The following information and diagram apply to a project:The earliest completion time for the project is:
Answer(s): C
The two paths through the network are A-C-E (5+4 + 6= 15days) and B-D-E (3 + 2 + 6 = 11 days). The critical or longest path is thus A-C-E. Hence, the earliest completion time is 15 days.
Which of the following terms is not used in project management?
Answer(s): D
Project management concerns managing teams assigned to special projects. Lumpy demand refers to periodic demand for a product or service that increases in large, lumpy increments.
Activity scheduling information for the installation of a new computer system is given below.For this project, the critical path is:
The critical path is the longest path because it defines the minimum duration of the project. A-D-E (4 + 6 + 5 = 15 days) is the critical path.
In a critical path analysis, if slack time in an activity exists, the activity:
Slack is the free time associated with activities not on the critical path. Slack represents unused resources that can be diverted to the critical path.
Various tools are employed to control large scale projects. They include all of the following except:
Statistical process (quality) control is not used to control large scale projects. Statistical quality control is a method of determining whether the shipment or production run of units lies within acceptable limits. It is also used to determine whether production processes are out of control.
Share your comments for IIA IIA-CIA-Part3 exam with other users:
physical tempering techniques
its giving best technical knowledge
please upload
great question with explanation thanks!!
does this exam have lab sections?
please upload the braindump for .net
i need this exam 1z0-1107-2. please.
very useful!
for this question - "which three type of basic patient or member information is displayed on the patient info component? (choose three.)", list of conditions is not displayed (it is displayed in patient card, not patient info). so should be thumbnail of chatter photo
q52 should be d. vm storage controller bandwidth represents the amount of data (in terms of bandwidth) that a vms storage controller is using to read and write data to the storage fabric.
nice questions
very useful
question # 208: failure logs is not an example of operational metadata.
good questions
thank you for the test materials!
its very helpful
good questons
i need the dumb of the hcip security v4.0 exam
upload the dump please
yes, iam looking this
please upload cima e2 managing performance dumps
wonderful questions
i used this site since 2000, still great to support my career
why is the answer to "which of the following is required by scrum?" all of the following stated below since most of them are not mandatory? sprint retrospective. members must be stand up at the daily scrum. sprint burndown chart. release planning.
great job. hope this helps out.
upload please. many thanks!
this is so interesting
great material thanks
anyone who wrote this exam recently
ok they re good
relevant questions
please post