PRINCE2 PRINCE2 Foundation Exam (page: 12)
PRINCE2 Foundation 7 Edition
Updated on: 25-Dec-2025

Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?

  1. Executive
  2. Senior User
  3. Senior Supplier
  4. Project Manager

Answer(s): B

Explanation:

The Senior User within the PRINCE2 project management team represents the interests of those who will use the project's products and benefit from their operation after the project is complete. This role is responsible for specifying the needs of users, ensuring the solution meets these needs, and is capable of delivering the anticipated benefits.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



What product is used to maintain a record of those who have an interest in the project and their information requirements?

  1. Project Plan
  2. Communication Management Strategy
  3. Project Brief
  4. Project Product Description

Answer(s): B

Explanation:

The Communication Management Strategy is used in PRINCE2 to maintain a record of stakeholders who have an interest in the project and their information requirements. This document outlines how and when stakeholders will be kept informed about the project's progress and any issues that may arise.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.

  1. quality
  2. supplier
  3. risk
  4. product

Answer(s): A

Explanation:

A member of the Project Board is responsible for quality assurance in PRINCE2. Quality assurance is concerned with ensuring that the project's products meet the quality requirements set out in the project and that the project adheres to the appropriate corporate, programme management, or customer quality standards.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



How many roles make up the Project Board?

  1. One
  2. Two
  3. Three
  4. Four

Answer(s): C

Explanation:

The Project Board within the PRINCE2® framework is made up of three key roles: the Executive, the Senior User, and the Senior Supplier. These roles represent the business, user, and supplier interests respectively, ensuring that the project's decision-making is balanced across these three perspectives.


Reference:

PRINCE2® Foundation official documentation and study materials.



Which of the following statements about stakeholders are true?

1. Someone who thinks they will be affected by a project is a stakeholder on that project.
2. Stakeholders may be internal or external to the corporate organization.

  1. Only 1 is true
  2. Only 2 is true
  3. Both 1 and 2 are true
  4. Neither 1 or 2 are true

Answer(s): C

Explanation:

Both statements about stakeholders are true in the context of PRINCE2®. A stakeholder in a project includes anyone who thinks they will be affected by the project, which can include both supporters and those who may oppose the project. Additionally, stakeholders can be both internal and external to the organization that is undertaking the project.


Reference:

PRINCE2® Foundation official documentation and study materials.



Viewing Page 12 of 94



Share your comments for PRINCE2 PRINCE2 Foundation exam with other users:

Ade 6/25/2023 1:14:00 PM

good questions
Anonymous


Praveen P 11/8/2023 5:18:00 AM

good content
UNITED STATES


Anastasiia 12/28/2023 9:06:00 AM

totally not correct answers. 21. you have one gcp account running in your default region and zone and another account running in a non-default region and zone. you want to start a new compute engine instance in these two google cloud platform accounts using the command line interface. what should you do? correct: create two configurations using gcloud config configurations create [name]. run gcloud config configurations activate [name] to switch between accounts when running the commands to start the compute engine instances.
Anonymous


Priyanka 7/24/2023 2:26:00 AM

kindly upload the dumps
Anonymous


Nabeel 7/25/2023 4:11:00 PM

still learning
Anonymous


gure 7/26/2023 5:10:00 PM

excellent way to learn
UNITED STATES


ciken 8/24/2023 2:55:00 PM

help so much
Anonymous


Biswa 11/20/2023 9:28:00 AM

understand sql col.
Anonymous


Saint Pierre 10/24/2023 6:21:00 AM

i would give 5 stars to this website as i studied for az-800 exam from here. it has all the relevant material available for preparation. i got 890/1000 on the test.
Anonymous


Rose 7/24/2023 2:16:00 PM

this is nice.
Anonymous


anon 10/15/2023 12:21:00 PM

q55- the ridac workflow can be modified using flow designer, correct answer is d not a
UNITED STATES


