PMI Certified Associate in Project Management (-100) PMI-100 Dumps in PDF

Free PMI PMI-100 Real Questions (page: 19)

The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:

  1. Human resource management plan.
  2. Activity resource requirements.
  3. Personnel assessment tools,
  4. Multi-criteria decision analysis.

Answer(s): A

Explanation:

9.1.3.1 Human Resource Management Plan
The human resource management plan, a part of the project management plan, provides guidance on how project human resources should be defined, staffed, managed, and eventually released. The human resource management plan and any subsequent revisions are also inputs into the Develop Project Management Plan process.

Process: 9.1 Plan Human Resource Management
Definition: The process of identifying and documenting project roles, responsibilities, required skills, reporting relationships, and creating a staffing management plan.
Key Benefit: The key benefit of this process is that it establishes project roles and responsibilities, project organization charts, and the staffing management plan including the timetable for staff acquisition and release.

Inputs
1. Project management plan
2. Activity resource requirements
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Organization charts and position descriptions
2. Networking
3. Organizational theory
4. Expert judgment
5. Meetings

Outputs
1. Human resource management plan



The process of identifying and documenting relationships among the project activities is known as:

  1. Control Schedule.
  2. Sequence Activities.
  3. Define Activities.
  4. Develop Schedule.

Answer(s): B

Explanation:

Process: 6.3 Sequence Activities
Definition: The process of identifying and documenting relationships among the project activities. Key Benefit: The key benefit of this process is that it defines the logical sequence of work to obtain the greatest efficiency given all project constraints.

Inputs
1. Schedule management plan
2. Activity list
3. Activity attributes
4. Milestone list
5. Project scope statement
6. Enterprise environmental factors
7. Organizational process assets

Tools & Techniques
1. Precedence diagramming method (PDM)
2. Dependency determination
3. Leads and lags

Outputs
1. Project schedule network diagrams
2. Project documents updates



Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:

  1. Enterprise environmental factors
  2. Work performance reports
  3. Organizational process assets
  4. Context diagrams

Answer(s): A

Explanation:

2.1.5 Enterprise Environmental Factors
Enterprise environmental factors refer to conditions, not under the control of the project team, that influence, constrain, or direct the project. Enterprise environmental factors are considered inputs to most planning processes, may enhance or constrain project management options, and may have a positive or negative influence on the outcome.
Enterprise environmental factors vary widely in type or nature. Enterprise environmental factors include, but are not limited to:
Organizational culture, structure, and governance; Geographic distribution of facilities and resources;
Government or industry standards (e.g., regulatory agency regulations, codes of conduct, product standards, quality standards, and workmanship standards);
Infrastructure (e.g., existing facilities and capital equipment);
Existing human resources (e.g., skills, disciplines, and knowledge, such as design, development, legal, contracting, and purchasing);
Personnel administration (e.g., staffing and retention guidelines, employee performance reviews and training records, reward and overtime policy, and time tracking);
Company work authorization systems; Marketplace conditions;
Stakeholder risk tolerances; Political climate;
Organization’s established communications channels;
Commercial databases (e.g., standardized cost estimating data, industry risk study information, and risk databases); and
Project management information system (e.g., an automated tool, such as a scheduling software tool, a configuration management system, and
Project management information system (e.g., an automated tool, such as a scheduling software tool, a configuration management system, an information collection and distribution system, or web interfaces to other online automated systems).



The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:

  1. Responses
  2. Appetite
  3. Tolerance
  4. Attitude

Answer(s): A

Explanation:

11 PROJECT RISK MANAGEMENT
[..]
Organizations perceive risk as the effect of uncertainty on projects and organizational objectives. Organizations and stakeholders are willing to accept varying degrees of risk depending on their risk attitude. The risk attitudes of both the organization and the stakeholders may be influenced by a number of factors, which are broadly classified into three themes:

Risk appetite, which is the degree of uncertainty an entity is willing to take on in anticipation of a reward.
Risk tolerance, which is the degree, amount, or volume of risk that an organization or individual will withstand.
Risk threshold, which refers to measures along the level of uncertainty or the level of impact at which a stakeholder may have a specific interest. Below that risk threshold, the organization will accept the risk. Above that risk threshold, the organization will not tolerate the risk.
For example, an organization’s risk attitude may include its appetite for uncertainty, its threshold for risk levels that are unacceptable, or its risk tolerance at which point the organization may select a different risk response. Positive and negative risks are commonly referred to as opportunities and threats. The project may be accepted if the risks are within tolerances and are in balance with the rewards that may be gained by taking the risks. Positive risks that offer opportunities within the limits of risk tolerances may be pursued in order to generate enhanced value. For example, adopting an aggressive resource optimization technique is a risk taken in anticipation of a reward for using fewer resources.



