PMI Certified Associate in Project Management (-100) PMI-100 Exam Questions in PDF

Free PMI PMI-100 Dumps Questions (page: 12)

The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:

  1. Collect Requirements.
  2. Conduct Procurements.
  3. Estimate Activity Durations.
  4. Estimate Activity Resources.

Answer(s): D

Explanation:

Process: 6.4 Estimate Activity Resources
Definition: The process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity.
Key Benefit: The key benefit of this process is that it identifies the type, quantity, and characteristics of resources required to complete the activity which allows more accurate cost and duration estimates.

Inputs
1. Schedule management plan
2. Activity list
3. Activity attributes
4. Resource calendars
5. Risk register
6. Activity cost estimates
7. Enterprise environmental factors
8. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Alternative analysis
3. Published estimating data
4. Bottom-up estimating
5. Project management software

Outputs
1. Activity resource requirements
2. Resource breakdown structure

3. Project documents updates



Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?

  1. Procurement documents
  2. Communications plan
  3. Project charter
  4. Stakeholder register

Answer(s): C

Explanation:

Process: 13.1 Identify Stakeholders
Definition: The process of identifying the people, groups, or organizations that could impact or be impacted by a decision, activity, or outcome of the project; and analyzing and documenting relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on project success.
Key Benefit: The key benefit of this process is that it allows the project manager to identify the appropriate focus for each stakeholder or group of stakeholders.

Inputs
Project charter
Procurement documents Enterprise environmental factors Organizational process assets

Tools & Techniques
1. Stakeholder analysis
2. Expert judgment
3. Meetings

Outputs
1. Stakeholder register



The Identify Stakeholders process is found in which Process Group?

  1. Initiating
  2. Monitoring and Controlling
  3. Planning
  4. Executing

Answer(s): A

Explanation:

Initiating Process Group
4.1 Develop Project Charter
13.1 Identify Stakeholders



An input to Develop Project Charter is a/an:

  1. Business case.
  2. Activity list.
  3. Project management plan.
  4. Cost forecast.

Answer(s): A

Explanation:

Process: 4.1. Develop Project Charter
Definition: The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Key Benefit: The key benefit of this process is a well-defined project start and project boundaries, creation of a formal record of the project, and a direct way for senior management to formally accept and commit to the project.

Inputs
1. Project statement of work
2. Business case
3. Agreements
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Facilitation techniques

Outputs
1. Project charter

4.1.1.2 Business Case
The business case or similar document describes the necessary information from a business standpoint to determine whether or not the project is worth the required investment. It is commonly used for decision making by managers or executives above the project level. Typically, the business need and the cost-benefit analysis are contained in the business case to justify and establish boundaries for the project, and such analysis is usually completed by a business analyst using various stakeholder inputs. The sponsor should agree to the scope and limitations of the business case. The business case is created as a result of one or more of the following:
Market demand (e.g., a car company authorizing a project to build more fuel-efficient cars in response to gasoline shortages),
Organizational need (e.g., due to high overhead costs a company may combine staff functions and streamline processes to reduce costs.),
Customer request (e.g., an electric utility authorizing a project to build a new substation to serve a new industrial park),
Technological advance (e.g., an airline authorizing a new project to develop electronic tickets instead of paper tickets based on technological advances),
Legal requirement (e.g., a paint manufacturer authorizing a project to establish guidelines for handling toxic materials),
Ecological impacts (e.g., a company authorizing a project to lessen its environmental impact), or
Social need (e.g., a nongovernmental organization in a developing country authorizing a project to provide potable water systems, latrines, and sanitation education to communities suffering from high rates of cholera).

Each of the examples in this list may contain elements of risk that should be addressed. In the case of multiphase projects, the business case may be periodically reviewed to ensure that the project is on track to deliver the business benefits. In the early stages of the project life cycle, periodic review of the business case by the sponsoring organization also helps to confirm that the project is still aligned with the business case. The project manager is responsible for ensuring that the project effectively and efficiently meets the goals of the organization and those requirements of a broad set of stakeholders, as defined in the business case.



Which item is a formal proposal to modify any document, deliverable, or baseline?

