What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

  1. Directing a Project
  2. Managing a Stage Boundary
  3. Controlling a Stage
  4. Starting up a Project

Answer(s): C

Explanation:

The Controlling a Stage process in PRINCE2 ensures focus on the delivery of a stage's products while managing and controlling any potential deviations or issues. This process helps in avoiding uncontrolled changes and maintains the project's focus on its objectives by providing regular monitoring and control.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Which process is triggered towards the end of the final stage when all the assigned work has been completed?

  1. Managing a Stage Boundary
  2. Managing Product Delivery
  3. Closing a Project
  4. Controlling a Stage

Answer(s): C

Explanation:

The Closing a Project process in PRINCE2 is triggered towards the end of the final stage when all assigned work has been completed. This process is designed to ensure that all project objectives have been achieved, all products have been delivered, and the project can be formally closed and evaluated for success and areas of improvement.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Which is a purpose of the Controlling a Stage process?

  1. Assign work to be done and take corrective action to ensure that the stage remains within tolerance
  2. Provide a fixed reference point at which acceptance for the project product is confirmed
  3. Enable the Project Board to be provided with sufficient information to authorize the next stage
  4. Enable the organization to understand the work that needs to be done to deliver the project's products

Answer(s): A

Explanation:

The purpose of the Controlling a Stage process in PRINCE2® is to monitor and control a stage within its authorized tolerances. During this process, the Project Manager assigns work, monitors work progress, deals with issues, reports stage status to the Project Board, and takes necessary corrective actions to stay within the stage's tolerances.


Reference:

PRINCE2® Foundation official documentation and study materials.



What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

  1. Directing a Project
  2. Controlling a Stage
  3. Managing a Stage Boundary
  4. Managing Product Delivery

Answer(s): B

Explanation:

The Controlling a Stage process is used by the Project Manager to maintain focus on the delivery of the stage's products within the agreed tolerances. This involves assigning work, monitoring such work, managing issues and risks, and ensuring that the stage remains on track in terms of time, cost, quality, scope, risk, and benefit performance.


Reference:

PRINCE2® Foundation official documentation and study materials.



In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?

  1. Product Description
  2. Team Plan
  3. Work Package
  4. Stage Plan

Answer(s): C

Explanation:

In PRINCE2®, a Work Package is the document where the Project Manager defines the time and cost tolerances for the work assigned to a Team Manager. The Work Package provides detailed information on the products to be delivered, the reporting requirements, and the tolerances within which the Team Manager operates.


Reference:

PRINCE2® Foundation official documentation and study materials.



Which is a purpose of the Directing a Project process?

  1. Create and authorize the project mandate
  2. Ensure that work on products allocated to the team is authorized and agreed
  3. Control the day-to-day running of the project
  4. Delegate day-to-day management of the project to the Project Manager

Answer(s): D

Explanation:

The purpose of the Directing a Project process is for the Project Board to delegate the day-to-day management of the project to the Project Manager, providing the overall direction and management of the project lifecycle. This process is critical for enabling the Project Manager to run the project on behalf of the Project Board within the constraints set out by them.


Reference:

PRINCE2® Foundation official documentation and study materials.



Which is a purpose of the Directing a Project process?

  1. Provide the information required to confirm if it is worthwhile to initiate a project
  2. Enable overall control of a project to be exercised by the Project Board
  3. Establish the level of control required by the Project Board after initiation.
  4. Provide sufficient information so that the current stage can be reviewed and the next Stage Plan approved

Answer(s): B

Explanation:

The purpose of the Directing a Project process in PRINCE2 is to enable the Project Board to exercise overall control over the project while delegating day-to-day management of the project stages to the Project Manager. This ensures that the Project Board can make key decisions and remain accountable for the project's success while not being involved in the lower-level, day-to-day activities.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Which is an objective of the Directing a Project process?