An output of the Manage Stakeholder Engagement process is:

  1. change requests
  2. enterprise environmental factors
  3. the stakeholder management plan
  4. the change log

Answer(s): A

Explanation:

13.3 Manage Stakeholder Engagement
Definition: The process of communicating and working with stakeholders to meet their needs/expectations, address issues as they occur, and foster appropriate stakeholder engagement in project activities throughout the project life cycle.
Key Benefit: The key benefit of this process is that it allows the project manager to increase support and minimize resistance from stakeholders, significantly increasing the chances to achieve project success.

Inputs
1. Stakeholder management plan
2. Communications management plan
3. Change log
4. Organizational process assets

Tools & Techniques
1. Communication methods
2. Interpersonal skills
3. Management skills

Outputs
1. Issue log
2. Change requests
3. Project management plan updates
4. Project documents updates
5. Organizational process assets updates



Share your comments for PMI PMI-100 exam with other users:

1
1
10/28/2023 7:32:00 AM

great sharing

A
Anand
1/20/2024 10:36:00 AM

very helpful

K
Kumar
6/23/2023 1:07:00 PM

thanks.. very helpful

U
User random
11/15/2023 3:01:00 AM

i registered for 1z0-1047-23 but dumps qre available for 1z0-1047-22. help me with this...

K
kk
1/17/2024 3:00:00 PM

very helpful

R
Raj
7/24/2023 10:20:00 AM

please upload oracle 1z0-1110-22 exam pdf

B
Blessious Phiri
8/13/2023 11:58:00 AM

becoming interesting on the logical part of the cdbs and pdbs

L
LOL what a joke
9/10/2023 9:09:00 AM

some of the answers are incorrect, i would be wary of using this until an admin goes back and reviews all the answers

M
Muhammad Rawish Siddiqui
12/9/2023 7:40:00 AM

question # 267: federated operating model is also correct.

M
Mayar
9/22/2023 4:58:00 AM

its helpful alot.

S
Sandeep
7/25/2022 11:58:00 PM

the questiosn from this braindumps are same as in the real exam. my passing mark was 84%.

E
Eman Sawalha
6/10/2023 6:09:00 AM

it is an exam that measures your understanding of cloud computing resources provided by aws. these resources are aligned under 6 categories: storage, compute, database, infrastructure, pricing and network. with all of the services and typees of services under each category

M
Mars
11/16/2023 1:53:00 AM

good and very useful

R
ronaldo7
10/24/2023 5:34:00 AM

i cleared the az-104 exam by scoring 930/1000 on the exam. it was all possible due to this platform as it provides premium quality service. thank you!

P
Palash Ghosh
9/11/2023 8:30:00 AM

easy questions

N
Noor
10/2/2023 7:48:00 AM

could you please upload ad0-127 dumps

K
Kotesh
7/27/2023 2:30:00 AM

good content

B
Biswa
11/20/2023 9:07:00 AM

understanding about joins

J
Jimmy Lopez
8/25/2023 10:19:00 AM

please upload oracle cloud infrastructure 2023 foundations associate exam braindumps. thank you.

L
Lily
4/24/2023 10:50:00 PM

questions made studying easy and enjoyable, passed on the first try!

J
John
8/7/2023 12:12:00 AM

has anyone recently attended safe 6.0 exam? did you see any questions from here?

B
Big Dog
6/24/2023 4:47:00 PM

question 13 should be dhcp option 43, right?

B
B.Khan
4/19/2022 9:43:00 PM

the buy 1 get 1 is a great deal. so far i have only gone over exam. it looks promissing. i report back once i write my exam.

G
Ganesh
12/24/2023 11:56:00 PM

is this dump good

A
Albin
10/13/2023 12:37:00 AM

good ................

P
Passed
1/16/2022 9:40:00 AM

passed

H
Harsh
6/12/2023 1:43:00 PM

yes going good

S
Salesforce consultant
1/2/2024 1:32:00 PM

good questions for practice

R
Ridima
9/12/2023 4:18:00 AM

need dump and sap notes for c_s4cpr_2308 - sap certified application associate - sap s/4hana cloud, public edition - sourcing and procurement

T
Tanvi Rajput
10/6/2023 6:50:00 AM

question 11: d i personally feel some answers are wrong.

A
Anil
7/18/2023 9:38:00 AM

nice questions

C
Chris
8/26/2023 1:10:00 AM

looking for c1000-158: ibm cloud technical advocate v4 questions

S
sachin
6/27/2023 1:22:00 PM

can you share the pdf

B
Blessious Phiri
8/13/2023 10:26:00 AM

admin ii is real technical stuff

AI Tutor 👋 I’m here to help!