PMI Risk Management Professional PMI-RMP Dumps in PDF

Free PMI PMI-RMP Real Questions (page: 8)

Which of the following demonstrates that a company's risk management process is successful?

  1. Projects deemed too risky are given additional time.
  2. The number of identified risks has decreased.
  3. Profitability has increased due to the risk management process.
  4. Additional resources were added to complete the project faster.

Answer(s): C



A heavy industrial design firm has over USS3 billion in current contract value. As a result of quantitative risk analysis of a geographically separated project, opportunities have been identified and assessed as high priorities for the project.

What is the most effective method to capture these opportunities?

  1. Integrate them into the RBS.
  2. Schedule a project team meeting.
  3. Formally notify the project manager.
  4. Establish a contingency reserve.

Answer(s): C



How can the project manager rank competing stakeholder priorities for all the identified risks?

  1. Perform qualitative and quantitative risk analysis.
  2. Engage the project sponsor to decide.
  3. Refer to stakeholder analysis prioritization tree.
  4. Perform a review of organizational process assets.

Answer(s): A



The senior risk manager hears that critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks.
Which area should be reviewed, as an opportunity for the risk manager to coach the project manager responsible for the project?

  1. Scope reduction to reduce SME reliance
  2. Risk management plan and planned risks responses
  3. Risk identification process and participation
  4. Detailed review of the project schedule before approval

Answer(s): C



Which of the following characteristics would a risk-adverse person or group demonstrate?

  1. Reasonable comfort with most uncertainty; accepts risk as a normal feature of projects and business, and takes uncertainty in stride with no apparent or significant influence on their behavior.
  2. Risk taking is a price worth paying for future payoffs; seeks strategies and tactics that have high future payoffs; thinks abstractly and creatively envisioning possibilities, and is not afraid of change oi unknowns.
  3. Discomfort with uncertainty; low tolerance for ambiguity, and seeks security and resolution when facing risk.
  4. Adaptable and resourceful, and is not afraid to take action, or even thrill seeking.

Answer(s): C



A project manager has a two-month project with three project team members. The project sponsor does not agree with the project manager that a risk planning process is necessary, since the project is very small.

Would it be appropriate for the project manager to implement some level of risk management?

  1. Yes, even small projects may require risk planning.
  2. No, small projects do not usually require risk planning.
  3. No, risk planning should be initiated with the sponsor's consent.
  4. Yes, the risk planning process implementation is ultimately the project manager's decision.

Answer(s): A



Which of the following would a proactive risk manager do during the Monitoring and Controlling Process?

  1. Develop risk responses, create risk management plan, and stay alert for risk events.
  2. Update the lessons learned documents, develop risk responses, and create the risk management plan.
  3. Review identified risks, stay alert for risk events, and remind team members to keep the risk manager informed about risk triggers.
  4. Review lessons learned document to identify risks, quantify risks, and lower impact ratings.

Answer(s): C



A stakeholder is asked to approve additional funding to implement a risk response plan. However, the stakeholder is unsure of the amount that could be approved without escalation.

Where should the stakeholder look to determine the amount that can be approved?

  1. Project charter
  2. Risk management plan
  3. Risk register
  4. Organizational process assets

Answer(s): B



Share your comments for PMI PMI-RMP exam with other users:

B
Bhuddhiman
7/20/2023 11:52:00 AM

great course

A
Anuj
1/14/2024 4:07:00 PM

very good question

S
Saravana Kumar TS
12/8/2023 9:49:00 AM

question: 93 which statement is true regarding the result? sales contain 6 columns and values contain 7 columns so c is not right answer.

L
Lue
3/30/2023 11:43:00 PM

highly recommend just passed my exam.

D
DC
1/7/2024 10:17:00 AM

great practice! thanks

A
Anonymus
11/9/2023 5:41:00 AM

anyone who wrote this exam recently?

K
Khalid Javid
11/17/2023 3:46:00 PM

kindly share the dump

N
Na
8/9/2023 8:39:00 AM

could you please upload cfe fraud prevention and deterrence questions? it will be very much helpful.

S
shime
10/23/2023 10:03:00 AM

this is really very very helpful for mcd level 1

V
Vnu
6/3/2023 2:39:00 AM

very helpful!

S
Steve
8/17/2023 2:19:00 PM

question #18s answer should be a, not d. this should be corrected. it should be minvalidityperiod

R
RITEISH
12/24/2023 4:33:00 AM

thanks for the exact solution

S
SB
10/15/2023 7:58:00 AM

need to refer the questions and have to give the exam

M
Mike Derfalem
7/16/2023 7:59:00 PM

i need it right now if it was possible please

I
Isak
7/6/2023 3:21:00 AM

i need it very much please share it in the fastest time.

M
Maria
6/23/2023 11:40:00 AM

correct answer is d for student.java program

N
Nagendra Pedipina
7/12/2023 9:10:00 AM

q:37 c is correct

J
John
9/16/2023 9:37:00 PM

q6 exam topic: terramearth, c: correct answer: copy 1petabyte to encrypted usb device ???

S
SAM
12/4/2023 12:56:00 AM

explained answers

A
Andy
12/26/2023 9:35:00 PM

plan to take theaws certified developer - associate dva-c02 in the next few weeks

S
siva
5/17/2023 12:32:00 AM

very helpfull

M
mouna
9/27/2023 8:53:00 AM

good questions

B
Bhavya
9/12/2023 7:18:00 AM

help to practice csa exam

M
Malik
9/28/2023 1:09:00 PM

nice tip and well documented

R
rodrigo
6/22/2023 7:55:00 AM

i need the exam

D
Dan
6/29/2023 1:53:00 PM

please upload

A
Ale M
11/22/2023 6:38:00 PM

prepping for fsc exam

A
ahmad hassan
9/6/2023 3:26:00 AM

pd1 with great experience

Ž
Žarko
9/5/2023 3:35:00 AM

@t it seems like azure service bus message quesues could be the best solution

S
Shiji
10/15/2023 1:08:00 PM

helpful to check your understanding.

D
Da Costa
8/27/2023 11:43:00 AM

question 128 the answer should be static not auto

B
bot
7/26/2023 6:45:00 PM

more comments here

K
Kaleemullah
12/31/2023 1:35:00 AM

great support to appear for exams

B
Bsmaind
8/20/2023 9:26:00 AM

useful dumps

AI Tutor 👋 I’m here to help!