Which of the following is the best reason for performing risk assessment?

  1. To determine the present state of risk
  2. To analyze the effect on the business
  3. To satisfy regulatory requirements
  4. To budget appropriately for the application of various controls

Answer(s): A

Explanation:

Risk assessment is a process of analyzing the identified risk, both quantitatively and qualitatively. Quantitative risk assessment requires calculations of two components of risk, the magnitude of the potential loss, and the probability that the loss will occur. While qualitatively risk assessment checks the severity of risk. Hence risk assessment helps in determining the present state of the risk.

Incorrect Answers:
B: Analyzing the effect of risk on an enterprise is the part of the process while performing risk assessment, but is not the reason for doing it.

C: Performing risk assessment may satisfy the regulatory requirements, but is not the reason to perform risk assessment.

D: Budgeting appropriately is one the results of risk assessment but is not the reason for performing the risk assessment.



You are the project manager of GHT project. You identified a risk of noncompliance with regulations due to missing of a number of relatively simple procedures.

The response requires creating the missing procedures and implementing them. In which of the following risk response prioritization should this case be categorized?

  1. Business case to be made
  2. Quick win
  3. Risk avoidance
  4. Deferrals

Answer(s): B

Explanation:

This is categorized as a "quick win" because the allocation of existing resources or a minor resource investment provides measurable benefits. Quick win is very effective and efficient response that addresses medium to high risk.

Incorrect Answers:
A: "Business case to be made" requires careful analysis and management decisions on investments that are more expensive or difficult risk responses to medium to high risk. Here in this scenario, there is only minor investment that is why, it is not "business case to be made".

C: Risk avoidance is a type of risk response and not risk response prioritization option.

D: Deferral addresses costly risk response to a low risk, and hence in this specified scenario it is not used.



What are the PRIMARY objectives of a control?

  1. Detect, recover, and attack
  2. Prevent, respond, and log
  3. Prevent, control, and attack
  4. Prevent, recover, and detect

Answer(s): D

Explanation:

Controls are the policies, procedures, practices and guidelines designed to provide appropriate assurance that business objectives are achieved and undesired events are detected, prevented, and corrected. Controls, or countermeasures, will reduce or neutralize threats or vulnerabilities.

Controls have three primary objectives: Prevent
Recover Detect

Incorrect Answers:
A, B, C: One or more objectives stated in these choices is not correct objective of control.



You work as the project manager for Company Inc. The project on which you are working has several risks that will affect several stakeholder requirements. Which project management plan will define who will be available to share information on the project risks?

  1. Resource Management Plan
  2. Communications Management Plan
  3. Risk Management Plan
  4. Stakeholder management strategy

Answer(s): B

Explanation:

The Communications Management Plan defines, in regard to risk management, who will be available to share information on risks and responses throughout the project.

The Communications Management Plan aims to define the communication necessities for the project and how the information will be circulated. The Communications Management Plan sets the communication structure for the project. This structure provides guidance for communication throughout the project's life and is updated as communication needs change. The Communication Managements Plan identifies and defines the roles of persons concerned with the project. It includes a matrix known as the communication matrix to map the communication requirements of the project.

Incorrect Answers:
A: The Resource Management Plan does not define risk communications.

C: The Risk Management Plan deals with risk identification, analysis, response, and monitoring. D: The stakeholder management strategy does not address risk communications.



Sensitive data has been lost after an employee inadvertently removed a file from the premises, in violation of organizational policy. Which of the following controls MOST likely failed?

  1. Background checks
  2. Awareness training
  3. User access
  4. Policy management

Answer(s): C



Viewing Page 60 of 361



Share your comments for ISACA CRISC exam with other users:

Varun 10/29/2023 9:11:00 PM

great question
Anonymous


Doc 10/29/2023 9:36:00 PM

question: a user wants to start a recruiting posting job posting. what must occur before the posting process can begin? 3 ans: comment- option e is incorrect reason: as part of enablement steps, sap recommends that to be able to post jobs to a job board, a user need to have the correct permission and secondly, be associated with one posting profile at minimum
UNITED KINGDOM


