ISACA CRISC Exam (page: 41)
ISACA Certified in Risk and Information Systems Control
Updated on: 17-Feb-2026

Viewing Page 41 of 361

To which level the risk should be reduced to accomplish the objective of risk management?

  1. To a level where ALE is lower than SLE
  2. To a level where ARO equals SLE
  3. To a level that an organization can accept
  4. To a level that an organization can mitigate

Answer(s): C

Explanation:

The main objective of risk management is to reduce risk to a level that the organization or company will accept, as the risk can never be completely eliminated.

Incorrect Answers:
A, B: There are no such concepts existing in manipulating risk level.

D: Risk mitigation involves identification, planning, and conduct of actions for reducing risk. Because the elimination of all risk is usually impractical or close to impossible, it is aimed at reducing risk to an acceptable level with minimal adverse impact on the organization's resources and mission.



You are the project manager of GHT project. Your hardware vendor left you a voicemail saying that the delivery of the equipment you have ordered would not arrive on time. You identified a risk response strategy for this risk and have arranged for a local company to lease you the needed equipment until yours arrives. This is an example of which risk response strategy?

  1. Avoid
  2. Transfer
  3. Acceptance
  4. Mitigate

Answer(s): D

Explanation:

Mitigation attempts to reduce the impact of a risk event in case it occurs. Making plans to arrange for the leased equipment reduces the consequences of the risk and hence this response in mitigation.
B: Risk transfer means that impact of risk is reduced by transferring or otherwise sharing a portion of the risk with an external organization or another internal entity. Transfer of risk can occur in many forms but is most effective when dealing with financial risks. Insurance is one form of risk transfer.
Here there no such action is taken, hence it is not a risk transfer.

Incorrect Answers:
A: Risk avoidance means to evade risk altogether, eliminate the cause of the risk event, or change the project plan to protect the project objectives from the risk event. Risk avoidance is applied when the level of risk, even after the applying controls, would be greater than the risk tolerance level of the enterprise. Hence this risk response is adopted when:
There is no other cost-effective response that can successfully reduce the likelihood and magnitude below the defined thresholds for risk appetite.
The risk cannot be shared or transferred.
The risk is deemed unacceptable by management.

C: Risk acceptance means that no action is taken relative to a particular risk; loss is accepted if it occurs. If an enterprise adopts a risk acceptance, it should carefully consider who can accept the risk. Risk should be accepted only by senior management in relationship with senior management and the board. There are two alternatives to the acceptance strategy, passive and active.
Passive acceptance means that enterprise has made no plan to avoid or mitigate the risk but willing to accept the consequences of the risk.
Active acceptance is the second strategy and might include developing contingency plans and reserves to deal with risks.



Who is at the BEST authority to develop the priorities and identify what risks and impacts would occur if there were loss of the organization's private information?

  1. External regulatory agencies
  2. Internal auditor
  3. Business process owners
  4. Security management

Answer(s): C



You are the project manager for TTP project. You are in the Identify Risks process. You have to create the risk register. Which of the following are included in the risk register?
Each correct answer represents a complete solution. (Choose two.)

  1. List of potential responses
  2. List of key stakeholders
  3. List of mitigation techniques
  4. List of identified risks

Answer(s): A,D

Explanation:

Risk register primarily contains the following:
List of identified risks: A reasonable description of the identified risks is noted in the risk register. The description includes event, cause, effect, impact related to the risks identified. In addition to the list of identified risks, the root causes of those risks may appear in the risk register.
List of potential responses: Potential responses to a risk may be identified during the Identify Risks process. These responses are useful as inputs to the Plan Risk Responses process.

Incorrect Answers:
B: This is not a valid content of risk register.
A risk register is an inventory of risks and exposure associated with those risks. Risks are commonly found in project management practices, and provide information to identify, analyze, and manage risks. Typically a risk register contains:
A description of the risk
The impact should this event actually occur The probability of its occurrence
Risk Score (the multiplication of Probability and Impact)
A summary of the planned response should the event occur
A summary of the mitigation (the actions taken in advance to reduce the probability and/or impact of the event)
Ranking of risks by Risk Score so as to highlight the highest priority risks to all involved.

C: Risk register do contain the summary of mitigation, but only after the applying risk response. Here in this scenario you are in risk identification phase, hence mitigation techniques cannot be documented at this situation.



You work as a project manager for BlueWell Inc. You are about to complete the quantitative risk analysis process for your project. You can use three available tools and techniques to complete this process. Which one of the following is NOT a tool or technique that is appropriate for the quantitative risk analysis process?

