land Protection?

  1. Build a two-story fitness facility
  2. Change the grade to install a security fence
  3. Provide a vehicular access drive that is less than 16 ft. (5 m) in width
  4. Remove trees that are less than 6 inches (15.24 cm) diameter at breast height

Answer(s): C

Explanation:

Providing a vehicular access drive that is less than 16 ft. (5 m) in width is considered an acceptable minor improvement within the wetland buffer for Location and Transportation Credit, Sensitive Land Protection. This credit requires avoiding development on land that meets one or more of the following criteria: prime farmland, floodplains, threatened or endangered species habitat, water bodies, wetlands, or land within 100 feet (30 meters) of these water bodies or wetlands. However, the credit allows minor improvements within the wetland buffer if they are necessary for the project and have minimal environmental impact. Examples of minor improvements include trails, boardwalks, stormwater outfalls, and utility crossings.


Reference:

Credit: Sensitive land protection | U.S. Green Building Council NC-v4.1 LTc2: Sensitive land protection | LEEDuser



Viewing Page 6 of 62



Share your comments for US Green Building Council LEED-AP-BD-C exam with other users:

Van 11/24/2023 4:02:00 AM

good for practice
Anonymous


Divya 8/2/2023 6:54:00 AM

need more q&a to go ahead
Anonymous


Rakesh 10/6/2023 3:06:00 AM

question 59 - a newly-created role is not assigned to any user, nor granted to any other role. answer is b https://docs.snowflake.com/en/user-guide/security-access-control-overview
Anonymous


Nik 11/10/2023 4:57:00 AM

just passed my exam today. i saw all of these questions in my text today. so i can confirm this is a valid dump.
HONG KONG


Deep 6/12/2023 7:22:00 AM

needed dumps
INDIA


tumz 1/16/2024 10:30:00 AM

very helpful
UNITED STATES


NRI 8/27/2023 10:05:00 AM

will post once the exam is finished
UNITED STATES


kent 11/3/2023 10:45:00 AM

relevant questions
Anonymous


Qasim 6/11/2022 9:43:00 AM

just clear exam on 10/06/2202 dumps is valid all questions are came same in dumps only 2 new questions total 46 questions 1 case study with 5 question no lab/simulation in my exam please check the answers best of luck
Anonymous


Cath 10/10/2023 10:09:00 AM

q.112 - correct answer is c - the event registry is a module that provides event definitions. answer a - not correct as it is the definition of event log
VIET NAM


Shiji 10/15/2023 1:31:00 PM

good and useful.
INDIA


Ade 6/25/2023 1:14:00 PM

good questions
Anonymous


Praveen P 11/8/2023 5:18:00 AM

good content
UNITED STATES


Anastasiia 12/28/2023 9:06:00 AM

totally not correct answers. 21. you have one gcp account running in your default region and zone and another account running in a non-default region and zone. you want to start a new compute engine instance in these two google cloud platform accounts using the command line interface. what should you do? correct: create two configurations using gcloud config configurations create [name]. run gcloud config configurations activate [name] to switch between accounts when running the commands to start the compute engine instances.
Anonymous


Priyanka 7/24/2023 2:26:00 AM

kindly upload the dumps
Anonymous


Nabeel 7/25/2023 4:11:00 PM

still learning
Anonymous


gure 7/26/2023 5:10:00 PM

excellent way to learn
UNITED STATES


ciken 8/24/2023 2:55:00 PM

help so much
Anonymous


Biswa 11/20/2023 9:28:00 AM

understand sql col.
Anonymous


Saint Pierre 10/24/2023 6:21:00 AM

i would give 5 stars to this website as i studied for az-800 exam from here. it has all the relevant material available for preparation. i got 890/1000 on the test.
Anonymous


Rose 7/24/2023 2:16:00 PM

this is nice.
Anonymous


anon 10/15/2023 12:21:00 PM

q55- the ridac workflow can be modified using flow designer, correct answer is d not a
UNITED STATES


NanoTek3 6/13/2022 10:44:00 PM

by far this is the most accurate exam dumps i have ever purchased. all questions are in the exam. i saw almost 90% of the questions word by word.
UNITED STATES


eriy 11/9/2023 5:12:00 AM

i cleared the az-104 exam by scoring 930/1000 on the exam. it was all possible due to this platform as it provides premium quality service. thank you!
UNITED STATES


Muhammad Rawish Siddiqui 12/8/2023 8:12:00 PM

question # 232: accessibility, privacy, and innovation are not data quality dimensions.
SAUDI ARABIA


Venkat 12/27/2023 9:04:00 AM

looks wrong answer for 443 question, please check and update
Anonymous


Varun 10/29/2023 9:11:00 PM

great question
Anonymous


Doc 10/29/2023 9:36:00 PM

question: a user wants to start a recruiting posting job posting. what must occur before the posting process can begin? 3 ans: comment- option e is incorrect reason: as part of enablement steps, sap recommends that to be able to post jobs to a job board, a user need to have the correct permission and secondly, be associated with one posting profile at minimum
UNITED KINGDOM


It‘s not A 9/17/2023 5:31:00 PM

answer to question 72 is d [sys_user_role]
Anonymous


indira m 8/14/2023 12:15:00 PM

please provide the pdf
UNITED STATES


ribrahim 8/1/2023 6:05:00 AM

hey guys, just to let you all know that i cleared my 312-38 today within 1 hr with 100 questions and passed. thank you so much brain-dumps.net all the questions that ive studied in this dump came out exactly the same word for word "verbatim". you rock brain-dumps.net!!! section name total score gained score network perimeter protection 16 11 incident response 10 8 enterprise virtual, cloud, and wireless network protection 12 8 application and data protection 13 10 network défense management 10 9 endpoint protection 15 12 incident d
SINGAPORE


Andrew 8/23/2023 6:02:00 PM

very helpful
Anonymous


latha 9/7/2023 8:14:00 AM

useful questions
GERMANY


ibrahim 11/9/2023 7:57:00 AM

page :20 https://exam-dumps.com/snowflake/free-cof-c02-braindumps.html?p=20#collapse_453 q 74: true or false: pipes can be suspended and resumed. true. desc.: pausing or resuming pipes in addition to the pipe owner, a role that has the following minimum permissions can pause or resume the pipe https://docs.snowflake.com/en/user-guide/data-load-snowpipe-intro
FINLAND