Eric is the project manager of the NQQ Project and has hired the ZAS Corporation to complete part of the project work for Eric's organization. Due to a change request the ZAS Corporation is no longer needed on the project even though they have completed nearly all of the project work. Is Eric's organization liable to pay the ZAS Corporation for the work they have completed so far on the project?

  1. It depends on what the outcome of a lawsuit will determine.
  2. No, the ZAS Corporation did not complete all of the work.
  3. It depends on what the termination clause of the contract stipulates.
  4. Yes, the ZAS Corporation did not choose to terminate the contract work.

Answer(s): C



Mike is the program manager of the NHQ Program. Mike and a vendor are in disagreement over the deliverable the vendor has created for Mike's program. Mike does not believe the vendor has correctly created the deliverable, while the vendor is adamant that his company has indeed completed the contract. Both parties have documented their stance in the debate.
This is an example of what?

  1. Breach of contract
  2. Issue
  3. Risk
  4. Claim

Answer(s): D



You are the program manager of the GHY Program in your organization. It has come to your attention that some of the project managers in your program are adding time to each project activity in an effort to pad their durations in case some event happens in their project that will cause delays. What principle should you share with these project managers that counterattack the concept of padding activities with additional time?

  1. Parkinson's Law
  2. Law of Diminishing Returns
  3. 80/20 Law
  4. Pareto's Law

Answer(s): A



You are the program manager for your organization. Your program team has 43 people that all need to be monitored and controlled. You would like to create a standardized report that you can use to monitor, control, and record the performance of each staff member in your program. What type of report can you create that will help you track your staff and their performance?

  1. Performance reports
  2. Staff variance reports
  3. Exceptions report
  4. Lessons learned

Answer(s): A



You have created a control chart for a repeatable process in your program. You have discovered that the seven most recent measurements are all on the positive side of the mean in your control chart. What is this phenomenon called?

  1. Rule of Improvement
  2. Mean Improvement
  3. Rule of Seven
  4. Low-Riding Mean

Answer(s): C



What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?

  1. Project Management Information System
  2. Integrated Change Control
  3. Scope Verification
  4. Configuration Management System

Answer(s): D



Donna is the project manager for her organization. She is preparing a plan to manage changes to the project should changes be requested. Her change management plan defines the process for documenting, tracking, and determining if the changes should be approved or declined. What system is considered the parent of the change control system documented in Donna's plan?

  1. Quality Management System
  2. Change Control System
  3. Project Management Information System
  4. Integrated Change Control System

Answer(s): C



You are a program manager for your organization. You have proposed a program to the management that will last four years and will cost $35 million to create. Management has asked to see the program charter and the proposed costs and benefits of the program.
Management agrees to your program charter and proposed to fund the program in increments at the completion of each milestone. What type of funding does management proposed for this program?

  1. Tentative
  2. Step funding
  3. Milestone approval
  4. Phase gate estimating

Answer(s): B



Share your comments for PMI PGMP exam with other users:

S
Shariq
7/28/2023 8:00:00 AM

how do i get the h12-724 dumps

A
adi
10/30/2023 11:51:00 PM

nice data dumps

E
EDITH NCUBE
7/25/2023 7:28:00 AM

answers are correct

R
Raja
6/20/2023 4:38:00 AM

good explanation

B
BigMouthDog
1/22/2022 8:17:00 PM

hi team just want to know if there is any update version of the exam 350-401

F
francesco
10/30/2023 11:08:00 AM

helpful on 2017 scrum guide

A
Amitabha Roy
10/5/2023 3:16:00 AM

planning to attempt for the exam.

P
Prem Yadav
7/29/2023 6:20:00 AM

pleaseee upload

A
Ahmed Hashi
7/6/2023 5:40:00 PM

thanks ly so i have information cia

M
mansi
5/31/2023 7:58:00 AM

hello team, i need sap qm dumps for practice

J
Jamil aljamil
12/4/2023 4:47:00 AM

it’s good but not senatios based

C
Cath
10/10/2023 10:19:00 AM

q.119 - the correct answer is b - they are not captured in an update set as theyre data.

P
P
1/6/2024 11:22:00 AM

good matter

S
surya
7/30/2023 2:02:00 PM

please upload c_sacp_2308

S
Sasuke
7/11/2023 10:30:00 PM

please upload the dump. thanks very much !!

V
V
7/4/2023 8:57:00 AM

good questions

T
TTB
8/22/2023 5:30:00 AM

hi, could you please update the latest dump version

T
T
7/28/2023 9:06:00 PM

this question is keep repeat : you are developing a sales application that will contain several azure cloud services and handle different components of a transaction. different cloud services will process customer orders, billing, payment, inventory, and shipping. you need to recommend a solution to enable the cloud services to asynchronously communicate transaction information by using xml messages. what should you include in the recommendation?

G
Gurgaon
9/28/2023 4:35:00 AM

great questions

W
wasif
10/11/2023 2:22:00 AM

its realy good

S
Shubhra Rathi
8/26/2023 1:12:00 PM

oracle 1z0-1059-22 dumps

L
Leo
7/29/2023 8:48:00 AM

please share me the pdf..

A
AbedRabbou Alaqabna
12/18/2023 3:10:00 AM

q50: which two functions can be used by an end user when pivoting an interactive report? the correct answer is a, c because we do not have rank in the function pivoting you can check in the apex app

R
Rohan Limaye
12/30/2023 8:52:00 AM

best to practice

A
Aparajeeta
10/13/2023 2:42:00 PM

so far it is good

V
Vgf
7/20/2023 3:59:00 PM

please provide me the dump

D
Deno
10/25/2023 1:14:00 AM

i failed the cisa exam today. but i have found all the questions that were on the exam to be on this site.

C
CiscoStudent
11/15/2023 5:29:00 AM

in question 272 the right answer states that an autonomous acces point is "configured and managed by the wlc" but this is not what i have learned in my ccna course. is this a mistake? i understand that lightweight aps are managed by wlc while autonomous work as standalones on the wlan.

P
pankaj
9/28/2023 4:36:00 AM

it was helpful

U
User123
10/8/2023 9:59:00 AM

good question

V
vinay
9/4/2023 10:23:00 AM

really nice

U
Usman
8/28/2023 10:07:00 AM

please i need dumps for isc2 cybersecuity

Q
Q44
7/30/2023 11:50:00 AM

ans is coldline i think

A
Anuj
12/21/2023 1:30:00 PM

very helpful

AI Tutor 👋 I’m here to help!