ISACA CRISC Exam (page: 41)
ISACA Certified in Risk and Information Systems Control
Updated on: 25-Dec-2025

Viewing Page 41 of 361

To which level the risk should be reduced to accomplish the objective of risk management?

  1. To a level where ALE is lower than SLE
  2. To a level where ARO equals SLE
  3. To a level that an organization can accept
  4. To a level that an organization can mitigate

Answer(s): C

Explanation:

The main objective of risk management is to reduce risk to a level that the organization or company will accept, as the risk can never be completely eliminated.

Incorrect Answers:
A, B: There are no such concepts existing in manipulating risk level.

D: Risk mitigation involves identification, planning, and conduct of actions for reducing risk. Because the elimination of all risk is usually impractical or close to impossible, it is aimed at reducing risk to an acceptable level with minimal adverse impact on the organization's resources and mission.



You are the project manager of GHT project. Your hardware vendor left you a voicemail saying that the delivery of the equipment you have ordered would not arrive on time. You identified a risk response strategy for this risk and have arranged for a local company to lease you the needed equipment until yours arrives. This is an example of which risk response strategy?

  1. Avoid
  2. Transfer
  3. Acceptance
  4. Mitigate

Answer(s): D

Explanation:

Mitigation attempts to reduce the impact of a risk event in case it occurs. Making plans to arrange for the leased equipment reduces the consequences of the risk and hence this response in mitigation.
B: Risk transfer means that impact of risk is reduced by transferring or otherwise sharing a portion of the risk with an external organization or another internal entity. Transfer of risk can occur in many forms but is most effective when dealing with financial risks. Insurance is one form of risk transfer.
Here there no such action is taken, hence it is not a risk transfer.

Incorrect Answers:
A: Risk avoidance means to evade risk altogether, eliminate the cause of the risk event, or change the project plan to protect the project objectives from the risk event. Risk avoidance is applied when the level of risk, even after the applying controls, would be greater than the risk tolerance level of the enterprise. Hence this risk response is adopted when:
There is no other cost-effective response that can successfully reduce the likelihood and magnitude below the defined thresholds for risk appetite.
The risk cannot be shared or transferred.
The risk is deemed unacceptable by management.

C: Risk acceptance means that no action is taken relative to a particular risk; loss is accepted if it occurs. If an enterprise adopts a risk acceptance, it should carefully consider who can accept the risk. Risk should be accepted only by senior management in relationship with senior management and the board. There are two alternatives to the acceptance strategy, passive and active.
Passive acceptance means that enterprise has made no plan to avoid or mitigate the risk but willing to accept the consequences of the risk.
Active acceptance is the second strategy and might include developing contingency plans and reserves to deal with risks.



Who is at the BEST authority to develop the priorities and identify what risks and impacts would occur if there were loss of the organization's private information?

  1. External regulatory agencies
  2. Internal auditor
  3. Business process owners
  4. Security management

Answer(s): C



You are the project manager for TTP project. You are in the Identify Risks process. You have to create the risk register. Which of the following are included in the risk register?
Each correct answer represents a complete solution. (Choose two.)

  1. List of potential responses
  2. List of key stakeholders
  3. List of mitigation techniques
  4. List of identified risks

Answer(s): A,D

Explanation:

Risk register primarily contains the following:
List of identified risks: A reasonable description of the identified risks is noted in the risk register. The description includes event, cause, effect, impact related to the risks identified. In addition to the list of identified risks, the root causes of those risks may appear in the risk register.
List of potential responses: Potential responses to a risk may be identified during the Identify Risks process. These responses are useful as inputs to the Plan Risk Responses process.

Incorrect Answers:
B: This is not a valid content of risk register.
A risk register is an inventory of risks and exposure associated with those risks. Risks are commonly found in project management practices, and provide information to identify, analyze, and manage risks. Typically a risk register contains:
A description of the risk
The impact should this event actually occur The probability of its occurrence
Risk Score (the multiplication of Probability and Impact)
A summary of the planned response should the event occur
A summary of the mitigation (the actions taken in advance to reduce the probability and/or impact of the event)
Ranking of risks by Risk Score so as to highlight the highest priority risks to all involved.

C: Risk register do contain the summary of mitigation, but only after the applying risk response. Here in this scenario you are in risk identification phase, hence mitigation techniques cannot be documented at this situation.



You work as a project manager for BlueWell Inc. You are about to complete the quantitative risk analysis process for your project. You can use three available tools and techniques to complete this process. Which one of the following is NOT a tool or technique that is appropriate for the quantitative risk analysis process?

