IIA Certified Internal Auditor - Part 3, Business Analysis and Information Technology IIA-CIA-Part3 Dumps in PDF

Free IIA IIA-CIA-Part3 Real Questions (page: 58)

The following information and diagram apply to a project:



The earliest completion time for the project is:

  1. 11 days.
  2. 14 days.
  3. 15 days.
  4. 20 days.

Answer(s): C

Explanation:

The two paths through the network are A-C-E 5 + 4 + 6 = 15 days) and B-D-E 3 +2 + 6 = 11 days). The critical or longest path is thus A-C-E. Hence, the earliest completion time is 15 days.



Which of the following terms is not used in project management?

  1. Dummy activity.
  2. Latest finish.
  3. Optimistic time.
  4. Lumpy demand.

Answer(s): D

Explanation:

Project management concerns managing teams assigned to special projects. Lumpy demand refers to periodic demand for a product or service that increases in large, lumpy increments.



Activity scheduling information for the installation of a new computer system is given below



The earliest completion time for the project is:

  1. A-C.
  2. B-E.
  3. A-D-E.
  4. B-D-C.

Answer(s): C

Explanation:

The critical path is the longest path because it defines the minimum duration of the project.
A-D-E 4 + 6 + 5 = 15) is the critical path.



In a critical path analysis, if slack time in an activity exists, the activity:

  1. Is not essential to the overall project.
  2. Is a backup activity to replace a main activity should it fail.
  3. Could be delayed without delaying the overall project.
  4. Involves essentially no time to complete.

Answer(s): C

Explanation:

Slack is the free time associated with each activity. In other words, paths that are not critical have slack time. Slack represents unused resources that can be diverted to the critical path.



The primary difference between PERT and CPM is that:

  1. CPM uses probabilities on the activity times and PERT does not.
  2. PERT considers activity costs and CPM does not.
  3. PERT can assign probabilities to activity times and CPM does not.
  4. CPM considers activity costs and PERT does not.

Answer(s): D

Explanation:

Both PERT and CPM are network analysis techniques. But CPM was developed independently of PERT and is widely used in the construction industry. CPM may be thought of as a subset of PERT. Like PERT, it is a network technique, but, unlike PERT, it uses deterministic time and cost estimates. Its advantages include cost estimates plus the concept of "crash" efforts and costs. Activity times are estimated for normal effort and crash effort. Crash time is the time to complete an activity assuming that all available resources were devoted to the task overtime, extra crew, etc.). Activity costs are also estimated for normal and crash efforts. These estimates allow the project manager to estimate the costs of completing the project if some of the activities are completed on a crash basis. The network diagram is constructed in the same manner as PERT diagrams. Once the diagram is constructed, the critical paths are found for normal and crash times. More than one critical path may exist for each diagram.



Share your comments for IIA IIA-CIA-Part3 exam with other users:

S
srija
8/14/2023 8:53:00 AM

very helpful

T
Thembelani
5/30/2023 2:17:00 AM

i am writing this exam tomorrow and have dumps

A
Anita
10/1/2023 4:11:00 PM

can i have the icdl excel exam

B
Ben
9/9/2023 7:35:00 AM

please upload it

A
anonymous
9/20/2023 11:27:00 PM

hye when will post again the past year question for this h13-311_v3 part since i have to for my test tommorow…thank you very much

R
Randall
9/28/2023 8:25:00 PM

on question 22, option b-once per session is also valid.

T
Tshegofatso
8/28/2023 11:51:00 AM

this website is very helpful

P
philly
9/18/2023 2:40:00 PM

its my first time exam

B
Beexam
9/4/2023 9:06:00 PM

correct answers are device configuration-enable the automatic installation of webview2 runtime. & policy management- prevent users from submitting feedback.

R
RAWI
7/9/2023 4:54:00 AM

is this dump still valid? today is 9-july-2023

A
Annie
6/7/2023 3:46:00 AM

i need this exam.. please upload these are really helpful

S
Shubhra Rathi
8/26/2023 1:08:00 PM

please upload the oracle 1z0-1059-22 dumps

S
Shiji
10/15/2023 1:34:00 PM

very good questions

R
Rita Rony
11/27/2023 1:36:00 PM

nice, first step to exams

A
Aloke Paul
9/11/2023 6:53:00 AM

is this valid for chfiv9 as well... as i am reker 3rd time...

C
Calbert Francis
1/15/2024 8:19:00 PM

great exam for people taking 220-1101

A
Ayushi Baria
11/7/2023 7:44:00 AM

this is very helpfull for me

A
alma
8/25/2023 1:20:00 PM

just started preparing for the exam

C
CW
7/10/2023 6:46:00 PM

these are the type of questions i need.

N
Nobody
8/30/2023 9:54:00 PM

does this actually work? are they the exam questions and answers word for word?

S
Salah
7/23/2023 9:46:00 AM

thanks for providing these questions

R
Ritu
9/15/2023 5:55:00 AM

interesting

R
Ron
5/30/2023 8:33:00 AM

these dumps are pretty good.

S
Sowl
8/10/2023 6:22:00 PM

good questions

B
Blessious Phiri
8/15/2023 2:02:00 PM

dbua is used for upgrading oracle database

R
Richard
10/24/2023 6:12:00 AM

i am thrilled to say that i passed my amazon web services mls-c01 exam, thanks to study materials. they were comprehensive and well-structured, making my preparation efficient.

J
Janjua
5/22/2023 3:31:00 PM

please upload latest ibm ace c1000-056 dumps

M
Matt
12/30/2023 11:18:00 AM

if only explanations were provided...

R
Rasha
6/29/2023 8:23:00 PM

yes .. i need the dump if you can help me

A
Anonymous
7/25/2023 8:05:00 AM

good morning, could you please upload this exam again?

A
AJ
9/24/2023 9:32:00 AM

hi please upload sre foundation and practitioner exam questions

P
peter parker
8/10/2023 10:59:00 AM

the exam is listed as 80 questions with a pass mark of 70%, how is your 50 questions related?

B
Berihun
7/13/2023 7:29:00 AM

all questions are so important and covers all ccna modules

N
nspk
1/19/2024 12:53:00 AM

q 44. ans:- b (goto setup > order settings > select enable optional price books for orders) reference link --> https://resources.docs.salesforce.com/latest/latest/en-us/sfdc/pdf/sfom_impl_b2b_b2b2c.pdf(decide whether you want to enable the optional price books feature. if so, select enable optional price books for orders. you can use orders in salesforce while managing price books in an external platform. if you’re using d2c commerce, you must select enable optional price books for orders.)

AI Tutor 👋 I’m here to help!