A Gantt chart:

  1. Shows the critical path for a project.
  2. Is used for determining an optimal product mix.
  3. Shows only the activities along the critical path of a network.
  4. Does not necessarily show the critical path through a network.

Answer(s): D

Explanation:

The major advantage of a Gantt chart is its simplicity: It requires no special tools or mathematics. However, it depicts only the interrelationships between tasks in a limited way. Thus, trying to identify a project's critical path from a Gantt chart may not be feasible.



In the Gantt chart below, shaded bars represent completed portions of activities, bars depicted with broken lines represent uncompleted portions, and blank bars represent activities notyet begun.



As of week 8, the Gantt chart shows that the project is:

  1. Complete.
  2. Ahead of schedule.
  3. On schedule.
  4. Behind schedule.

Answer(s): C

Explanation:

Activities B and C are the only activities that should be underway during week 8. Since both are underway and on schedule, the project is on schedule.



When using PERT (Program Evaluation Review Technique), the expected time for an activity when given an optimistic time (a), a pessimistic time (b),andamostlikelytime(m) is calculated by which one of the following formulas?

  1. (b - a) + 2
  2. (a + b) + 2
  3. (a + 4m+b) + 6
  4. (4abm) + 6

Answer(s): C

Explanation:

PERT was developed to aid managers in controlling large, complex projects. PERT analysis includes probabilistic estimates of activity completion times. Three time estimates are made:
optimistic, most likely, and pessimistic. The time estimates for an activity are assumed to approximate a beta probability distribution. PERT approximates the mean of the beta distribution by dividing the sum of the optimistic time, the pessimistic time, and four times the most likely time by six.



The process of adding resources to shorten selected activity times on the critical path in project scheduling is called:

  1. Crashing.
  2. The Delphi technique.
  3. ABC analysis.
  4. A branch-and-bound solution.

Answer(s): A

Explanation:

Crashing is the process of adding resources to shorten activity times on the critical path in project scheduling.



The network diagram and the corresponding activity cost chart for a manufacturing project at Networks, Inc., are presented below. The numbers in the diagram are the expected times (in days) to perform each activity in the project.


The expected time of the critical path is:

  1. 12.0 days
  2. 13.0 days
  3. 11.5 days
  4. 11.0 days

Answer(s): B

Explanation:

The critical path is the longest path. The longest path in the diagram is A-D-E, which requires 13 days (5.5 + 7.5) based on expected times.



Share your comments for IIA IIA-CIA-Part3 exam with other users:

P
PeterPan
10/18/2023 10:22:00 AM

are the question real or fake?

C
CW
7/11/2023 3:19:00 PM

thank you for providing such assistance.

M
Mn8300
11/9/2023 8:53:00 AM

nice questions

N
Nico
4/23/2023 11:41:00 PM

my 3rd purcahse from this site. these exam dumps are helpful. very helpful.

C
Chere
9/15/2023 4:21:00 AM

found it good

T
Thembelani
5/30/2023 2:47:00 AM

excellent material

V
vinesh phale
9/11/2023 2:51:00 AM

very helpfull

B
Bhagiii
11/4/2023 7:04:00 AM

well explained.

R
Rahul
8/8/2023 9:40:00 PM

i need the pdf, please.

C
CW
7/11/2023 2:51:00 PM

a good source for exam preparation

A
Anchal
10/23/2023 4:01:00 PM

nice questions

J
J Nunes
9/29/2023 8:19:00 AM

i need ielts general training audio guide questions

A
Ananya
9/14/2023 5:16:00 AM

please make this content available

S
Swathi
6/4/2023 2:18:00 PM

content is good

L
Leo
7/29/2023 8:45:00 AM

latest dumps please

L
Laolu
2/15/2023 11:04:00 PM

aside from pdf the test engine software is helpful. the interface is user-friendly and intuitive, making it easy to navigate and find the questions.

Z
Zaynik
9/17/2023 5:36:00 AM

questions and options are correct, but the answers are wrong sometimes. so please check twice or refer some other platform for the right answer

M
Massam
6/11/2022 5:55:00 PM

90% of questions was there but i failed the exam, i marked the answers as per the guide but looks like they are not accurate , if not i would have passed the exam given that i saw about 45 of 50 questions from dump

A
Anonymous
12/27/2023 12:47:00 AM

answer to this question "what administrative safeguards should be implemented to protect the collected data while in use by manasa and her product management team? " it should be (c) for the following reasons: this administrative safeguard involves controlling access to collected data by ensuring that only individuals who need the data for their job responsibilities have access to it. this helps minimize the risk of unauthorized access and potential misuse of sensitive information. while other options such as (a) documenting data flows and (b) conducting a privacy impact assessment (pia) are important steps in data protection, implementing a "need to know" access policy directly addresses the issue of protecting data while in use by limiting access to those who require it for legitimate purposes. (d) is not directly related to safeguarding data during use; it focuses on data transfers and location.

J
Japles
5/23/2023 9:46:00 PM

password lockout being the correct answer for question 37 does not make sense. it should be geofencing.

F
Faritha
8/10/2023 6:00:00 PM

for question 4, the righr answer is :recover automatically from failures

A
Anonymous
9/14/2023 4:27:00 AM

question number 4s answer is 3, option c. i

P
p das
12/7/2023 11:41:00 PM

very good questions

A
Anna
1/5/2024 1:12:00 AM

i am confused about the answers to the questions. are the answers correct?

B
Bhavya
9/13/2023 10:15:00 AM

very usefull

R
Rahul Kumar
8/31/2023 12:30:00 PM

need certification.

D
Diran Ole
9/17/2023 5:15:00 PM

great exam prep

V
Venkata Subbarao Bandaru
6/24/2023 8:45:00 AM

i require dump

D
D
7/15/2023 1:38:00 AM

good morning, could you please upload this exam again,

A
Ann
9/15/2023 5:39:00 PM

hi can you please upload the dumps for sap contingent module. thanks

S
Sridhar
1/16/2024 9:19:00 PM

good questions

S
Summer
10/4/2023 9:57:00 PM

looking forward to the real exam

V
vv
12/2/2023 2:45:00 PM

good ones for exam preparation

D
Danny Zas
9/15/2023 4:45:00 AM

this is a good experience

AI Tutor 👋 I’m here to help!