Which of the following is the PRIMARY requirement before choosing Key performance indicators of an enterprise?

  1. Determine size and complexity of the enterprise
  2. Prioritize various enterprise processes
  3. Determine type of market in which the enterprise operates
  4. Enterprise must establish its strategic and operational goals

Answer(s): D

Explanation:

Key Performance Indicators is a set of measures that a company or industry uses to measure and/or compare performance in terms of meeting their strategic and operational goals. KPIs vary with company to company, depending on their priorities or performance criteria.
A company must establish its strategic and operational goals and then choose their KPIs which can best reflect those goals. For example, if a software company's goal is to have the fastest growth in its industry, its main performance indicator may be the measure of its annual revenue growth.

Incorrect Answers:
A: Determination of size and complexity of the enterprise is the selection criteria of the KRI, not KPI. KPI does not have any relevancy with size and complexity of the enterprise.

B: This is not the valid answer.

C: Type of market in which the enterprise is operating do not affect the selection of KPIs.



You are the project manager of project for a client. The client has promised your company a bonus, if the project is completed early. After studying the project work, you elect to crash the project in order to realize the early end date. This is an example of what type of risk response?

  1. Negative risk response, because crashing will add risks.
  2. Positive risk response, as crashing is an example of enhancing.
  3. Positive risk response, as crashing is an example of exploiting.
  4. Negative risk response, because crashing will add costs.

Answer(s): C



Judy has identified a risk event in her project that will have a high probability and a high impact. Based on the requirements of the project, Judy has asked to change the project scope to remove the associated requirement and the associated risk. What type of risk response is this?

  1. Exploit
  2. Not a risk response, but a change request
  3. Avoidance
  4. Transference

Answer(s): C

Explanation:

Risk avoidance involves changing the project management plan to eliminate the threat entirely. The project manager may also isolate the project objectives from the risk's impact or change the objective that is in jeopardy. Examples of this include extending the schedule, changing the strategy, or reducing the scope. The most radical avoidance strategy is to shut down the project entirely. Some risks that arise early in the project can be avoided by clarifying requirements, obtaining information, improving communication, or acquiring expertise.

Incorrect Answers:
A: Exploit risk response is used for positive risk or opportunity, not for negative risk.

B: This risk response does require a change request, in some instances, but it's the avoidance risk response and not just a change request.

D: Transference allows the risk to be transferred, not removed from the project, to a third party. Transference usually requires a contractual relationship with the third party.



You are the risk professional of your enterprise. You have performed cost and benefit analysis of control that you have adopted. What are all the benefits of performing cost and benefit analysis of control? Each correct answer represents a complete solution. Choose three.

  1. It helps in determination of the cost of protecting what is important
  2. It helps in taking risk response decisions
  3. It helps in providing a monetary impact view of risk
  4. It helps making smart choices based on potential risk mitigation costs and losses

Answer(s): A,C,D



You are the project manager of GHT project. You want to perform post-project review of your project. What is the BEST time to perform post-project review by you and your project development team to access the effectiveness of the project?

  1. Project is completed and the system has been in production for a sufficient time period
  2. During the project
  3. Immediately after the completion of the project
  4. Project is about to complete

Answer(s): A

Explanation:

The project development team and appropriate end users perform a post-project review jointly after the project has been completed and the system has been in production for a sufficient time period to assess its effectiveness.

Incorrect Answers:
B: The post-project review of project for accessing effectiveness cannot be done during the project as effectiveness can only evaluated after setting the project in process of production.

C: It is not done immediately after the completion of the project as its effectiveness cannot be measured until the system has been in production for certain time period.

D: Post-project review for evaluating the effectiveness of the project can only be done after the completion of the project and the project is in production phase.



Share your comments for ISACA CRISC exam with other users:

T
tumz
1/16/2024 10:30:00 AM

very helpful

N
NRI
8/27/2023 10:05:00 AM

will post once the exam is finished

K
kent
11/3/2023 10:45:00 AM

relevant questions

Q
Qasim
6/11/2022 9:43:00 AM

just clear exam on 10/06/2202 dumps is valid all questions are came same in dumps only 2 new questions total 46 questions 1 case study with 5 question no lab/simulation in my exam please check the answers best of luck

C
Cath
10/10/2023 10:09:00 AM

q.112 - correct answer is c - the event registry is a module that provides event definitions. answer a - not correct as it is the definition of event log

S
Shiji
10/15/2023 1:31:00 PM

good and useful.

