A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?
Answer(s): B
On most projects, communication planning is performed very early, such as during project management plan development. This allows appropriate resources, such as time and budget, to be allocated to communication activities.Effective communication means that the information is provided in the right format, at the right time, to the right audience, and with the right impact. Efficient communication means providing only the information that is needed.
Scope, schedule, and cost parameters are integrated in the:
Answer(s): A
Performance Measurement Baseline (PMB). An approved, integrated scope-schedule-cost plan for the project work against which project execution is compared to measure and manage performance. The PMB includes contingency reserve, but excludes management reserve.
A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:
2.4.2.2 Predictive Life CyclesPredictive life cycles (also known as fully plan-driven) are ones in which the project scope, and the time and cost required to deliver that scope, are determined as early in the project life cycle as practically possible. As shown in Figure 2-13, these projects proceed through a series of sequential or overlapping phases, with each phase generally focusing on a subset of project activities and project management processes. The work performed in each phase is usually different in nature to that in the preceding and subsequent phases, therefore, the makeup and skills required of the project team may vary from phase to phase.
What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?
CV = EV - AC CPI = EV / AC SV = EV - PV SPI = EV / PV
Which item is an input to the Define Activities process?
Answer(s): D
5.4.3.1 Scope BaselineThe scope baseline is the approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary, that can be changed only through formal change control procedures and is used as a basis for comparison. It is a component of the project management plan. Components of the scope baseline include:Project scope statement. The project scope statement includes the description of the project scope, major deliverables, assumptions, and constraints.WBS. The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. Each descending level of the WBS represents an increasingly detailed definition of the project work. The WBS is finalized by assigning each work package to a control account and establishing a unique identifier for that work package from a code of accounts. These identifiers provide a structure for hierarchical summation of costs, schedule, and resource information. A control account is a management control point where scope, budget, actual cost, and schedule are integrated and compared to the earned value for performance measurement. Control accounts are placed at selected management points in the WBS. Each control account may include one or more work packages, but each of the work packages should be associated with only one control account. A control account may include one or more planning packages. A planning package is a work breakdown structure component below the control account with known work content but without detailed schedule activities.WBS dictionary. The WBS dictionary is a document that provides detailed deliverable, activity, and scheduling information about each component in the WBS. The WBS dictionary is a document that supports the WBS. Information in the WBS dictionary may include, but is not limited to:○ Code of account identifier,○ Description of work,○ Assumptions and constraints,○ Responsible organization,○ Schedule milestones,○ Associated schedule activities,○ Resources required,○ Cost estimates,○ Quality requirements,○ Acceptance criteria,○ Technical references, and○ Agreement informationProcess: 6.2 Define ActivitiesDefinition: The process of identifying and documenting the specific actions to be performed to produce the project deliverables.Key Benefit: The key benefit of this process is to break down work packages into activities that provide a basis for estimating, scheduling, executing, monitoring, and controlling the project work.Inputs1. Schedule management plan2. Scope baseline3. Enterprise environmental factors4. Organizational process assetsTools & Techniques1. Decomposition2. Rolling wave planning3. Expert judgmentOutputs1. Activity list2. Activity attributes3. Milestone list
Share your comments for PMI PMI-002 exam with other users:
these questions are not valid , they dont come for the exam now
question looks valid
good for practice
need more q&a to go ahead
question 59 - a newly-created role is not assigned to any user, nor granted to any other role. answer is b https://docs.snowflake.com/en/user-guide/security-access-control-overview
just passed my exam today. i saw all of these questions in my text today. so i can confirm this is a valid dump.
needed dumps
very helpful
will post once the exam is finished
relevant questions
just clear exam on 10/06/2202 dumps is valid all questions are came same in dumps only 2 new questions total 46 questions 1 case study with 5 question no lab/simulation in my exam please check the answers best of luck
q.112 - correct answer is c - the event registry is a module that provides event definitions. answer a - not correct as it is the definition of event log
good and useful.
good questions
good content
totally not correct answers. 21. you have one gcp account running in your default region and zone and another account running in a non-default region and zone. you want to start a new compute engine instance in these two google cloud platform accounts using the command line interface. what should you do? correct: create two configurations using gcloud config configurations create [name]. run gcloud config configurations activate [name] to switch between accounts when running the commands to start the compute engine instances.
kindly upload the dumps
still learning
excellent way to learn
help so much
understand sql col.
i would give 5 stars to this website as i studied for az-800 exam from here. it has all the relevant material available for preparation. i got 890/1000 on the test.
this is nice.
q55- the ridac workflow can be modified using flow designer, correct answer is d not a
by far this is the most accurate exam dumps i have ever purchased. all questions are in the exam. i saw almost 90% of the questions word by word.
i cleared the az-104 exam by scoring 930/1000 on the exam. it was all possible due to this platform as it provides premium quality service. thank you!
question # 232: accessibility, privacy, and innovation are not data quality dimensions.
looks wrong answer for 443 question, please check and update
great question
question: a user wants to start a recruiting posting job posting. what must occur before the posting process can begin? 3 ans: comment- option e is incorrect reason: as part of enablement steps, sap recommends that to be able to post jobs to a job board, a user need to have the correct permission and secondly, be associated with one posting profile at minimum
answer to question 72 is d [sys_user_role]
please provide the pdf
hey guys, just to let you all know that i cleared my 312-38 today within 1 hr with 100 questions and passed. thank you so much brain-dumps.net all the questions that ive studied in this dump came out exactly the same word for word "verbatim". you rock brain-dumps.net!!! section name total score gained score network perimeter protection 16 11 incident response 10 8 enterprise virtual, cloud, and wireless network protection 12 8 application and data protection 13 10 network défense management 10 9 endpoint protection 15 12 incident d