You are the project manager for Bluewell Inc. You are studying the documentation of project plan. The documentation states that there are twenty-five stakeholders with the project. What will be the number of communication channel s for the project?

  1. 20
  2. 100
  3. 50
  4. 300

Answer(s): D

Explanation:

Communication channels are paths of communication with stakeholders in a project. The number of communication channels shows the complexity of a project's communication and can be derived through the formula shown below:
Total Number of Communication Channels = n (n-1)/2 where n is the number of stakeholders.

Hence, a project having five stakeholders will have ten communication channels. Putting the value of the number of stakeholders in the formula will provide the number of communication channels.

Hence, Number of communication channel = (n (n-1)) / 2
= (25 (25-1)) / 2
= (25 x 24) / 2
= 600 / 2
= 300

Incorrect Answers:
A, B, C: These are not valid number of communication channels for the given scenario.



Which of the following are the common mistakes while implementing KRIs? Each correct answer represents a complete solution. Choose three.

  1. Choosing KRIs that are difficult to measure
  2. Choosing KRIs that has high correlation with the risk
  3. Choosing KRIs that are incomplete or inaccurate due to unclear specifications
  4. Choosing KRIs that are not linked to specific risk

Answer(s): A,C,D

Explanation:

A common mistake when implementing KRIs other than selecting too many KRIs includes choosing KRIs that are:
Not linked to specific risk
Incomplete or inaccurate due to unclear specifications Too generic
Difficult to aggregate, compare and interpret Difficult to measure

Incorrect Answers:
B: For ensuring high reliability of the KRI, The indicator must possess a high correlation with the risk and be a good predictor or outcome measure. Hence KRIs are chosen that has high correlation with the risk.



Which of the following control audit is performed to assess the efficiency of the productivity in the operations environment?

  1. Operational
  2. Financial
  3. Administrative
  4. Specialized

Answer(s): A



Billy is the project manager of the HAR Project and is in month six of the project. The project is scheduled to last for 18 months.

Management asks Billy how often the project team is participating in risk reassessment in this project. What should Billy tell management if he's following the best practices for risk management?

  1. Project risk management has been concluded with the project planning.
  2. Project risk management happens at every milestone.
  3. Project risk management is scheduled for every month in the 18-month project.
  4. At every status meeting the project team project risk management is an agenda item.

Answer(s): D

Explanation:

Risk management is an ongoing project activity. It should be an agenda item at every project status meeting. Incorrect Answers:
A: Risk management happens throughout the project as does project planning.

B: Milestones are good times to do reviews, but risk management should happen frequently.

C: This answer would only be correct if the project has a status meeting just once per month in the project.



You are the project manager of the NGQQ Project for your company. To help you communicate project status to your stakeholders, you are going to create a stakeholder register. All of the following information should be included in the stakeholder register except for which one?

  1. Stakeholder management strategy
  2. Assessment information of the stakeholders' major requirements, expectations, and potential influence
  3. Identification information for each stakeholder
  4. Stakeholder classification of their role in the project

Answer(s): A

Explanation:

The stakeholder management strategy is generally not included in the stakeholder registry because it may contain sensitive information that should not be shared with project team members or certain other individuals that could see the stakeholder register. The stakeholder register is a project management document that contains a list of the stakeholders associated with the project. It assesses how they are involved in the project and identifies what role they play in the organization. The information in this document can be very perceptive and is meant for limited exchange only. It also contains relevant information about the stakeholders, such as their requirements, expectations, and influence on the project.

Incorrect Answers:
B, C, D: Stakeholder identification, Assessment information, and Stakeholder classification should be included in the stakeholder register.



Share your comments for ISACA CRISC exam with other users:

K
Kenneth
12/8/2023 7:34:00 AM

thank you for the test materials!

H
Harjinder Singh
8/9/2023 4:16:00 AM

its very helpful

S
SD
7/13/2023 12:56:00 AM

good questions

K
kanjoe
7/2/2023 11:40:00 AM

good questons

M
Mahmoud
7/6/2023 4:24:00 AM

i need the dumb of the hcip security v4.0 exam

W
Wei
8/3/2023 4:18:00 AM

upload the dump please

S
Stephen
10/3/2023 6:24:00 PM

yes, iam looking this

S
Stephen
8/4/2023 9:08:00 PM

please upload cima e2 managing performance dumps

H
hp
6/16/2023 12:44:00 AM

wonderful questions

P
Priyo
11/14/2023 2:23:00 AM

i used this site since 2000, still great to support my career

J
Jude
8/29/2023 1:56:00 PM

why is the answer to "which of the following is required by scrum?" all of the following stated below since most of them are not mandatory? sprint retrospective. members must be stand up at the daily scrum. sprint burndown chart. release planning.

M
Marc blue
9/15/2023 4:11:00 AM

great job. hope this helps out.

A
Anne
9/13/2023 2:33:00 AM

upload please. many thanks!

P
pepe el toro
9/12/2023 7:55:00 PM

this is so interesting

A
Antony
11/28/2023 12:13:00 AM

great material thanks

T
Thembelani
5/30/2023 2:22:00 AM

anyone who wrote this exam recently

P
P
9/16/2023 1:27:00 AM

ok they re good

J
Jorn
7/13/2023 5:05:00 AM

relevant questions

A
AM
6/20/2023 7:54:00 PM

please post

N
Nagendra Pedipina
7/13/2023 2:22:00 AM

q:42 there has to be a image in the question to choose what does it mean from the options

B
BrainDumpee
11/18/2023 1:36:00 PM

looking for cphq dumps, where can i find these for free? please and thank you.

S
sheik
10/14/2023 11:37:00 AM

@aarun , thanks for the information. it would be great help if you share your email

R
Random user
12/11/2023 1:34:00 AM

1z0-1078-23 need this dumps

L
labuschanka
11/16/2023 6:06:00 PM

i gave the microsoft azure az-500 tests and prepared from this site as it has latest mock tests available which helped me evaluate my performance and score 919/1000

M
Marianne
10/22/2023 11:57:00 PM

i cannot see the button to go to the questions

S
sushant
6/28/2023 4:52:00 AM

good questions

A
A\MAM
6/27/2023 5:17:00 PM

q-6 ans-b correct. https://docs.paloaltonetworks.com/pan-os/9-1/pan-os-cli-quick-start/use-the-cli/commit-configuration-changes

U
unanimous
12/15/2023 6:38:00 AM

very nice very nice

A
akminocha
9/28/2023 10:36:00 AM

please help us with 1z0-1107-2 dumps

J
Jefi
9/4/2023 8:15:00 AM

please upload the practice questions

T
Thembelani
5/30/2023 2:45:00 AM

need this dumps

A
Abduraimov
4/19/2023 12:43:00 AM

preparing for this exam is overwhelming. you cannot pass without the help of these exam dumps.

P
Puneeth
10/5/2023 2:06:00 AM

new to this site but i feel it is good

A
Ashok Kumar
1/2/2024 6:53:00 AM

the correct answer to q8 is b. explanation since the mule app has a dependency, it is necessary to include project modules and dependencies to make sure the app will run successfully on the runtime on any other machine. source code of the component that the mule app is dependent of does not need to be included in the exported jar file, because the source code is not being used while executing an app. compiled code is being used instead.

AI Tutor 👋 I’m here to help!