As of week 8, the Gantt chart shows that the project is:
Answer(s): B
Assuming that 1) each of the bars represents the expected time necessary to complete an activity and 2) the shaded regions represent the portions completed, activity A has been completed as scheduled and activities B and C are ahead of schedule. Consequently, the project is ahead of schedule.
When using PERT Program Evaluation Review Technique), the expected time for an activity when given an optimistic time A), a pessimistic time B), and a most likely time m) is calculated by which one of the following formulas?
Answer(s): C
PERT was developed to aid managers in controlling large, complex projects. PERT analysis includes probabilistic estimates of activity completion times. Three time estimates are made:Optimistic, most likely, and pessimistic. The time estimates for an activity are assumed to approximate a beta probability distribution. PERT approximates the mean of the beta distribution by dividing the sum of the optimistic time, the pessimistic time, and four times the most likely time by six.
The process of adding resources to shorten selected activity times on the critical path in project scheduling is called:
Answer(s): A
Activity times are estimated for normal effort and crash effort. Crashing is the process of adding resources to shorten activity times on the critical path in project scheduling. The network diagram and the corresponding activity cost chart for a manufacturing project at Networks, Inc. are presented below. The numbers in the diagram are the expected times in days) to perform each activity in the project.
The expected time of the critical path is:
The critical path is the longest path. The longest path in the diagram is A-D-E, which requires 13 days 5.5 + 7.5) based on expected times. The network diagram and the corresponding activity cost chart for a manufacturing project at Networks, Inc. are presented below. The numbers in the diagram are the expected times in days) to perform each activity in the project.
To keep costs at a minimum and decrease the completion time by 1-1/2 days, Networks, Inc.should crash activity)
The critical longest) path is A-D-E, which has an expected time of 13 days 5.5 +7.5). However, to decrease the project's completion time by 1.5 days, paths A-B-C-E 4.5 + 1.0 + 6.5 = 12 days) and A-B-D-E 4.5 + .5 + 7.5 = 12.5 days) as well as A-D-E must also be shortened. Hence, A-D-E must be reduced by 1.5 days, A-B-C-E by .5 day, and A-B-D-E by 1.0 day. The only way to decrease A-D-E by 1.5 days is to crash activity. AD 5.5 expected time - 4.0 crash time = 1.5 days). Crashing DE results in a 1.0-day saving 7.5 -- 6.5) only.Crashing AB is the efficient way to reduce both A-B-C-E and A-B-D-E by the desired amount of time because it i s hart of both paths. The incremental cost of crashing AB is U $1,000 US $4,000 crash cost -- US $3,000 normal cost) to shorten the completion time by 1.0 day 4.5 -- 3.5). The alternatives for decreasing both A-B-C-E and A-B-D-E are more costly.
Share your comments for IIA IIA-CIA-Part3 exam with other users:
this exam dumps just did the job. i donot want to ruffle your feathers but your exam dumps and mock test engine is amazing.
nice questions
the explanation are really helpful
just passed my exam yesterday on my first attempt. these dumps were extremely helpful in passing first time. the questions were very, very similar to these questions!
cosmos db is paas not saas
what is the percentage of common questions in gcp exam compared to 197 dump questions? are they 100% matching with real gcp exam?
not able to see questions
by far one of the best sites for free questions. i have pass 2 exams with the help of this website.
excellent question bank.
it really helped
excelent material
the new versoin of this exam which i downloaded has all the latest questions from the exam. i only saw 3 new questions in the exam which was not in this dump.
question 8 - can cloudtrail be used for storing jobs? based on aws - aws cloudtrail is used for governance, compliance and investigating api usage across all of our aws accounts. every action that is taken by a user or script is an api call so this is logged to [aws] cloudtrail. something seems incorrect here.
question 13 tda - c01 answer : quick table calculation -> percentage of total , compute using table down
pls share teh dump
question 44 answer is user risk
please post the questions for preparation
thanks for the questions
please reopen it now ..its really urgent
these practice exam questions were exactly what i needed. the variety of questions and the realistic exam-like environment they created helped me assess my strengths and weaknesses. i felt more confident and well-prepared on exam day, and i owe it to this exam dumps!
thank u it very instructuf
its helpful?
is this dump still valid???
question 205 answer is b
question 39, should be answer b, directions stated is being sudneted from /21 to a /23. a /23 has 512 ips so 510 hosts. and can make 4 subnets out of the /21
beautiful test engine software and very helpful. questions are same as in the real exam. i passed my paper.
the questions are exactly the same in real exam. just make sure not to answer all them correct or else they suspect you are cheating.
question: 78 the right answer i think is d not a
very helpful
i am writing this exam tomorrow and have dumps
can i have the icdl excel exam
please upload it
hye when will post again the past year question for this h13-311_v3 part since i have to for my test tommorow…thank you very much
on question 22, option b-once per session is also valid.