PMI Certified Associate in Project Management (-100) PMI-002 Dumps in PDF

Free PMI PMI-002 Real Questions (page: 17)

Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?

  1. Plan Procurement Management
  2. Control Procurements
  3. Collect Requirements
  4. Plan Cost Management

Answer(s): A

Explanation:

Process: 12.1 Plan Procurement Management
Definition: The process of documenting project procurement decisions, specifying the approach, and identifying potential sellers.
Key Benefit: The key benefit of this process is that it determines whether to acquire outside support, and if so, what to acquire, how to acquire it, how much is needed, and when to acquire it.

Inputs
1. Project management plan
2. Requirements documentation
3. Risk register
4. Activity resource requirements
5. Project schedule
6. Activity cost estimates
7. Stakeholder register
8. Enterprise environmental factors
9. Organizational process assets

Tools & Techniques
1. Make-or-buy analysis
2. Expert judgment
3. Market research
4. Meetings

Outputs
1. Procurement management plan
2. Procurement statement of work
3. Procurement documents
4. Source selection criteria
5. Make-or-buy decisions
6. Change requests
7. Project documents updates



Which tool or technique is used to manage change requests and the resulting decisions?

  1. Change control tools
  2. Expert judgment
  3. Delphi technique
  4. Change log

Answer(s): A

Explanation:

4.5.2.3 Change Control Tools
In order to facilitate Configuration and change management, manual or automated tools may be used. Tool selection should be based on the needs of the project stakeholders including organizational and environmental considerations and/or constraints.
Tools are used to manage the change requests and the resulting decisions. Additional considerations should be made for communication to assist the CCB members in their duties as well as distribute the decisions to the appropriate stakeholders


4.3.3.3 Change Requests
A change request is a formal proposal to modify any document, deliverable, or baseline. An approved change request will replace the associated document, deliverable, or baseline and may result in an update to other parts of the project management plan. When issues are found while project work is being performed, change requests are submitted, which may modify project policies or procedures, project scope, project cost or budget, project schedule, or project quality. Other change requests cover the needed preventive or corrective actions to forestall negative impact later in the project. Requests for a change can be direct or indirect, externally or internally initiated, and can be optional or legally/contractually mandated, and may include:
Corrective action—An intentional activity that realigns the performance of the project work with the project management plan;
Preventive action—An intentional activity that ensures the future performance of the project work is aligned with the project management plan;
Defect repair—An intentional activity to modify a nonconforming product or product component;
Updates—Changes to formally controlled project documents, plans, etc., to reflect modified or additional ideas or content.



The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:

  1. Work packages.
  2. Accepted deliverables.
  3. The WBS dictionary.
  4. The scope baseline.

Answer(s): A



In which Knowledge Area is the project charter developed?

  1. Project Cost Management
  2. Project Scope Management
  3. Project Time Management
  4. Project Integration Management

Answer(s): D

Explanation:

Knowledge Areas
4. Project Integration Management
5. Project Scope Management
6. Project Time Management
7. Project Cost Management
8. Project Quality Management
9. Project Human Resource Management 10.Project Communications Management 11.Project Risk Management
12.Project Procurement Management 13.Project Stakeholder Management

Process: 4.1. Develop Project Charter
Definition: The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Key Benefit: The key benefit of this process is a well-defined project start and project boundaries, creation of a formal record of the project, and a direct way for senior management to formally accept and commit to the project.

Inputs
1. Project statement of work
2. Business case
3. Agreements
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Facilitation techniques

Outputs
1. Project charter



The ability to influence cost is greatest during which stages of the project?

  1. Early
  2. Middle
  3. Late
  4. Completion

Answer(s): A



Share your comments for PMI PMI-002 exam with other users:

A
Alkaed
10/19/2022 10:41:00 AM

the purchase and download process is very much streamlined. the xengine application is very nice and user-friendly but there is always room for improvement.

D
Dave Gregen
9/4/2023 3:17:00 PM

please upload p_sapea_2023

S
Sarah
6/13/2023 1:42:00 PM

anyone use this? the question dont seem to follow other formats and terminology i have been studying im getting worried

S
Shuv
10/3/2023 8:19:00 AM

good questions

R
Reb974
8/5/2023 1:44:00 AM

hello are these questions valid for ms-102

M
Mchal
7/20/2023 3:38:00 AM

some questions are wrongly answered but its good nonetheless

S
Sonbir
8/8/2023 1:04:00 PM

how to get system serial number using intune

M
Manju
10/19/2023 1:19:00 PM

is it really helpful to pass the exam

L
LeAnne Hair
8/24/2023 12:47:00 PM

#229 in incorrect - all the customers require an annual review

A
Abdul SK
9/28/2023 11:42:00 PM

kindy upload

A
Aderonke
10/23/2023 12:53:00 PM

fantastic assessment on psm 1

S
SAJI
7/20/2023 2:51:00 AM

56 question correct answer a,b

R
Raj Kumar
10/23/2023 8:52:00 PM

thank you for providing the q bank

P
piyush keshari
7/7/2023 9:46:00 PM

true quesstions

B
B.A.J
11/6/2023 7:01:00 AM

i can´t believe ms asks things like this, seems to be only marketing material.

G
Guss
5/23/2023 12:28:00 PM

hi, could you please add the last update of ns0-527

R
Rond65
8/22/2023 4:39:00 PM

question #3 refers to vnet4 and vnet5. however, there is no vnet5 listed in the case study (testlet 2).

C
Cheers
12/13/2023 9:55:00 AM

sometimes it may be good some times it may be

S
Sumita Bose
7/21/2023 1:01:00 AM

qs 4 answer seems wrong- please check

A
Amit
9/7/2023 12:53:00 AM

very detailed explanation !

F
FisherGirl
5/16/2022 10:36:00 PM

the interactive nature of the test engine application makes the preparation process less boring.

C
Chiranthaka
9/20/2023 11:15:00 AM

very useful.

S
SK
7/15/2023 3:51:00 AM

complete question dump should be made available for practice.

G
Gamerrr420
5/25/2022 9:38:00 PM

i just passed my first exam. i got 2 exam dumps as part of the 50% sale. my second exam is under work. once i write that exam i report my result. but so far i am confident.

K
Kudu hgeur
9/21/2023 5:58:00 PM

nice create dewey stefen

A
Anorag
9/6/2023 9:24:00 AM

i just wrote this exam and it is still valid. the questions are exactly the same but there are about 4 or 5 questions that are answered incorrectly. so watch out for those. best of luck with your exam.

N
Nathan
1/10/2023 3:54:00 PM

passed my exam today. this is a good start to 2023.

1
1
10/28/2023 7:32:00 AM

great sharing

A
Anand
1/20/2024 10:36:00 AM

very helpful

K
Kumar
6/23/2023 1:07:00 PM

thanks.. very helpful

U
User random
11/15/2023 3:01:00 AM

i registered for 1z0-1047-23 but dumps qre available for 1z0-1047-22. help me with this...

K
kk
1/17/2024 3:00:00 PM

very helpful

R
Raj
7/24/2023 10:20:00 AM

please upload oracle 1z0-1110-22 exam pdf

B
Blessious Phiri
8/13/2023 11:58:00 AM

becoming interesting on the logical part of the cdbs and pdbs

AI Tutor 👋 I’m here to help!