You are working with Anna on your project to determine and map the probability distributions of

risk within the project. You have indicated that you will use the uniform distribution method for a portion of the project. Which part of your project is most likely to have a uniform risk distribution?

  1. Late completion stages of a project
  2. Project phases that deal with "cutover" technologies
  3. Early concept stage of design
  4. Project initiating

Answer(s): C



You are the project manager of the GYH project for your organization. Management has asked you to begin identifying risks and to use an information gathering technique. Which one of the following risk identification approaches is an information gathering technique?

  1. Root cause analysis
  2. Assumptions analysis
  3. SWOT analysis
  4. Documentation reviews

Answer(s): A



Sammy is the project manager for her organization. She would like to rate each risk based on its probability and affect on time, cost, and scope. Harry, a project team member, has never done this before and thinks Sammy is wrong to attempt this approach. Harry says that an accumulative risk score should be created, not three separate risk scores. Who is correct in this scenario?

  1. Harry is correct, because the risk probability and impact considers all objectives of the project.
  2. Harry is correct, the risk probability and impact matrix is the only approach to risk assessment.
  3. Sammy is correct, because organizations can create risk scores for each objective of the project.
  4. Sammy is correct, because she is the project manager.

Answer(s): C



Your organization has named you the project manager of the JKN Project. This project has a BAC of $1,500,000 and it is expected to last 18 months. Management has agreed that if the schedule baseline has a variance of more than five percent then you will need to crash the project. What happens when the project manager crashes a project?

  1. Project risks will increase.
  2. The project will take longer to complete, but risks will diminish.
  3. Project costs will increase.
  4. The amount of hours a resource can be used will diminish.

Answer(s): C



Kelly is the project manager of the BHH project for her organization. She is completing the risk identification process for this portion of her project. Which one of the following is the only thing that the risk identification process will create for Kelly?

  1. Risk register
  2. Risk register updates
  3. Change requests
  4. Project document updates

Answer(s): A



Viewing Page 2 of 56



Share your comments for PMI PMI-RMP exam with other users:

H 7/17/2023 4:28:00 AM

could you please upload the exam?
Anonymous


Anonymous 9/14/2023 4:47:00 AM

please upload this
UNITED STATES


Naveena 1/13/2024 9:55:00 AM

good material
Anonymous


WildWilly 1/19/2024 10:43:00 AM

lets see if this is good stuff...
Anonymous


Lavanya 11/2/2023 1:53:00 AM

useful information
UNITED STATES


Moussa 12/12/2023 5:52:00 AM

intéressant
BURKINA FASO


Madan 6/22/2023 9:22:00 AM

thank you for making the interactive questions
Anonymous


Vavz 11/2/2023 6:51:00 AM

questions are accurate
Anonymous


Su 11/23/2023 4:34:00 AM

i need questions/dumps for this exam.
Anonymous


LuvSN 7/16/2023 11:19:00 AM

i need this exam, when will it be uploaded
ROMANIA


Mihai 7/19/2023 12:03:00 PM

i need the dumps !
Anonymous


Wafa 11/13/2023 3:06:00 AM

very helpful
Anonymous


Alokit 7/3/2023 2:13:00 PM

good source
Anonymous


Show-Stopper 7/27/2022 11:19:00 PM

my 3rd test and passed on first try. hats off to this brain dumps site.
UNITED STATES


Michelle 6/23/2023 4:06:00 AM

please upload it
Anonymous


Lele 11/20/2023 11:55:00 AM

does anybody know if are these real exam questions?
EUROPEAN UNION


Girish Jain 10/9/2023 12:01:00 PM

are these questions similar to actual questions in the exam? because they seem to be too easy
Anonymous


Phil 12/8/2022 11:16:00 PM

i have a lot of experience but what comes in the exam is totally different from the practical day to day tasks. so i thought i would rather rely on these brain dumps rather failing the exam.
GERMANY


BV 6/8/2023 4:35:00 AM

good questions
NETHERLANDS


krishna 12/19/2023 2:05:00 AM

valied exam dumps. they were very helpful and i got a pretty good score. i am very grateful for this service and exam questions
Anonymous


Pie 9/3/2023 4:56:00 AM

will it help?
INDIA


Lucio 10/6/2023 1:45:00 PM

very useful to verify knowledge before exam
POLAND


Ajay 5/17/2023 4:54:00 AM

good stuffs
Anonymous


TestPD1 8/10/2023 12:19:00 PM

question 17 : responses arent b and c ?
EUROPEAN UNION


Nhlanhla 12/13/2023 5:26:00 AM

just passed the exam on my first try using these dumps.
Anonymous


Rizwan 1/6/2024 2:18:00 AM

very helpful
INDIA


Yady 5/24/2023 10:40:00 PM

these questions look good.
SINGAPORE


Kettie 10/12/2023 1:18:00 AM

this is very helpful content
Anonymous


SB 7/21/2023 3:18:00 AM

please provide the dumps
UNITED STATES


David 8/2/2023 8:20:00 AM

it is amazing
Anonymous


User 8/3/2023 3:32:00 AM

quesion 178 about "a banking system that predicts whether a loan will be repaid is an example of the" the answer is classification. not regresion, you should fix it.
EUROPEAN UNION


quen 7/26/2023 10:39:00 AM

please upload apache spark dumps
Anonymous


Erineo 11/2/2023 5:34:00 PM

q14 is b&c to reduce you will switch off mail for every single alert and you will switch on daily digest to get a mail once per day, you might even skip the empty digest mail but i see this as a part of the daily digest adjustment
Anonymous


Paul 10/21/2023 8:25:00 AM

i think it is good question
Anonymous