A
Ade
6/25/2023 1:14:00 PM

good questions

P
Praveen P
11/8/2023 5:18:00 AM

good content

A
Anastasiia
12/28/2023 9:06:00 AM

totally not correct answers. 21. you have one gcp account running in your default region and zone and another account running in a non-default region and zone. you want to start a new compute engine instance in these two google cloud platform accounts using the command line interface. what should you do? correct: create two configurations using gcloud config configurations create [name]. run gcloud config configurations activate [name] to switch between accounts when running the commands to start the compute engine instances.

P
Priyanka
7/24/2023 2:26:00 AM

kindly upload the dumps

N
Nabeel
7/25/2023 4:11:00 PM

still learning

G
gure
7/26/2023 5:10:00 PM

excellent way to learn

C
ciken
8/24/2023 2:55:00 PM

help so much

B
Biswa
11/20/2023 9:28:00 AM

understand sql col.

S
Saint Pierre
10/24/2023 6:21:00 AM

i would give 5 stars to this website as i studied for az-800 exam from here. it has all the relevant material available for preparation. i got 890/1000 on the test.

R
Rose
7/24/2023 2:16:00 PM

this is nice.

A
anon
10/15/2023 12:21:00 PM

q55- the ridac workflow can be modified using flow designer, correct answer is d not a

N
NanoTek3
6/13/2022 10:44:00 PM

by far this is the most accurate exam dumps i have ever purchased. all questions are in the exam. i saw almost 90% of the questions word by word.

E
eriy
11/9/2023 5:12:00 AM

i cleared the az-104 exam by scoring 930/1000 on the exam. it was all possible due to this platform as it provides premium quality service. thank you!

M
Muhammad Rawish Siddiqui
12/8/2023 8:12:00 PM

question # 232: accessibility, privacy, and innovation are not data quality dimensions.

V
Venkat
12/27/2023 9:04:00 AM

looks wrong answer for 443 question, please check and update

V
Varun
10/29/2023 9:11:00 PM

great question

D
Doc
10/29/2023 9:36:00 PM

question: a user wants to start a recruiting posting job posting. what must occur before the posting process can begin? 3 ans: comment- option e is incorrect reason: as part of enablement steps, sap recommends that to be able to post jobs to a job board, a user need to have the correct permission and secondly, be associated with one posting profile at minimum

I
It‘s not A
9/17/2023 5:31:00 PM

answer to question 72 is d [sys_user_role]

I
indira m
8/14/2023 12:15:00 PM

please provide the pdf

R
ribrahim
8/1/2023 6:05:00 AM

hey guys, just to let you all know that i cleared my 312-38 today within 1 hr with 100 questions and passed. thank you so much brain-dumps.net all the questions that ive studied in this dump came out exactly the same word for word "verbatim". you rock brain-dumps.net!!! section name total score gained score network perimeter protection 16 11 incident response 10 8 enterprise virtual, cloud, and wireless network protection 12 8 application and data protection 13 10 network défense management 10 9 endpoint protection 15 12 incident d

A
Andrew
8/23/2023 6:02:00 PM

very helpful

L
latha
9/7/2023 8:14:00 AM

useful questions

I
ibrahim
11/9/2023 7:57:00 AM

page :20 https://exam-dumps.com/snowflake/free-cof-c02-braindumps.html?p=20#collapse_453 q 74: true or false: pipes can be suspended and resumed. true. desc.: pausing or resuming pipes in addition to the pipe owner, a role that has the following minimum permissions can pause or resume the pipe https://docs.snowflake.com/en/user-guide/data-load-snowpipe-intro

F
Franklin Allagoa
7/5/2023 5:16:00 AM

i want hcia exam dumps

S
SSA
12/24/2023 1:18:00 PM

good training

B
BK
8/11/2023 12:23:00 PM

very useful

D
Deepika Narayanan
7/13/2023 11:05:00 PM

yes need this exam dumps

B
Blessious Phiri
8/15/2023 3:31:00 PM

these questions are a great eye opener

AI Tutor 👋 I’m here to help!