  1. Data gathering and representation techniques
  2. Expert judgment
  3. Quantitative risk analysis and modeling techniques
  4. Organizational process assets

Answer(s): D

Explanation:

Organizational process asset is not a tool and technique, but an input to the quantitative risk analysis process. Quantitative Risk Analysis is a process to assess the probability of achieving particular project objectives, to quantify the effect of risks on the whole project objective, and to prioritize the risks based on the impact to overall project risk. Quantitative Risk Analysis process analyzes the affect of a risk event deriving a numerical value. It also presents a quantitative approach to build decisions in the presence of uncertainty. The inputs for Quantitative Risk Analysis are:

Organizational process assets Project Scope Statement
Risk Management Plan Risk Register
Project Management Plan

Incorrect Answers:
A: Data gathering and representation technique is a tool and technique for the quantitative risk analysis process.

B: Expert judgment is a tool and technique for the quantitative risk analysis process.

C: Quantitative risk analysis and modeling techniques is a tool and technique for the quantitative risk analysis process.



Viewing Page 41 of 361



Share your comments for ISACA CRISC exam with other users:

Romero 3/23/2022 4:20:00 PM

i never use these dumps sites but i had to do it for this exam as it is impossible to pass without using these question dumps.
UNITED STATES


John Kennedy 9/20/2023 3:33:00 AM

good practice and well sites.
Anonymous


Nenad 7/12/2022 11:05:00 PM

passed my first exam last week and pass the second exam this morning. thank you sir for all the help and these brian dumps.
INDIA


Lucky 10/31/2023 2:01:00 PM

does anyone who attended exam csa 8.8, can confirm these questions are really coming ? or these are just for practicing?
HONG KONG


Prateek 9/18/2023 11:13:00 AM

kindly share the dumps
UNITED STATES


Irfan 11/25/2023 1:26:00 AM

very nice content
Anonymous


php 6/16/2023 12:49:00 AM

passed today
Anonymous


Durga 6/23/2023 1:22:00 AM

hi can you please upload questions
Anonymous


JJ 5/28/2023 4:32:00 AM

please upload quetions
THAILAND


Norris 1/3/2023 8:06:00 PM

i passed my exam thanks to this braindumps questions. these questions are valid in us and i highly recommend it!
UNITED STATES


abuti 7/21/2023 6:10:00 PM

are they truely latest
Anonymous


Curtis Nakawaki 7/5/2023 8:46:00 PM

questions appear contemporary.
UNITED STATES


Vv 12/2/2023 6:31:00 AM

good to prepare in this site
UNITED STATES


praveenkumar 11/20/2023 11:57:00 AM

very helpful to crack first attempt
Anonymous


asad Raza 5/15/2023 5:38:00 AM

please upload this exam
CHINA


Reeta 7/17/2023 5:22:00 PM

please upload the c_activate22 dump questions with answer
SWEDEN


Wong 12/20/2023 11:34:00 AM

q10 - the answer should be a. if its c, the criteria will meet if either the prospect is not part of the suppression lists or if the job title contains vice president
MALAYSIA


david 12/12/2023 12:38:00 PM

this was on the exam as of 1211/2023
Anonymous


Tink 7/24/2023 9:23:00 AM

great for prep
GERMANY


Jaro 12/18/2023 3:12:00 PM

i think in question 7 the first answer should be power bi portal (not power bi)
Anonymous


9eagles 4/7/2023 10:04:00 AM

on question 10 and so far 2 wrong answers as evident in the included reference link.
Anonymous


Tai 8/28/2023 5:28:00 AM

wonderful material
SOUTH AFRICA


VoiceofMidnight 12/29/2023 4:48:00 PM

i passed!! ...but barely! got 728, but needed 720 to pass. the exam hit me with labs right out of the gate! then it went to multiple choice. protip: study the labs!
UNITED STATES


A K 8/3/2023 11:56:00 AM

correct answer for question 92 is c -aws shield
Anonymous


Nitin Mindhe 11/27/2023 6:12:00 AM

great !! it is really good
IRELAND


BailleyOne 11/22/2023 1:45:00 AM

explanations for the answers are to the point.
Anonymous


patel 10/25/2023 8:17:00 AM

how can rea next
INDIA


MortonG 10/19/2023 6:32:00 PM

question: 128 d is the wrong answer...should be c
EUROPEAN UNION


Jayant 11/2/2023 3:15:00 AM

thanks for az 700 dumps
Anonymous


Bipul Mishra 12/14/2023 7:12:00 AM

thank you for this tableau dumps . it will helpfull for tableau certification
UNITED STATES


hello 10/31/2023 12:07:00 PM

good content
Anonymous


Matheus 9/3/2023 2:14:00 PM

just testing if the comments are real
UNITED STATES


yenvti2@gmail.com 8/12/2023 7:56:00 PM

very helpful for exam preparation
Anonymous


Miguel 10/5/2023 12:16:00 PM

question 11: https://help.salesforce.com/s/articleview?id=sf.admin_lead_to_patient_setup_overview.htm&type=5
SPAIN