  1. Change request
  2. Requirements documentation
  3. Scope baseline
  4. Risk urgency assessment

Answer(s): A

Explanation:

4.3.3.3 Change Requests
A change request is a formal proposal to modify any document, deliverable, or baseline. An approved change request will replace the associated document, deliverable, or baseline and may result in an update to other parts
of the project management plan. When issues are found while project work is being performed, change requests are submitted, which may modify project policies or procedures, project scope, project cost or budget, project schedule, or project quality. Other change requests cover the needed preventive or corrective actions to forestall negative impact later in the project. Requests for a change can be direct or indirect, externally or internally initiated, and can be optional or legally/contractually mandated, and may include:

Corrective action—An intentional activity that realigns the performance of the project work with the project management plan;
Preventive action—An intentional activity that ensures the future performance of the project work is aligned with the project management plan;
Defect repair—An intentional activity to modify a nonconforming product or product component;
Updates—Changes to formally controlled project documents, plans, etc., to reflect modified or additional ideas or content.



Share your comments for PMI PMI-100 exam with other users:

C
Checo Lee
7/3/2023 5:45:00 PM

very useful to practice

D
dixitdnoh@gmail.com
8/27/2023 2:58:00 PM

this website is very helpful.

S
Sanjay
8/14/2023 8:07:00 AM

good content

B
Blessious Phiri
8/12/2023 2:19:00 PM

so challenging

P
PAYAL
10/17/2023 7:14:00 AM

17 should be d ,for morequery its scale out

K
Karthik
10/12/2023 10:51:00 AM

nice question

G
Godmode
5/7/2023 10:52:00 AM

yes.

B
Bhuddhiman
7/30/2023 1:18:00 AM

good mateial

K
KJ
11/17/2023 3:50:00 PM

good practice exam

S
sowm
10/29/2023 2:44:00 PM

impressivre qustion

C
CW
7/6/2023 7:06:00 PM

questions seem helpful

L
luke
9/26/2023 10:52:00 AM

good content

Z
zazza
6/16/2023 9:08:00 AM

question 21 answer is alerts

A
Abwoch Peter
7/4/2023 3:08:00 AM

am preparing for exam

M
mohamed
9/12/2023 5:26:00 AM

good one thanks

M
Mfc
10/23/2023 3:35:00 PM

only got thru 5 questions, need more to evaluate

W
Whizzle
7/24/2023 6:19:00 AM

q26 should be b

S
sarra
1/17/2024 3:44:00 AM

the aaa triad in information security is authentication, accounting and authorisation so the answer should be d 1, 3 and 5.

D
DBS
5/14/2023 12:56:00 PM

need to attend this

D
Da_costa
8/1/2023 5:28:00 PM

these are free brain dumps i understand, how can one get free pdf

V
vikas
10/28/2023 6:57:00 AM

provide access

A
Abdullah
9/29/2023 2:06:00 AM

good morning

R
Raj
6/26/2023 3:12:00 PM

please upload the ncp-mci 6.5 dumps, really need to practice this one. thanks guys

M
Miguel
10/5/2023 12:21:00 PM

question 16: https://help.salesforce.com/s/articleview?id=sf.care_console_overview.htm&type=5

H
Hiren Ladva
7/8/2023 10:34:00 PM

yes i m prepared exam

O
oliverjames
10/24/2023 5:37:00 AM

my experience was great with this site as i studied for the ms-900 from here and got 900/1000 on the test. my main focus was on the tutorials which were provided and practice questions. thanks!

B
Bhuddhiman
7/20/2023 11:52:00 AM

great course

A
Anuj
1/14/2024 4:07:00 PM

very good question

S
Saravana Kumar TS
12/8/2023 9:49:00 AM

question: 93 which statement is true regarding the result? sales contain 6 columns and values contain 7 columns so c is not right answer.

L
Lue
3/30/2023 11:43:00 PM

highly recommend just passed my exam.

D
DC
1/7/2024 10:17:00 AM

great practice! thanks

A
Anonymus
11/9/2023 5:41:00 AM

anyone who wrote this exam recently?

K
Khalid Javid
11/17/2023 3:46:00 PM

kindly share the dump

N
Na
8/9/2023 8:39:00 AM

could you please upload cfe fraud prevention and deterrence questions? it will be very much helpful.

AI Tutor 👋 I’m here to help!