PMI Risk Management Professional PMI-RMP Exam Questions in PDF

Free PMI PMI-RMP Dumps Questions (page: 10)

During project execution, the project team realizes that the power outlet for imported equipment is not compatible with the current customer's electrical infrastructure. This event was not originally identified as a risk. To maintain the project schedule, the project manager decides to purchase a new power adapter.

What type of response best describes this course of action?

  1. Contingency plan
  2. Management plan
  3. Fall-back plan
  4. Workaround

Answer(s): D



After a risk review meeting, three key risks are identified as likely to be realized. The project manager requests a risk scenario be calculated to establish the impact on the budget.

What is the forecasting methodology that should be utilized to calculate the impact?

  1. Estimate to complete (ETC)
  2. Budget at completion (BAC)
  3. Estimate risk completion (ERC)
  4. Estimate at completion (EAC)

Answer(s): D



A risk has been identified in a multi-functional project. The project manager decides to take no action.

What type of response is this considered?

  1. Avoidance
  2. Exploitation
  3. Procrastination
  4. Acceptance

Answer(s): D



Which of the following could be included in risk monitoring and controlling techniques?

  1. Status review meetings, trend analysis, earned value analysis, McGregor's analysis, defect repair, inspection
  2. Status review meetings, variance analysis, trend analysis, earned value analysis, inspection, control charts
  3. Status review meetings, control charts, Inspection, defect repair, Maslow's analysis, trend analysis
  4. Variance analysis, trend analysis, earned value analysis, Maslow's analysis, control charts, brainstorming

Answer(s): B



The company is a risk seeking organization, and has experienced measurable success based on their current strategy for growth. A new project has that exceeds the risk levels documented in the risk management plan.

What would be the best course of action for the company to take with the project based on its current scope?

  1. Monitor ongoing risks closely for any major changes.
  2. Perform a Monte Carlo simulation to understand possible risk outcomes.
  3. Cancel the project, as the overall level of risk remains unacceptable.
  4. Conduct a stakeholder meeting to validate stakeholder risk appetite.

Answer(s): C



What are the critical success factors for the Plan Risk Management process?

  1. Mitigate all risks, engage stakeholders, and follow organizational policies.
  2. Identify and address barriers, engage stakeholders, and follow organizational policies.
  3. Contingency reserves engage stakeholders and follow organizational policies.
  4. Identify and address barriers, engage stakeholders, and follow government regulations.

Answer(s): B



What items should be included in a complex project's risk management plan?

  1. Risk management methodology, scope statement, and thresholds and corresponding definitions
  2. Risk management methodology, risk management organization, and thresholds and corresponding definitions
  3. Risk management organization, templates, and milestone plan
  4. Risk management organization, risk communication plan, and milestone plan

Answer(s): B



Which analysis method has a lower standard deviation?

  1. European Hypercube
  2. Monte Carlo simulation
  3. Hecht analysis
  4. Latin Hypercube

Answer(s): D



Share your comments for PMI PMI-RMP exam with other users:

F
Future practitioner
8/10/2023 1:26:00 PM

question 4 answer is c. this site shows the correct answer as b. "adopt a consumption model" is clearly a cost optimization design principle. looks like im done using this site to study!!!

A
Ace
8/3/2023 10:37:00 AM

number 52 answer is d

N
Nathan
12/17/2023 12:04:00 PM

just started preparing for my exam , and this site is so much help

C
Corey
12/29/2023 5:06:00 PM

question 35 is incorrect, the correct answer is c, it even states so: explanation: when a vm is infected with ransomware, you should not restore the vm to the infected vm. this is because the ransomware will still be present on the vm, and it will encrypt the files again. you should also not restore the vm to any vm within the companys subscription. this is because the ransomware could spread to other vms in the subscription. the best way to restore a vm that is infected with ransomware is to restore it to a new azure vm. this will ensure that the ransomware is not present on the new vm.

R
Rajender
10/18/2023 3:54:00 AM

i would like to take psm1 exam.

B
Blessious Phiri
8/14/2023 9:53:00 AM

cbd and pdb are key to the database

A
Alkaed
10/19/2022 10:41:00 AM

the purchase and download process is very much streamlined. the xengine application is very nice and user-friendly but there is always room for improvement.

D
Dave Gregen
9/4/2023 3:17:00 PM

please upload p_sapea_2023

S
Sarah
6/13/2023 1:42:00 PM

anyone use this? the question dont seem to follow other formats and terminology i have been studying im getting worried

S
Shuv
10/3/2023 8:19:00 AM

good questions

R
Reb974
8/5/2023 1:44:00 AM

hello are these questions valid for ms-102

M
Mchal
7/20/2023 3:38:00 AM

some questions are wrongly answered but its good nonetheless

S
Sonbir
8/8/2023 1:04:00 PM

how to get system serial number using intune

M
Manju
10/19/2023 1:19:00 PM

is it really helpful to pass the exam

L
LeAnne Hair
8/24/2023 12:47:00 PM

#229 in incorrect - all the customers require an annual review

A
Abdul SK
9/28/2023 11:42:00 PM

kindy upload

A
Aderonke
10/23/2023 12:53:00 PM

fantastic assessment on psm 1

S
SAJI
7/20/2023 2:51:00 AM

56 question correct answer a,b

R
Raj Kumar
10/23/2023 8:52:00 PM

thank you for providing the q bank

P
piyush keshari
7/7/2023 9:46:00 PM

true quesstions

B
B.A.J
11/6/2023 7:01:00 AM

i can´t believe ms asks things like this, seems to be only marketing material.

G
Guss
5/23/2023 12:28:00 PM

hi, could you please add the last update of ns0-527

R
Rond65
8/22/2023 4:39:00 PM

question #3 refers to vnet4 and vnet5. however, there is no vnet5 listed in the case study (testlet 2).

C
Cheers
12/13/2023 9:55:00 AM

sometimes it may be good some times it may be

S
Sumita Bose
7/21/2023 1:01:00 AM

qs 4 answer seems wrong- please check

A
Amit
9/7/2023 12:53:00 AM

very detailed explanation !

F
FisherGirl
5/16/2022 10:36:00 PM

the interactive nature of the test engine application makes the preparation process less boring.

C
Chiranthaka
9/20/2023 11:15:00 AM

very useful.

S
SK
7/15/2023 3:51:00 AM

complete question dump should be made available for practice.

G
Gamerrr420
5/25/2022 9:38:00 PM

i just passed my first exam. i got 2 exam dumps as part of the 50% sale. my second exam is under work. once i write that exam i report my result. but so far i am confident.

K
Kudu hgeur
9/21/2023 5:58:00 PM

nice create dewey stefen

A
Anorag
9/6/2023 9:24:00 AM

i just wrote this exam and it is still valid. the questions are exactly the same but there are about 4 or 5 questions that are answered incorrectly. so watch out for those. best of luck with your exam.

N
Nathan
1/10/2023 3:54:00 PM

passed my exam today. this is a good start to 2023.

1
1
10/28/2023 7:32:00 AM

great sharing

AI Tutor 👋 I’m here to help!