A project manager is hired as a consultant by the executive sponsor to manage a major change program that has experienced two past failures. The current executive sponsor believes the project is in good shape based on feedback from the last project manager and reports this to senior executive management. The executive sponsor believes there were no major risks threatening the time, budget, or quality of the project. In the first week of risk analysis, the project manager concludes the project timeline is unrealistic and is three months behind schedule. The organization's risk appetite is low.

What is the first step that should be taken?

  1. Review the project schedule and recommend fast tracking the schedule and/or crashing the critical path.
  2. Discuss the project schedule with the executive sponsor and agree on a strategy for updating the risk management plan and risk response plans.
  3. Update existing risk response plans and include more resources to get the project back on track.
  4. Immediately call a steering committee meeting, report the project status, and suggest project scope reductions to save time.

Answer(s): B



During what process should a project manager assign a risk owner?

  1. Plan Risk Responses
  2. Plan Risk Management
  3. Monitor Risks
  4. Identify Risks

Answer(s): A



A risk manager wants to determine which risks are going to have the highest impact on a project.
Which of the following techniques should the risk manager use?

  1. Assumptions analysis
  2. Sensitivity analysis
  3. Root cause analysis
  4. Prioritization matrices

Answer(s): B



Critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks. How could the situation be improved for the future?

  1. Cross train others to reduce the SME workload.
  2. Introduce scope reductions to limit the reliance on SMEs.
  3. Replace the SME with resources, who are responsible for receiving output from the SME on their deliverables.
  4. Extend the project schedule timeline to accommodate availability of the SME.

Answer(s): B



In what way can the risk manager determine when poor risk planning techniques are influencing the scope, schedule, quality, and/or budget of the project?

  1. Evaluate the results of the Monte Carlo analysis
  2. Document and periodically update project risk information
  3. Monitor project metrics and performance information
  4. Update the risk management plan

Answer(s): C



The company board is concerned about potential legal action from a high-risk project What technique can be used to justify risk response decisions taken on this project?

  1. Interviews
  2. Nominal group technique
  3. Brainstorming
  4. Decision tree analysis

Answer(s): D



The project manager generates a monthly risk report for key stakeholders which documents high and medium risk items only.
Where would the project manager find the list of recipients for the report?

  1. Communications management plan
  2. Risk management plan
  3. Risk register
  4. Project charter

Answer(s): A



A CEO wants to reduce costs in the time spent for risk management activities.
What step did the risk manager fail to perform?

  1. Assigning the CEO as a risk owner
  2. Preventing all issues from occurring
  3. Properly communicating the risk management activities and their outcomes
  4. Explaining the purpose of the management reserve

Answer(s): B



Share your comments for PMI PMI-RMP exam with other users:

V
VINNY
6/2/2023 11:59:00 AM

very good use full

A
Andy
12/6/2023 5:56:00 AM

very valid questions

M
Mamo
8/12/2023 7:46:00 AM

will these question help me to clear pl-300 exam?

M
Marial Manyang
7/26/2023 10:13:00 AM

please provide me with these dumps questions. thanks

A
Amel Mhamdi
12/16/2022 10:10:00 AM

in the pdf downloaded is write google cloud database engineer i think that it isnt the correct exam

A
Angel
8/30/2023 10:58:00 PM

i think you have the answers wrong regarding question: "what are three core principles of web content accessibility guidelines (wcag)? answer: robust, operable, understandable

S
SH
5/16/2023 1:43:00 PM

these questions are not valid , they dont come for the exam now

S
sudhagar
9/6/2023 3:02:00 PM

question looks valid

V
Van
11/24/2023 4:02:00 AM

good for practice

D
Divya
8/2/2023 6:54:00 AM

need more q&a to go ahead

R
Rakesh
10/6/2023 3:06:00 AM

question 59 - a newly-created role is not assigned to any user, nor granted to any other role. answer is b https://docs.snowflake.com/en/user-guide/security-access-control-overview

N
Nik
11/10/2023 4:57:00 AM

just passed my exam today. i saw all of these questions in my text today. so i can confirm this is a valid dump.

D
Deep
6/12/2023 7:22:00 AM

needed dumps

T
tumz
1/16/2024 10:30:00 AM

very helpful

N
NRI
8/27/2023 10:05:00 AM

will post once the exam is finished

K
kent
11/3/2023 10:45:00 AM

relevant questions

Q
Qasim
6/11/2022 9:43:00 AM

just clear exam on 10/06/2202 dumps is valid all questions are came same in dumps only 2 new questions total 46 questions 1 case study with 5 question no lab/simulation in my exam please check the answers best of luck

C
Cath
10/10/2023 10:09:00 AM

q.112 - correct answer is c - the event registry is a module that provides event definitions. answer a - not correct as it is the definition of event log

S
Shiji
10/15/2023 1:31:00 PM

good and useful.

A
Ade
6/25/2023 1:14:00 PM

good questions

P
Praveen P
11/8/2023 5:18:00 AM

good content

A
Anastasiia
12/28/2023 9:06:00 AM

totally not correct answers. 21. you have one gcp account running in your default region and zone and another account running in a non-default region and zone. you want to start a new compute engine instance in these two google cloud platform accounts using the command line interface. what should you do? correct: create two configurations using gcloud config configurations create [name]. run gcloud config configurations activate [name] to switch between accounts when running the commands to start the compute engine instances.

P
Priyanka
7/24/2023 2:26:00 AM

kindly upload the dumps

N
Nabeel
7/25/2023 4:11:00 PM

still learning

G
gure
7/26/2023 5:10:00 PM

excellent way to learn

C
ciken
8/24/2023 2:55:00 PM

help so much

B
Biswa
11/20/2023 9:28:00 AM

understand sql col.

S
Saint Pierre
10/24/2023 6:21:00 AM

i would give 5 stars to this website as i studied for az-800 exam from here. it has all the relevant material available for preparation. i got 890/1000 on the test.

R
Rose
7/24/2023 2:16:00 PM

this is nice.

A
anon
10/15/2023 12:21:00 PM

q55- the ridac workflow can be modified using flow designer, correct answer is d not a

N
NanoTek3
6/13/2022 10:44:00 PM

by far this is the most accurate exam dumps i have ever purchased. all questions are in the exam. i saw almost 90% of the questions word by word.

E
eriy
11/9/2023 5:12:00 AM

i cleared the az-104 exam by scoring 930/1000 on the exam. it was all possible due to this platform as it provides premium quality service. thank you!

M
Muhammad Rawish Siddiqui
12/8/2023 8:12:00 PM

question # 232: accessibility, privacy, and innovation are not data quality dimensions.

V
Venkat
12/27/2023 9:04:00 AM

looks wrong answer for 443 question, please check and update

AI Tutor 👋 I’m here to help!