Which of the following are factors that need to be taken into consideration when identifying management stages?
1. Where the key decisions points need to be
2. The amount of risk within the project
3. The number of technical stages
4. How confident the Project Board and Project Manager are with proceeding

  1. 1, 2, 3
  2. 1, 2, 4
  3. 1, 3, 4
  4. 2, 3, 4

Answer(s): B



The creation of an Exception Plan often follows which of the following situations?

  1. A time or cost slippage occurring during a management stage
  2. An Exception Report being submitted to the Project Board in the case of a management stage being forecast to exceed its tolerance
  3. A Stage Plan updated due to an urgent corrective action being taken by the Project Manager
  4. A newly identified risk being captured and documented in the Risk Register

Answer(s): B



What type of progress control is a Checkpoint Report?

  1. Event-driven
  2. Exception-based
  3. Time-driven
  4. Ad hoc-based

Answer(s): C



Which of the following is NOT within the authority of the Project Board?

  1. Approve the End Project Report
  2. Set Stage-level tolerance
  3. Approve Stage Plans
  4. Set project-level tolerance

Answer(s): D



Which of the following is a Project Board control?

  1. Project-level tolerance
  2. Stage-level tolerance
  3. Checkpoint Report
  4. Quality Register

Answer(s): B



Which level of management in the project management team has the ability to review progress and decide whether to continue, change or stop the project?

  1. Project Manager
  2. Project Board
  3. Team Manager
  4. Corporate or programme management

Answer(s): B



There should be at least two management stages in a PRINCE2 project. Which of the following options describes those stages?

  1. Initiation as the first stage, the remainder of the project as the second stage
  2. Initiation as the first stage, closure activities as the second stage
  3. Procurement as the first stage, design and implementation as the second stage
  4. Pre-project work as the first stage, initiation as the second stage

Answer(s): A



Please refer to section 10.3.2.1 in the PRINCE2 Manual. (Exception Plans are only produced if requested by the Project Board. Team Plans and the use of seperate people as Team Managers are optional in PRINCE2)

  1. Use of Team Managers
  2. Use of management stages
  3. Use of Exception Plans
  4. Use of Team Plans

Answer(s): B



Share your comments for PRINCE2 PRINCE2 Foundation exam with other users:

M
Meg
10/12/2023 8:02:00 AM

q 105 . ans is d

N
Navaneeth S
7/14/2023 7:57:00 AM

i have interest to get a sybase iq dba certification

A
Aish
10/11/2023 5:27:00 AM

want to pass exm.

A
Anonymous
6/12/2023 7:23:00 AM

are the answers correct?

K
Kris
7/7/2023 9:43:00 AM

good morning, could you please upload this exam again, i need it to test my knowledge in sd-wan with version 7.0.

M
Meghraj mali
10/7/2023 1:47:00 PM

very nice question

N
Noel
11/1/2022 9:14:00 PM

i have learning disability and this exam dumps allowed me to focus on the actual questions and not worry about notes and the those other study materials.

J
Jas
10/25/2023 6:01:00 PM

165 should be apt

N
Neetu
6/22/2023 8:41:00 AM

please upload the dumps, real need of them

M
Mark
10/24/2023 1:34:00 AM

any recent feeedback?

G
Gopinadh
8/9/2023 4:05:00 AM

question number 2 is indicating you are giving proper questions. observe and change properly.

S
Santhi
1/1/2024 8:23:00 AM

passed today.40% questions were new.litwere case study,lots of new questions on afd,ratelimit,tm,lb,app gatway.got 2 set series of questions which are not present here.questions on azure cyclecloud, no.of vnet/vms required for implimentation,blueprints assignment/management group etc

R
Raviraj Magadum
1/12/2024 11:39:00 AM

practice test

S
sivaramakrishnan
7/27/2023 8:12:00 AM

want the dumps for emc content management server programming(cmsp)

A
Aderonke
10/23/2023 1:52:00 PM

brilliant and helpful

A
Az
9/16/2023 2:43:00 PM

q75. azure files is pass

K
ketty
11/9/2023 8:10:00 AM

very helpful

S
Sonail
5/2/2022 1:36:00 PM

thank you for these questions. it helped a lot.

S
Shariq
7/28/2023 8:00:00 AM

how do i get the h12-724 dumps

A
adi
10/30/2023 11:51:00 PM

nice data dumps

E
EDITH NCUBE
7/25/2023 7:28:00 AM

answers are correct

R
Raja
6/20/2023 4:38:00 AM

good explanation

B
BigMouthDog
1/22/2022 8:17:00 PM

hi team just want to know if there is any update version of the exam 350-401

F
francesco
10/30/2023 11:08:00 AM

helpful on 2017 scrum guide

A
Amitabha Roy
10/5/2023 3:16:00 AM

planning to attempt for the exam.

P
Prem Yadav
7/29/2023 6:20:00 AM

pleaseee upload

A
Ahmed Hashi
7/6/2023 5:40:00 PM

thanks ly so i have information cia

M
mansi
5/31/2023 7:58:00 AM

hello team, i need sap qm dumps for practice

J
Jamil aljamil
12/4/2023 4:47:00 AM

it’s good but not senatios based

C
Cath
10/10/2023 10:19:00 AM

q.119 - the correct answer is b - they are not captured in an update set as theyre data.

P
P
1/6/2024 11:22:00 AM

good matter

S
surya
7/30/2023 2:02:00 PM

please upload c_sacp_2308

S
Sasuke
7/11/2023 10:30:00 PM

please upload the dump. thanks very much !!

V
V
7/4/2023 8:57:00 AM

good questions

AI Tutor 👋 I’m here to help!