Risk is configured by default, to calculate Risk = High for a change that is scheduled with only 3 days lead time. Your customer’s change policy requires that changes be requested with 5 days lead time.
How would you satisfy this requirement?
- Update the Risk Property for Insufficient lead time
- Update the Risk Assessment Matrix for Insufficient lead time
- Update the Calculate Risk UI Action
- Update the Risk Matrix for insufficient lead time
- Update the Risk Condition for Insufficient lead time