  1. Create and authorize the project mandate
  2. Provide management control and direction
  3. Control the day-to-day running of the project
  4. Provide accurate progress information to the Project Manager

Answer(s): B

Explanation:

An objective of the Directing a Project process is to provide management control and direction for the project. This involves making strategic decisions, providing overall guidance to the Project Manager, and ensuring the project remains aligned with organizational objectives and capable of delivering the benefits defined in the Business Case.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Share your comments for PRINCE2 PRINCE2-7-Foundation exam with other users:

T
Tanvi Rajput
10/6/2023 6:50:00 AM

question 11: d i personally feel some answers are wrong.

A
Anil
7/18/2023 9:38:00 AM

nice questions

C
Chris
8/26/2023 1:10:00 AM

looking for c1000-158: ibm cloud technical advocate v4 questions

S
sachin
6/27/2023 1:22:00 PM

can you share the pdf

B
Blessious Phiri
8/13/2023 10:26:00 AM

admin ii is real technical stuff

L
Luis Manuel
7/13/2023 9:30:00 PM

could you post the link

V
vijendra
8/18/2023 7:54:00 AM

hello send me dumps

S
Simeneh
7/9/2023 8:46:00 AM

it is very nice

J
john
11/16/2023 5:13:00 PM

i gave the amazon dva-c02 tests today and passed. very helpful.

T
Tao
11/20/2023 8:53:00 AM

there is an incorrect word in the problem statement. for example, in question 1, there is the word "speci c". this is "specific. in the other question, there is the word "noti cation". this is "notification. these mistakes make this site difficult for me to use.

P
patricks
10/24/2023 6:02:00 AM

passed my az-120 certification exam today with 90% marks. studied using the dumps highly recommended to all.

A
Ananya
9/14/2023 5:17:00 AM

i need it, plz make it available

J
JM
12/19/2023 2:41:00 PM

q47: intrusion prevention system is the correct answer, not patch management. by definition, there are no patches available for a zero-day vulnerability. the way to prevent an attacker from exploiting a zero-day vulnerability is to use an ips.

R
Ronke
8/18/2023 10:39:00 AM

this is simple but tiugh as well

C
CesarPA
7/12/2023 10:36:00 PM

questão 4, segundo meu compilador local e o site https://www.jdoodle.com/online-java-compiler/, a resposta correta é "c" !

J
Jeya
9/13/2023 7:50:00 AM

its very useful

T
Tracy
10/24/2023 6:28:00 AM

i mastered my skills and aced the comptia 220-1102 exam with a score of 920/1000. i give the credit to for my success.

J
James
8/17/2023 4:33:00 PM

real questions

A
Aderonke
10/23/2023 1:07:00 PM

very helpful assessments

S
Simmi
8/24/2023 7:25:00 AM

hi there, i would like to get dumps for this exam

J
johnson
10/24/2023 5:47:00 AM

i studied for the microsoft azure az-204 exam through it has 100% real questions available for practice along with various mock tests. i scored 900/1000.

M
Manas
9/9/2023 1:48:00 AM

please upload 1z0-1072-23 exam dups

S
SB
9/12/2023 5:15:00 AM

i was hoping if you could please share the pdf as i’m currently preparing to give the exam.

J
Jagjit
8/26/2023 5:01:00 PM

i am looking for oracle 1z0-116 exam

S
S Mallik
11/27/2023 12:32:00 AM

where we can get the answer to the questions

P
PiPi Li
12/12/2023 8:32:00 PM

nice questions

D
Dan
8/10/2023 4:19:00 PM

question 129 is completely wrong.

G
gayathiri
7/6/2023 12:10:00 AM

i need dump

D
Deb
8/15/2023 8:28:00 PM

love the site.

M
Michelle
6/23/2023 4:08:00 AM

can you please upload it back?

A
Ajay
10/3/2023 12:17:00 PM

could you please re-upload this exam? thanks a lot!

H
him
9/30/2023 2:38:00 AM

great about shared quiz

S
San
11/14/2023 12:46:00 AM

goood helping

W
Wang
6/9/2022 10:05:00 PM

pay attention to questions. they are very tricky. i waould say about 80 to 85% of the questions are in this exam dump.

AI Tutor 👋 I’m here to help!