IIA Certified Internal Auditor - Part 3, Business Analysis and Information Technology IIA-CIA-Part3 Dumps in PDF

Free IIA IIA-CIA-Part3 Real Questions (page: 56)

As of week 8, the Gantt chart shows that the project is:

  1. Complete.
  2. Ahead of schedule.
  3. On schedule.
  4. Behind schedule.

Answer(s): B

Explanation:

Assuming that 1) each of the bars represents the expected time necessary to complete an activity and 2) the shaded regions represent the portions completed, activity A has been completed as scheduled and activities B and C are ahead of schedule. Consequently, the project is ahead of schedule.



When using PERT Program Evaluation Review Technique), the expected time for an activity when given an optimistic time A), a pessimistic time B), and a most likely time m) is calculated by which one of the following formulas?

  1. b ­ a) =2
  2. a + b) =2
  3. a + 4m +b) =6
  4. 4 abm) =6

Answer(s): C

Explanation:

PERT was developed to aid managers in controlling large, complex projects. PERT analysis includes probabilistic estimates of activity completion times. Three time estimates are made:
Optimistic, most likely, and pessimistic. The time estimates for an activity are assumed to approximate a beta probability distribution. PERT approximates the mean of the beta distribution by dividing the sum of the optimistic time, the pessimistic time, and four times the most likely time by six.



The process of adding resources to shorten selected activity times on the critical path in project scheduling is called:

  1. Crashing.
  2. The Delphi technique.
  3. ABC analysis.
  4. A branch-and-bound solution.

Answer(s): A

Explanation:

Activity times are estimated for normal effort and crash effort. Crashing is the process of adding resources to shorten activity times on the critical path in project scheduling. The network diagram and the corresponding activity cost chart for a manufacturing project at Networks, Inc. are presented below. The numbers in the diagram are the expected times in days) to perform each activity in the project.



The expected time of the critical path is:

  1. 12.0 days.
  2. 13.0 days.
  3. 11.5 days.
  4. 11.0 days.

Answer(s): B

Explanation:

The critical path is the longest path. The longest path in the diagram is A-D-E, which requires 13 days 5.5 + 7.5) based on expected times. The network diagram and the corresponding activity cost chart for a manufacturing project at Networks, Inc. are presented below. The numbers in the diagram are the expected times in days) to perform each activity in the project.



To keep costs at a minimum and decrease the completion time by 1-1/2 days, Networks, Inc.
should crash activity)

  1. AD and AB.
  2. DE.
  3. AD.
  4. AB and CE.

Answer(s): A

Explanation:

The critical longest) path is A-D-E, which has an expected time of 13 days 5.5 +7.5). However, to decrease the project's completion time by 1.5 days, paths A-B-C-E 4.5 + 1.0 + 6.5 = 12 days) and A-B-D-E 4.5 + .5 + 7.5 = 12.5 days) as well as A-D-E must also be shortened. Hence, A-D-E must be reduced by 1.5 days, A-B-C-E by .5 day, and A-B-D-E by 1.0 day. The only way to decrease A-D-E by 1.5 days is to crash activity. AD 5.5 expected time - 4.0 crash time = 1.5 days). Crashing DE results in a 1.0-day saving 7.5 -- 6.5) only.
Crashing AB is the efficient way to reduce both A-B-C-E and A-B-D-E by the desired amount of time because it i s hart of both paths. The incremental cost of crashing AB is U $1,000 US $4,000 crash cost -- US $3,000 normal cost) to shorten the completion time by 1.0 day 4.5 -- 3.5). The alternatives for decreasing both A-B-C-E and A-B-D-E are more costly.



Share your comments for IIA IIA-CIA-Part3 exam with other users:

S
SB
7/21/2023 3:18:00 AM

please provide the dumps

D
David
8/2/2023 8:20:00 AM

it is amazing

U
User
8/3/2023 3:32:00 AM

quesion 178 about "a banking system that predicts whether a loan will be repaid is an example of the" the answer is classification. not regresion, you should fix it.

Q
quen
7/26/2023 10:39:00 AM

please upload apache spark dumps

E
Erineo
11/2/2023 5:34:00 PM

q14 is b&c to reduce you will switch off mail for every single alert and you will switch on daily digest to get a mail once per day, you might even skip the empty digest mail but i see this as a part of the daily digest adjustment

P
Paul
10/21/2023 8:25:00 AM

i think it is good question

U
Unknown
8/15/2023 5:09:00 AM

good for students who wish to give certification.

C
Ch
11/20/2023 10:56:00 PM

is there a google drive link to the images? the links in questions are not working.

J
Joey
5/16/2023 5:25:00 AM

very promising, looks great, so much wow!

A
alaska
10/24/2023 5:48:00 AM

i scored 87% on the az-204 exam. thanks! i always trust

N
nnn
7/9/2023 11:09:00 PM

good need more

U
User-sfdc
12/29/2023 7:21:00 AM

sample questions seems good

T
Tamer dam
8/4/2023 10:21:00 AM

huawei is ok

Y
YK
12/11/2023 1:10:00 AM

good one nice

D
de
8/28/2023 2:38:00 AM

please continue

D
DMZ
6/25/2023 11:56:00 PM

this exam dumps just did the job. i donot want to ruffle your feathers but your exam dumps and mock test engine is amazing.

J
Jose
8/30/2023 6:14:00 AM

nice questions

T
Tar01
7/24/2023 7:07:00 PM

the explanation are really helpful

D
DaveG
12/15/2023 4:50:00 PM

just passed my exam yesterday on my first attempt. these dumps were extremely helpful in passing first time. the questions were very, very similar to these questions!

A
A.K.
6/30/2023 6:34:00 AM

cosmos db is paas not saas

S
S Roychowdhury
6/26/2023 5:27:00 PM

what is the percentage of common questions in gcp exam compared to 197 dump questions? are they 100% matching with real gcp exam?

B
Bella
7/22/2023 2:05:00 AM

not able to see questions

S
Scott
9/8/2023 7:19:00 AM

by far one of the best sites for free questions. i have pass 2 exams with the help of this website.

D
donald
8/19/2023 11:05:00 AM

excellent question bank.

A
Ashwini
8/22/2023 5:13:00 AM

it really helped

S
sk
5/13/2023 2:07:00 AM

excelent material

C
Christopher
9/5/2022 10:54:00 PM

the new versoin of this exam which i downloaded has all the latest questions from the exam. i only saw 3 new questions in the exam which was not in this dump.

S
Sam
9/7/2023 6:51:00 AM

question 8 - can cloudtrail be used for storing jobs? based on aws - aws cloudtrail is used for governance, compliance and investigating api usage across all of our aws accounts. every action that is taken by a user or script is an api call so this is logged to [aws] cloudtrail. something seems incorrect here.

T
Tanvi Rajput
8/14/2023 10:55:00 AM

question 13 tda - c01 answer : quick table calculation -> percentage of total , compute using table down

P
PMSAGAR
9/19/2023 2:48:00 AM

pls share teh dump

Z
zazza
6/16/2023 10:47:00 AM

question 44 answer is user risk

P
Prasana
6/23/2023 1:59:00 AM

please post the questions for preparation

T
test user
9/24/2023 3:15:00 AM

thanks for the questions

D
Draco
7/19/2023 5:34:00 AM

please reopen it now ..its really urgent

AI Tutor 👋 I’m here to help!