NanoTek3 6/13/2022 10:44:00 PM

by far this is the most accurate exam dumps i have ever purchased. all questions are in the exam. i saw almost 90% of the questions word by word.
UNITED STATES


eriy 11/9/2023 5:12:00 AM

i cleared the az-104 exam by scoring 930/1000 on the exam. it was all possible due to this platform as it provides premium quality service. thank you!
UNITED STATES


Muhammad Rawish Siddiqui 12/8/2023 8:12:00 PM

question # 232: accessibility, privacy, and innovation are not data quality dimensions.
SAUDI ARABIA


Venkat 12/27/2023 9:04:00 AM

looks wrong answer for 443 question, please check and update
Anonymous


Varun 10/29/2023 9:11:00 PM

great question
Anonymous


Doc 10/29/2023 9:36:00 PM

question: a user wants to start a recruiting posting job posting. what must occur before the posting process can begin? 3 ans: comment- option e is incorrect reason: as part of enablement steps, sap recommends that to be able to post jobs to a job board, a user need to have the correct permission and secondly, be associated with one posting profile at minimum
UNITED KINGDOM


It‘s not A 9/17/2023 5:31:00 PM

answer to question 72 is d [sys_user_role]
Anonymous


indira m 8/14/2023 12:15:00 PM

please provide the pdf
UNITED STATES


ribrahim 8/1/2023 6:05:00 AM

hey guys, just to let you all know that i cleared my 312-38 today within 1 hr with 100 questions and passed. thank you so much brain-dumps.net all the questions that ive studied in this dump came out exactly the same word for word "verbatim". you rock brain-dumps.net!!! section name total score gained score network perimeter protection 16 11 incident response 10 8 enterprise virtual, cloud, and wireless network protection 12 8 application and data protection 13 10 network défense management 10 9 endpoint protection 15 12 incident d
SINGAPORE


Andrew 8/23/2023 6:02:00 PM

very helpful
Anonymous


latha 9/7/2023 8:14:00 AM

useful questions
GERMANY


ibrahim 11/9/2023 7:57:00 AM

page :20 https://exam-dumps.com/snowflake/free-cof-c02-braindumps.html?p=20#collapse_453 q 74: true or false: pipes can be suspended and resumed. true. desc.: pausing or resuming pipes in addition to the pipe owner, a role that has the following minimum permissions can pause or resume the pipe https://docs.snowflake.com/en/user-guide/data-load-snowpipe-intro
FINLAND


Franklin Allagoa 7/5/2023 5:16:00 AM

i want hcia exam dumps
Anonymous


SSA 12/24/2023 1:18:00 PM

good training
Anonymous


BK 8/11/2023 12:23:00 PM

very useful
INDIA


Deepika Narayanan 7/13/2023 11:05:00 PM

yes need this exam dumps
Anonymous


Blessious Phiri 8/15/2023 3:31:00 PM

these questions are a great eye opener
Anonymous


Jagdesh 9/8/2023 8:17:00 AM

thank you for providing these questions and answers. they helped me pass my exam. you guys are great.
CANADA


TS 7/18/2023 3:32:00 PM

good knowledge
Anonymous


Asad Khan 11/1/2023 2:44:00 AM

answer 10 should be a because only a new project will be created & the organization is the same.
Anonymous


Raj 9/12/2023 3:49:00 PM

can you please upload the dump again
UNITED STATES


Christian Klein 6/23/2023 1:32:00 PM

is it legit questions from sap certifications ?
UNITED STATES


anonymous 1/12/2024 3:34:00 PM

question 16 should be b (changing the connector settings on the monitor) pc and monitor were powered on. the lights on the pc are on indicating power. the monitor is showing an error text indicating that it is receiving power too. this is a clear sign of having the wrong input selected on the monitor. thus, the "connector setting" needs to be switched from hdmi to display port on the monitor so it receives the signal from the pc, or the other way around (display port to hdmi).
UNITED STATES