A Gantt chart:

  1. Shows the critical path for a project.
  2. Is used for determining an optimal product mix.
  3. Shows only the activities along the critical path of a network.
  4. Does not necessarily show the critical path through a network.

Answer(s): D

Explanation:

The major advantage of a Gantt chart is its simplicity: It requires no special tools or mathematics. However, it depicts only the interrelationships between tasks in a limited way. Thus, trying to identify a project's critical path from a Gantt chart may not be feasible.



In the Gantt chart below, shaded bars represent completed portions of activities, bars depicted with broken lines represent uncompleted portions, and blank bars represent activities notyet begun.



As of week 8, the Gantt chart shows that the project is:

  1. Complete.
  2. Ahead of schedule.
  3. On schedule.
  4. Behind schedule.

Answer(s): C

Explanation:

Activities B and C are the only activities that should be underway during week 8. Since both are underway and on schedule, the project is on schedule.



When using PERT (Program Evaluation Review Technique), the expected time for an activity when given an optimistic time (a), a pessimistic time (b),andamostlikelytime(m) is calculated by which one of the following formulas?

  1. (b - a) + 2
  2. (a + b) + 2
  3. (a + 4m+b) + 6
  4. (4abm) + 6

Answer(s): C

Explanation:

PERT was developed to aid managers in controlling large, complex projects. PERT analysis includes probabilistic estimates of activity completion times. Three time estimates are made:
optimistic, most likely, and pessimistic. The time estimates for an activity are assumed to approximate a beta probability distribution. PERT approximates the mean of the beta distribution by dividing the sum of the optimistic time, the pessimistic time, and four times the most likely time by six.



The process of adding resources to shorten selected activity times on the critical path in project scheduling is called:

  1. Crashing.
  2. The Delphi technique.
  3. ABC analysis.
  4. A branch-and-bound solution.

Answer(s): A

Explanation:

Crashing is the process of adding resources to shorten activity times on the critical path in project scheduling.



The network diagram and the corresponding activity cost chart for a manufacturing project at Networks, Inc., are presented below. The numbers in the diagram are the expected times (in days) to perform each activity in the project.


The expected time of the critical path is:

  1. 12.0 days
  2. 13.0 days
  3. 11.5 days
  4. 11.0 days

Answer(s): B

Explanation:

The critical path is the longest path. The longest path in the diagram is A-D-E, which requires 13 days (5.5 + 7.5) based on expected times.



Share your comments for IIA IIA-CIA-Part3 exam with other users:

S
Sowl
8/10/2023 6:22:00 PM

good questions

B
Blessious Phiri
8/15/2023 2:02:00 PM

dbua is used for upgrading oracle database

R
Richard
10/24/2023 6:12:00 AM

i am thrilled to say that i passed my amazon web services mls-c01 exam, thanks to study materials. they were comprehensive and well-structured, making my preparation efficient.

J
Janjua
5/22/2023 3:31:00 PM

please upload latest ibm ace c1000-056 dumps

M
Matt
12/30/2023 11:18:00 AM

if only explanations were provided...

R
Rasha
6/29/2023 8:23:00 PM

yes .. i need the dump if you can help me

A
Anonymous
7/25/2023 8:05:00 AM

good morning, could you please upload this exam again?

A
AJ
9/24/2023 9:32:00 AM

hi please upload sre foundation and practitioner exam questions

P
peter parker
8/10/2023 10:59:00 AM

the exam is listed as 80 questions with a pass mark of 70%, how is your 50 questions related?

B
Berihun
7/13/2023 7:29:00 AM

all questions are so important and covers all ccna modules

N
nspk
1/19/2024 12:53:00 AM

q 44. ans:- b (goto setup > order settings > select enable optional price books for orders) reference link --> https://resources.docs.salesforce.com/latest/latest/en-us/sfdc/pdf/sfom_impl_b2b_b2b2c.pdf(decide whether you want to enable the optional price books feature. if so, select enable optional price books for orders. you can use orders in salesforce while managing price books in an external platform. if you’re using d2c commerce, you must select enable optional price books for orders.)

M
Muhammad Rawish Siddiqui
12/2/2023 5:28:00 AM

"cost of replacing data if it were lost" is also correct.

A
Anonymous
7/14/2023 3:17:00 AM

pls upload the questions

M
Mukesh
7/10/2023 4:14:00 PM

good questions

E
Elie Abou Chrouch
12/11/2023 3:38:00 AM

question 182 - correct answer is d. ethernet frame length is 64 - 1518b. length of user data containing is that frame: 46 - 1500b.

D
Damien
9/23/2023 8:37:00 AM

i need this exam pls

N
Nani
9/10/2023 12:02:00 PM

its required for me, please make it enable to access. thanks

E
ethiopia
8/2/2023 2:18:00 AM

seems good..

W
whoAreWeReally
12/19/2023 8:29:00 PM

took the test last week, i did have about 15 - 20 word for word from this site on the test. (only was able to cram 600 of the questions from this site so maybe more were there i didnt review) had 4 labs, bgp, lacp, vrf with tunnels and actually had to skip a lab due to time. lots of automation syntax questions.

V
vs
9/2/2023 12:19:00 PM

no comments

J
john adenu
11/14/2023 11:02:00 AM

nice questions bring out the best in you.

O
Osman
11/21/2023 2:27:00 PM

really helpful

E
Edward
9/13/2023 5:27:00 PM

question #50 and question #81 are exactly the same questions, azure site recovery provides________for virtual machines. the first says that it is fault tolerance is the answer and second says disater recovery. from my research, it says it should be disaster recovery. can anybody explain to me why? thank you

M
Monti
5/24/2023 11:14:00 PM

iam thankful for these exam dumps questions, i would not have passed without this exam dumps.

A
Anon
10/25/2023 10:48:00 PM

some of the answers seem to be inaccurate. q10 for example shouldnt it be an m custom column?

P
PeterPan
10/18/2023 10:22:00 AM

are the question real or fake?

C
CW
7/11/2023 3:19:00 PM

thank you for providing such assistance.

M
Mn8300
11/9/2023 8:53:00 AM

nice questions

N
Nico
4/23/2023 11:41:00 PM

my 3rd purcahse from this site. these exam dumps are helpful. very helpful.

C
Chere
9/15/2023 4:21:00 AM

found it good

T
Thembelani
5/30/2023 2:47:00 AM

excellent material

V
vinesh phale
9/11/2023 2:51:00 AM

very helpfull

B
Bhagiii
11/4/2023 7:04:00 AM

well explained.

R
Rahul
8/8/2023 9:40:00 PM

i need the pdf, please.

AI Tutor 👋 I’m here to help!