  1. Data gathering and representation techniques
  2. Expert judgment
  3. Quantitative risk analysis and modeling techniques
  4. Organizational process assets

Answer(s): D

Explanation:

Organizational process asset is not a tool and technique, but an input to the quantitative risk analysis process. Quantitative Risk Analysis is a process to assess the probability of achieving particular project objectives, to quantify the effect of risks on the whole project objective, and to prioritize the risks based on the impact to overall project risk. Quantitative Risk Analysis process analyzes the affect of a risk event deriving a numerical value. It also presents a quantitative approach to build decisions in the presence of uncertainty. The inputs for Quantitative Risk Analysis are:

Organizational process assets Project Scope Statement
Risk Management Plan Risk Register
Project Management Plan

Incorrect Answers:
A: Data gathering and representation technique is a tool and technique for the quantitative risk analysis process.

B: Expert judgment is a tool and technique for the quantitative risk analysis process.

C: Quantitative risk analysis and modeling techniques is a tool and technique for the quantitative risk analysis process.



Viewing Page 41 of 361



Share your comments for ISACA CRISC exam with other users:

test user 9/24/2023 3:15:00 AM

thanks for the questions
AUSTRALIA


Draco 7/19/2023 5:34:00 AM

please reopen it now ..its really urgent
UNITED STATES


Megan 4/14/2023 5:08:00 PM

these practice exam questions were exactly what i needed. the variety of questions and the realistic exam-like environment they created helped me assess my strengths and weaknesses. i felt more confident and well-prepared on exam day, and i owe it to this exam dumps!
UNITED KINGDOM


abdo casa 8/9/2023 6:10:00 PM

thank u it very instructuf
Anonymous


Danny 1/15/2024 9:10:00 AM

its helpful?
INDIA


hanaa 10/3/2023 6:57:00 PM

is this dump still valid???
Anonymous


Georgio 1/19/2024 8:15:00 AM

question 205 answer is b
Anonymous


Matthew Dievendorf 5/30/2023 9:37:00 PM

question 39, should be answer b, directions stated is being sudneted from /21 to a /23. a /23 has 512 ips so 510 hosts. and can make 4 subnets out of the /21
Anonymous


Adhithya 8/11/2022 12:27:00 AM

beautiful test engine software and very helpful. questions are same as in the real exam. i passed my paper.
UNITED ARAB EMIRATES


SuckerPumch88 4/25/2022 10:24:00 AM

the questions are exactly the same in real exam. just make sure not to answer all them correct or else they suspect you are cheating.
UNITED STATES


soheib 7/24/2023 7:05:00 PM

question: 78 the right answer i think is d not a
Anonymous


srija 8/14/2023 8:53:00 AM

very helpful
EUROPEAN UNION


Thembelani 5/30/2023 2:17:00 AM

i am writing this exam tomorrow and have dumps
Anonymous


Anita 10/1/2023 4:11:00 PM

can i have the icdl excel exam
Anonymous


Ben 9/9/2023 7:35:00 AM

please upload it
Anonymous


anonymous 9/20/2023 11:27:00 PM

hye when will post again the past year question for this h13-311_v3 part since i have to for my test tommorow…thank you very much
Anonymous


Randall 9/28/2023 8:25:00 PM

on question 22, option b-once per session is also valid.
Anonymous


Tshegofatso 8/28/2023 11:51:00 AM

this website is very helpful
SOUTH AFRICA


philly 9/18/2023 2:40:00 PM

its my first time exam
SOUTH AFRICA


Beexam 9/4/2023 9:06:00 PM

correct answers are device configuration-enable the automatic installation of webview2 runtime. & policy management- prevent users from submitting feedback.
NEW ZEALAND


RAWI 7/9/2023 4:54:00 AM

is this dump still valid? today is 9-july-2023
SWEDEN


Annie 6/7/2023 3:46:00 AM

i need this exam.. please upload these are really helpful
PAKISTAN


Shubhra Rathi 8/26/2023 1:08:00 PM

please upload the oracle 1z0-1059-22 dumps
Anonymous


Shiji 10/15/2023 1:34:00 PM

very good questions
INDIA


Rita Rony 11/27/2023 1:36:00 PM

nice, first step to exams
Anonymous


Aloke Paul 9/11/2023 6:53:00 AM

is this valid for chfiv9 as well... as i am reker 3rd time...
CHINA


Calbert Francis 1/15/2024 8:19:00 PM

great exam for people taking 220-1101
UNITED STATES


Ayushi Baria 11/7/2023 7:44:00 AM

this is very helpfull for me
Anonymous


alma 8/25/2023 1:20:00 PM

just started preparing for the exam
UNITED KINGDOM


CW 7/10/2023 6:46:00 PM

these are the type of questions i need.
UNITED STATES


Nobody 8/30/2023 9:54:00 PM

does this actually work? are they the exam questions and answers word for word?
Anonymous


Salah 7/23/2023 9:46:00 AM

thanks for providing these questions
Anonymous


Ritu 9/15/2023 5:55:00 AM

interesting
CANADA


Ron 5/30/2023 8:33:00 AM

these dumps are pretty good.
Anonymous