Which process involves developing an approximation of the monetary resources needed to complete project activities?

  1. Estimate Costs
  2. Control Costs
  3. Determine Budget
  4. Plan Cost Management

Answer(s): A

Explanation:

Process: 7.2 Estimate Costs
Definition: The process of developing an approximation of the monetary resources needed to complete project activities.
Key Benefit: The key benefit of this process is that it determines the amount of cost required to complete project work.

Inputs
1. Cost management plan
2. Human resource management plan
3. Scope baseline
4. Project schedule
5. Risk register
6. Enterprise environmental factors
7. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Analogous estimating
3. Parametric estimating
4. Bottom-up estimating
5. Three-point estimating
6. Reserve analysis
7. Cost of quality
8. Project management software
9. Vendor bid analysis
10. Group decision-making techniques

Outputs
1. Activity cost estimates
2. Basis of estimates
3. Project documents updates



Which tool or technique is used in the Develop Project Management Plan process?

  1. Project management information system (PMIS)
  2. Project charter
  3. Quality assurance
  4. Expert judgment

Answer(s): D

Explanation:

4.1.2.1 Expert Judgment
Expert judgment is often used to assess the inputs used to develop the project charter. Expert judgment is applied to all technical and management details during this process. Such expertise is provided by any group or individual with specialized knowledge or training and is available from many sources, including:
Other units within the organization, Consultants,
Stakeholders, including customers or sponsors, Professional and technical associations, Industry groups,
Subject matter experts (SME), and Project management office (PMO).

Process: 4.2. Develop Project Management Plan
Definition: The process of defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive project management plan. The project’s integrated baselines and subsidiary plans may be included within the project management plan.
Key Benefit: The key benefit of this process is a central document that defines the basis of all project work.

Inputs
1. Project charter
2. Outputs from other processes
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Facilitation techniques

Outputs
Project management plan

4.2.3.1 Project Management Plan
The project management plan is the document that describes how the project will be executed, monitored, and controlled. It integrates and consolidates all of the subsidiary plans and baselines from the planning processes. Project baselines include, but are not limited to:
Scope baseline (Section 5.4.3.1), Schedule baseline (Section 6.6.3.1), and Cost baseline (Section 7.3.3.1).

Subsidiary plans include, but are not limited to: Scope management plan (Section 5.1.3.1), Requirements management plan (Section 5.1.3.2), Schedule management plan (Section 6.1.3.1), Cost management plan (Section 7.1.3.1),
Quality management plan (Section 8.1.3.1), Process improvement plan (Section 8.1.3.2),
Human resource management plan (Section 9.1.3.1), Communications management plan (Section 10.1.3.1), Risk management plan (Section 11.1.3.1), Procurement management plan (Section 12.1.3.1), and Stakeholder management plan (Section 13.2.3.1).

Among other things, the project management plan may also include the following:
Life cycle selected for the project and the processes that will be applied to each phase; Details of the tailoring decisions specified by the project management team as follows:
○ Project management processes selected by the project management team,
○ Level of implementation for each selected process,
○ Descriptions of the tools and techniques to be used for accomplishing those processes, and
○ Description of how the selected processes will be used to manage the specific project, including the dependencies and interactions among those processes and the essential inputs and outputs.
Description of how work will be executed to accomplish the project objectives;
Change management plan that documents how changes will be monitored and controlled; Configuration management plan that documents how Configuration management will be performed; Description of how the integrity of the project baselines will be maintained;
Requirements and techniques for communication among stakeholders; and
Key management reviews for content, the extent of, and timing to address, open issues and pending decisions.

The project management plan may be either summary level or detailed, and may be composed of one or more subsidiary plans. Each of the subsidiary plans is detailed to the extent required by the specific project. Once the project management plan is baselined, it may only be changed when a change request is generated and approved through the Perform Integrated Change Control process.



Lessons learned are created and project resources are released in which Process Group?

  1. Planning
  2. Executing
  3. Closing
  4. Initiating

Answer(s): C



When should quality planning be performed?

  1. While developing the project charter
  2. In parallel with the other planning processes
  3. As part of a detailed risk analysis
  4. As a separate step from the other planning processes

Answer(s): B

Explanation:

Quality planning should be performed in parallel with the other planning processes. For example, proposed changes in the deliverables to meet identified quality standards may require cost or schedule adjustments and a detailed risk analysis of the impact to plans.
The quality planning techniques discussed here are those used most frequently on projects. There are many others that may be useful on certain projects or in some application areas.