It‘s not A 9/17/2023 5:31:00 PM

answer to question 72 is d [sys_user_role]
Anonymous


indira m 8/14/2023 12:15:00 PM

please provide the pdf
UNITED STATES


ribrahim 8/1/2023 6:05:00 AM

hey guys, just to let you all know that i cleared my 312-38 today within 1 hr with 100 questions and passed. thank you so much brain-dumps.net all the questions that ive studied in this dump came out exactly the same word for word "verbatim". you rock brain-dumps.net!!! section name total score gained score network perimeter protection 16 11 incident response 10 8 enterprise virtual, cloud, and wireless network protection 12 8 application and data protection 13 10 network défense management 10 9 endpoint protection 15 12 incident d
SINGAPORE


Andrew 8/23/2023 6:02:00 PM

very helpful
Anonymous


latha 9/7/2023 8:14:00 AM

useful questions
GERMANY


ibrahim 11/9/2023 7:57:00 AM

page :20 https://exam-dumps.com/snowflake/free-cof-c02-braindumps.html?p=20#collapse_453 q 74: true or false: pipes can be suspended and resumed. true. desc.: pausing or resuming pipes in addition to the pipe owner, a role that has the following minimum permissions can pause or resume the pipe https://docs.snowflake.com/en/user-guide/data-load-snowpipe-intro
FINLAND


Franklin Allagoa 7/5/2023 5:16:00 AM

i want hcia exam dumps
Anonymous


SSA 12/24/2023 1:18:00 PM

good training
Anonymous


BK 8/11/2023 12:23:00 PM

very useful
INDIA


Deepika Narayanan 7/13/2023 11:05:00 PM

yes need this exam dumps
Anonymous


Blessious Phiri 8/15/2023 3:31:00 PM

these questions are a great eye opener
Anonymous


Jagdesh 9/8/2023 8:17:00 AM

thank you for providing these questions and answers. they helped me pass my exam. you guys are great.
CANADA


TS 7/18/2023 3:32:00 PM

good knowledge
Anonymous


Asad Khan 11/1/2023 2:44:00 AM

answer 10 should be a because only a new project will be created & the organization is the same.
Anonymous


Raj 9/12/2023 3:49:00 PM

can you please upload the dump again
UNITED STATES


Christian Klein 6/23/2023 1:32:00 PM

is it legit questions from sap certifications ?
UNITED STATES


anonymous 1/12/2024 3:34:00 PM

question 16 should be b (changing the connector settings on the monitor) pc and monitor were powered on. the lights on the pc are on indicating power. the monitor is showing an error text indicating that it is receiving power too. this is a clear sign of having the wrong input selected on the monitor. thus, the "connector setting" needs to be switched from hdmi to display port on the monitor so it receives the signal from the pc, or the other way around (display port to hdmi).
UNITED STATES


NSPK 1/18/2024 10:26:00 AM

q 10. ans is d (in the target org: open deployment settings, click edit next to the source org. select allow inbound changes and save
Anonymous


mohamed abdo 9/1/2023 4:59:00 AM

very useful
Anonymous


Tom 3/18/2022 8:00:00 PM

i purchased this exam dumps from another website with way more questions but they were all invalid and outdate. this exam dumps was right to the point and all from recent exam. it was a hard pass.
UNITED KINGDOM


Edrick GOP 10/24/2023 6:00:00 AM

it was a good experience and i got 90% in the 200-901 exam.
Anonymous


anonymous 8/10/2023 2:28:00 AM

hi please upload this
Anonymous


Bakir 7/6/2023 7:24:00 AM

please upload it
UNITED KINGDOM


Aman 6/18/2023 1:27:00 PM

really need this dump. can you please help.
UNITED KINGDOM


Neela Para 1/8/2024 6:39:00 PM

really good and covers many areas explaining the answer.
NEW ZEALAND


Karan Patel 8/15/2023 12:51:00 AM

yes, can you please upload the exam?
UNITED STATES


NISHAD 11/7/2023 11:28:00 AM

how many questions are there in these dumps?
UNITED STATES


Pankaj 7/3/2023 3:57:00 AM

hi team, please upload this , i need it.
UNITED STATES


DN 9/4/2023 11:19:00 PM

question 14 - run terraform import: this is the recommended best practice for bringing manually created or destroyed resources under terraform management. you use terraform import to associate an existing resource with a terraform resource configuration. this ensures that terraform is aware of the resource, and you can subsequently manage it with terraform.
Anonymous


Zhiguang 8/19/2023 11:37:00 PM

please upload dump. thanks in advance.
Anonymous


deedee 12/23/2023 5:51:00 PM

great great
UNITED STATES


Asad Khan 11/1/2023 3:10:00 AM

answer 16 should be b your organizational policies require you to use virtual machines directly
Anonymous