When making a cost-time trade-off in PERT analysis, the first activity that should be crashed is the activity:
Answer(s): D
When making a cost-time trade-off, the first activity to be crashed have its completion time accelerated) is one on the critical path. To select an activity on another path would not reduce the total time of completion. The initial activity chosen should be the one with the completion time that can be accelerated at the lowest possible cost per unit of time saved.
In PERT, slack is the:
PERT diagrams are free-form networks showing each activity in a large project as a line between events. The critical path is the longest path in time through the network. That path is critical in that, if any activity on the critical path takes longer than expected, the entire project will be delayed. Paths that are not critical have slack time. Slack is the number of days an activity can be delayed without forcing a delay for the entire project.
The network below describes the interrelationships of several activities necessary to complete a project. The arrows represent the activities. The numbers between the arrows indicate the number of months to complete each activity. The shortest time to complete the project is:
Answer(s): C
The longest, or critical, path in the network from node A) to node F) is path A- -D-F. All other paths are shorter than path A-C-D-F, so the activities along those paths can be completed before the activities along path A-C-D-F. Thus, the shortest time to complete the project is 8 months 3 + 3 +2).
A shortest-route algorithm is used in network models to:
Answer(s): B
Network models are used to solve managerial problems pertaining to project scheduling, information systems design, and transportation systems design. Networks consisting of nodes and arcs may be created to represent in graphic form problems related to transportation, assignment, and transshipment. The shortest-route, minimal spanning tree, and maximal flow problems are other applications of network models. A shortest-route algorithm minimizes total travel time from one site to each of the other sites in a transportation system.
Which of the following project scheduling techniques is commonly used in total quality management for simplifying work processes?
Flowcharting is commonly used in computer programming for determining program logic and in total quality management for simplifying work processes. However, they are also used for establishing the desirable sequence of activities and decisions.
Share your comments for IIA IIA-CIA-Part3 exam with other users:
question number 2 is indicating you are giving proper questions. observe and change properly.
passed today.40% questions were new.litwere case study,lots of new questions on afd,ratelimit,tm,lb,app gatway.got 2 set series of questions which are not present here.questions on azure cyclecloud, no.of vnet/vms required for implimentation,blueprints assignment/management group etc
practice test
want the dumps for emc content management server programming(cmsp)
brilliant and helpful
q75. azure files is pass
very helpful
thank you for these questions. it helped a lot.
how do i get the h12-724 dumps
nice data dumps
answers are correct
good explanation
hi team just want to know if there is any update version of the exam 350-401
helpful on 2017 scrum guide
planning to attempt for the exam.
pleaseee upload
thanks ly so i have information cia
hello team, i need sap qm dumps for practice
it’s good but not senatios based
q.119 - the correct answer is b - they are not captured in an update set as theyre data.
good matter
please upload c_sacp_2308
please upload the dump. thanks very much !!
good questions
hi, could you please update the latest dump version
this question is keep repeat : you are developing a sales application that will contain several azure cloud services and handle different components of a transaction. different cloud services will process customer orders, billing, payment, inventory, and shipping. you need to recommend a solution to enable the cloud services to asynchronously communicate transaction information by using xml messages. what should you include in the recommendation?
great questions
its realy good
oracle 1z0-1059-22 dumps
please share me the pdf..
q50: which two functions can be used by an end user when pivoting an interactive report? the correct answer is a, c because we do not have rank in the function pivoting you can check in the apex app
best to practice
so far it is good
please provide me the dump