A key benefit of the Manage Communications process is that it enables:

  1. The best use of communication methods.
  2. An efficient and effective communication flow.
  3. Project costs to be reduced.
  4. The best use of communication technology.

Answer(s): B

Explanation:

Process: 10.2 Manage Communications
Definition: The process of creating, collecting, distributing, storing, retrieving and the ultimate disposition of project information in accordance with the communications management plan.
Key Benefit: The key benefit of this process is that it enables an efficient and effective communications flow between project stakeholders.
Inputs
1. Communications management plan
2. Work performance reports
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Communication technology
2. Communication models
3. Communication methods
4. Information management systems
5. Performance reporting

Outputs
1. Project communications
2. Project management plan updates
3. Project documents updates
4. Organizational process assets updates



Share your comments for PMI PMI-100 exam with other users:

S
Salesforce consultant
1/2/2024 1:32:00 PM

good questions for practice

R
Ridima
9/12/2023 4:18:00 AM

need dump and sap notes for c_s4cpr_2308 - sap certified application associate - sap s/4hana cloud, public edition - sourcing and procurement

T
Tanvi Rajput
10/6/2023 6:50:00 AM

question 11: d i personally feel some answers are wrong.

A
Anil
7/18/2023 9:38:00 AM

nice questions

C
Chris
8/26/2023 1:10:00 AM

looking for c1000-158: ibm cloud technical advocate v4 questions

S
sachin
6/27/2023 1:22:00 PM

can you share the pdf

B
Blessious Phiri
8/13/2023 10:26:00 AM

admin ii is real technical stuff

L
Luis Manuel
7/13/2023 9:30:00 PM

could you post the link

V
vijendra
8/18/2023 7:54:00 AM

hello send me dumps

S
Simeneh
7/9/2023 8:46:00 AM

it is very nice

J
john
11/16/2023 5:13:00 PM

i gave the amazon dva-c02 tests today and passed. very helpful.

T
Tao
11/20/2023 8:53:00 AM

there is an incorrect word in the problem statement. for example, in question 1, there is the word "speci c". this is "specific. in the other question, there is the word "noti cation". this is "notification. these mistakes make this site difficult for me to use.

P
patricks
10/24/2023 6:02:00 AM

passed my az-120 certification exam today with 90% marks. studied using the dumps highly recommended to all.

A
Ananya
9/14/2023 5:17:00 AM

i need it, plz make it available

J
JM
12/19/2023 2:41:00 PM

q47: intrusion prevention system is the correct answer, not patch management. by definition, there are no patches available for a zero-day vulnerability. the way to prevent an attacker from exploiting a zero-day vulnerability is to use an ips.

R
Ronke
8/18/2023 10:39:00 AM

this is simple but tiugh as well

C
CesarPA
7/12/2023 10:36:00 PM

questão 4, segundo meu compilador local e o site https://www.jdoodle.com/online-java-compiler/, a resposta correta é "c" !

J
Jeya
9/13/2023 7:50:00 AM

its very useful

T
Tracy
10/24/2023 6:28:00 AM

i mastered my skills and aced the comptia 220-1102 exam with a score of 920/1000. i give the credit to for my success.

J
James
8/17/2023 4:33:00 PM

real questions

A
Aderonke
10/23/2023 1:07:00 PM

very helpful assessments

S
Simmi
8/24/2023 7:25:00 AM

hi there, i would like to get dumps for this exam

J
johnson
10/24/2023 5:47:00 AM

i studied for the microsoft azure az-204 exam through it has 100% real questions available for practice along with various mock tests. i scored 900/1000.

M
Manas
9/9/2023 1:48:00 AM

please upload 1z0-1072-23 exam dups

S
SB
9/12/2023 5:15:00 AM

i was hoping if you could please share the pdf as i’m currently preparing to give the exam.

J
Jagjit
8/26/2023 5:01:00 PM

i am looking for oracle 1z0-116 exam

S
S Mallik
11/27/2023 12:32:00 AM

where we can get the answer to the questions

P
PiPi Li
12/12/2023 8:32:00 PM

nice questions

D
Dan
8/10/2023 4:19:00 PM

question 129 is completely wrong.

G
gayathiri
7/6/2023 12:10:00 AM

i need dump

D
Deb
8/15/2023 8:28:00 PM

love the site.

M
Michelle
6/23/2023 4:08:00 AM

can you please upload it back?

A
Ajay
10/3/2023 12:17:00 PM

could you please re-upload this exam? thanks a lot!

H
him
9/30/2023 2:38:00 AM

great about shared quiz

AI Tutor 👋 I’m here to help!