Which is a typical core activity within configuration management?
Answer(s): C
Identification is one of the core activities within configuration management in the PRINCE2 methodology. This activity entails defining and identifying the configuration items within a project, documenting their relationships and characteristics, and ensuring that each product's unique identity is maintained throughout the project.
PRINCE2 Foundation Training Manual, PRINCE2 official website
What needs to be in place to ensure effective issue and change control?
Answer(s): A
Effective issue and change control within a PRINCE2® project relies heavily on a configuration management system. This system tracks all items of the project, including their versions and changes, allowing for controlled changes and ensuring that all items are identified, accounted for, and monitored throughout the project.
PRINCE2® Foundation official study guide and online resources.
Which should be funded by a change budget?
The change budget in a PRINCE2® project is designed to fund changes that involve an increase in the agreed scope of the project. Such changes typically require additional budget allocations as they extend or modify what the project initially planned to deliver.
Which should be funded from a change budget?
Similar to the answer to question 11, the change budget is specifically allocated for changes that are agreed upon that modify the scope of the project. This ensures that any scope modifications are funded without compromising the existing budget for planned deliverables.
Which is the Issue Register NOT used for?
The Issue Register in PRINCE2® is used to capture and record all issues that may affect the project but it is not designed to capture external events unless they become issues directly impacting project deliverables or processes. Its primary function is to log problems identified in project execution, not general external events.
If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
When the Project Board instructs the Project Manager to implement a request for change, details of that change are contained in an Issue Report. This document provides a detailed description of the issue, its evaluation, and the decisions regarding its resolution, including any changes to be implemented.
PRINCE2® Foundation official study guide and online resources. These answers are based on the latest materials and guidelines from the PRINCE2® Foundation documentation and should reflect the most current practices and theoretical underpinnings of the methodology.
Which is the purpose of the Change theme?
Answer(s): B
The purpose of the Change theme in PRINCE2 is to establish a clear, structured approach for identifying, assessing, and controlling changes to baselined products. This theme ensures that only approved changes are implemented, helping to manage and minimize their potential impacts on the project's objectives.
PRINCE2 Foundation manual, PRINCE2 official resources
Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?
In the issue and change control procedure within PRINCE2, the "Examine" step involves considering alternative options to address an issue that is being managed formally. This step is crucial for evaluating the possible responses to an issue before making a decision on the best course of action.
Share your comments for PRINCE2 PRINCE2-7-Foundation exam with other users:
good material
lets see if this is good stuff...
useful information
intéressant
thank you for making the interactive questions
questions are accurate
i need questions/dumps for this exam.
i need this exam, when will it be uploaded
i need the dumps !
very helpful
good source
my 3rd test and passed on first try. hats off to this brain dumps site.
please upload it
does anybody know if are these real exam questions?
are these questions similar to actual questions in the exam? because they seem to be too easy
i have a lot of experience but what comes in the exam is totally different from the practical day to day tasks. so i thought i would rather rely on these brain dumps rather failing the exam.
good questions
valied exam dumps. they were very helpful and i got a pretty good score. i am very grateful for this service and exam questions
will it help?
very useful to verify knowledge before exam
good stuffs
question 17 : responses arent b and c ?
just passed the exam on my first try using these dumps.
these questions look good.
this is very helpful content
please provide the dumps
it is amazing
quesion 178 about "a banking system that predicts whether a loan will be repaid is an example of the" the answer is classification. not regresion, you should fix it.
please upload apache spark dumps
q14 is b&c to reduce you will switch off mail for every single alert and you will switch on daily digest to get a mail once per day, you might even skip the empty digest mail but i see this as a part of the daily digest adjustment
i think it is good question
good for students who wish to give certification.
is there a google drive link to the images? the links in questions are not working.