The following information and diagram apply to a project:The earliest completion time for the project is:
Answer(s): C
The two paths through the network are A-C-E 5 + 4 + 6 = 15 days) and B-D-E 3 +2 + 6 = 11 days). The critical or longest path is thus A-C-E. Hence, the earliest completion time is 15 days.
Which of the following terms is not used in project management?
Answer(s): D
Project management concerns managing teams assigned to special projects. Lumpy demand refers to periodic demand for a product or service that increases in large, lumpy increments.
Activity scheduling information for the installation of a new computer system is given belowThe earliest completion time for the project is:
The critical path is the longest path because it defines the minimum duration of the project.A-D-E 4 + 6 + 5 = 15) is the critical path.
In a critical path analysis, if slack time in an activity exists, the activity:
Slack is the free time associated with each activity. In other words, paths that are not critical have slack time. Slack represents unused resources that can be diverted to the critical path.
The primary difference between PERT and CPM is that:
Both PERT and CPM are network analysis techniques. But CPM was developed independently of PERT and is widely used in the construction industry. CPM may be thought of as a subset of PERT. Like PERT, it is a network technique, but, unlike PERT, it uses deterministic time and cost estimates. Its advantages include cost estimates plus the concept of "crash" efforts and costs. Activity times are estimated for normal effort and crash effort. Crash time is the time to complete an activity assuming that all available resources were devoted to the task overtime, extra crew, etc.). Activity costs are also estimated for normal and crash efforts. These estimates allow the project manager to estimate the costs of completing the project if some of the activities are completed on a crash basis. The network diagram is constructed in the same manner as PERT diagrams. Once the diagram is constructed, the critical paths are found for normal and crash times. More than one critical path may exist for each diagram.
Share your comments for IIA IIA-CIA-Part3 exam with other users:
thank you for making the interactive questions
questions are accurate
i need questions/dumps for this exam.
i need this exam, when will it be uploaded
i need the dumps !
very helpful
good source
my 3rd test and passed on first try. hats off to this brain dumps site.
please upload it
does anybody know if are these real exam questions?
are these questions similar to actual questions in the exam? because they seem to be too easy
i have a lot of experience but what comes in the exam is totally different from the practical day to day tasks. so i thought i would rather rely on these brain dumps rather failing the exam.
good questions
valied exam dumps. they were very helpful and i got a pretty good score. i am very grateful for this service and exam questions
will it help?
very useful to verify knowledge before exam
good stuffs
question 17 : responses arent b and c ?
just passed the exam on my first try using these dumps.
these questions look good.
this is very helpful content
please provide the dumps
it is amazing
quesion 178 about "a banking system that predicts whether a loan will be repaid is an example of the" the answer is classification. not regresion, you should fix it.
please upload apache spark dumps
q14 is b&c to reduce you will switch off mail for every single alert and you will switch on daily digest to get a mail once per day, you might even skip the empty digest mail but i see this as a part of the daily digest adjustment
i think it is good question
good for students who wish to give certification.
is there a google drive link to the images? the links in questions are not working.
very promising, looks great, so much wow!
i scored 87% on the az-204 exam. thanks! i always trust
good need more
sample questions seems good