IIA Certified Internal Auditor - Part 3, Business Analysis and Information Technology IIA-CIA-Part3 Dumps in PDF

Free IIA IIA-CIA-Part3 Real Questions (page: 22)

To keep costs at a minimum and decrease the completion time by 1-1/2 days, Networks, Inc.
should crash activity(ies):

  1. AD and AB
  2. DE
  3. AD
  4. AB and CE

Answer(s): A

Explanation:

The critical (longest) path is A-D-E, which has an expected time of 13 days (5.5 + 7.5). However, to decrease the project's completion time by 1.5 days, paths A-B-C-E (4.5 + 1.0 + 6.5 = 12 days) and A-B-D-E (4.5 + .5 + 7.5= 12.5 days) as well as A-D-E must also be shortened. Hence, A-D-E must be reduced by 1.5 days. A-B-C-E by .5 day, and A-B-D-E by 1.0 day. The only way to decrease A-D-E by 1.5 days is to crash activity AD (5.5 expected time - 4.0 crash time = 1.5 days). Crashing DE results in a 1.0-day saving (7.5-6.5) only. Crashing AB is the efficient way to reduce both A-B-C-E and A-B-D-E by the desired amount of time because it is part of both paths. The incremental cost of crashing AB is US $1,000 (US $4,000 crash cost - US $3,000 normal cost) to shorten the completion time by 1.0 day (4.5 - 3.5). The alternatives for decreasing both A-B-C-E and A-B-D-E are more costly.



When making a cost-time trade-off in CPM analysis, the first activity that should be crashed is the activity:

  1. With the largest amount of slack.
  2. With the lowest unit crash cost.
  3. On the critical path with the maximum possible time reduction.
  4. On the critical path with the lowest unit crash cost.

Answer(s): D

Explanation:

When making a cost-time trade-off, the first activity to be crashed (have its completion time accelerated) is one on the critical path. To select an activity on another path would not reduce the total time of completion. The initial activity chosen should be the one with the completion time that can be accelerated at the lowest possible cost per unit of time saved.



In PERT, slack is the:

  1. Uncertainty associated with time estimates.
  2. Difference between the latest starting time and earliest finishing time.
  3. Path that has the largest amount of time associated with it.
  4. Number of days an activity can be delayed without forcing a delay for the entire project.

Answer(s): D

Explanation:

Slack is the amount of time that commencement of an activity can be delayed without forcing a delay of the entire project.



The network below describes the interrelationships of several activities necessary to complete a project. The arrows represent the activities. The numbers between the arrows indicate the number of months to complete each activity.


The shortest time to complete the project is:

  1. 5 months.
  2. 6 months.
  3. 8 months.
  4. 14 months.

Answer(s): C

Explanation:

The critical (longest) path through the network from node (A) to node (F) is path A-C-D-F. All other paths are shorter than path A-C-D-F, so the activities along those paths can be completed before the activities along path A-C-D-F. Thus, the shortest time to complete the project is 8 months (3 + 3 + 2).



A shortest-route algorithm is used in network models to:

  1. Identify bottlenecks in a network and hence identify the longest path.
  2. Minimize total travel time from one site to each of the other sites in a transportation system.
  3. Maximize throughput in networks with distinct entry (source node) and exit (sink node) points.
  4. Identify the set of connecting branches having the shortest combined length.

Answer(s): B

Explanation:

Network models are used to solve managerial problems pertaining to project scheduling, information systems design, and transportation systems design. Networks consisting of nodes and arcs may be created to represent in graphic form problems related to transportation, assignment, and transshipment. The shortest-route, minimal spanning tree, and maximal flow problems are other applications of network models. A shortest-route algorithm minimizes total travel time from one site to each of the other sites in a transportation system.



Share your comments for IIA IIA-CIA-Part3 exam with other users:

M
Manju
10/19/2023 1:19:00 PM

is it really helpful to pass the exam

L
LeAnne Hair
8/24/2023 12:47:00 PM

#229 in incorrect - all the customers require an annual review

A
Abdul SK
9/28/2023 11:42:00 PM

kindy upload

A
Aderonke
10/23/2023 12:53:00 PM

fantastic assessment on psm 1

S
SAJI
7/20/2023 2:51:00 AM

56 question correct answer a,b

R
Raj Kumar
10/23/2023 8:52:00 PM

thank you for providing the q bank

P
piyush keshari
7/7/2023 9:46:00 PM

true quesstions

B
B.A.J
11/6/2023 7:01:00 AM

i can´t believe ms asks things like this, seems to be only marketing material.

G
Guss
5/23/2023 12:28:00 PM

hi, could you please add the last update of ns0-527

R
Rond65
8/22/2023 4:39:00 PM

question #3 refers to vnet4 and vnet5. however, there is no vnet5 listed in the case study (testlet 2).

C
Cheers
12/13/2023 9:55:00 AM

sometimes it may be good some times it may be

S
Sumita Bose
7/21/2023 1:01:00 AM

qs 4 answer seems wrong- please check

A
Amit
9/7/2023 12:53:00 AM

very detailed explanation !

F
FisherGirl
5/16/2022 10:36:00 PM

the interactive nature of the test engine application makes the preparation process less boring.

C
Chiranthaka
9/20/2023 11:15:00 AM

very useful.

S
SK
7/15/2023 3:51:00 AM

complete question dump should be made available for practice.

G
Gamerrr420
5/25/2022 9:38:00 PM

i just passed my first exam. i got 2 exam dumps as part of the 50% sale. my second exam is under work. once i write that exam i report my result. but so far i am confident.

K
Kudu hgeur
9/21/2023 5:58:00 PM

nice create dewey stefen

A
Anorag
9/6/2023 9:24:00 AM

i just wrote this exam and it is still valid. the questions are exactly the same but there are about 4 or 5 questions that are answered incorrectly. so watch out for those. best of luck with your exam.

N
Nathan
1/10/2023 3:54:00 PM

passed my exam today. this is a good start to 2023.

1
1
10/28/2023 7:32:00 AM

great sharing

A
Anand
1/20/2024 10:36:00 AM

very helpful

K
Kumar
6/23/2023 1:07:00 PM

thanks.. very helpful

U
User random
11/15/2023 3:01:00 AM

i registered for 1z0-1047-23 but dumps qre available for 1z0-1047-22. help me with this...

K
kk
1/17/2024 3:00:00 PM

very helpful

R
Raj
7/24/2023 10:20:00 AM

please upload oracle 1z0-1110-22 exam pdf

B
Blessious Phiri
8/13/2023 11:58:00 AM

becoming interesting on the logical part of the cdbs and pdbs

L
LOL what a joke
9/10/2023 9:09:00 AM

some of the answers are incorrect, i would be wary of using this until an admin goes back and reviews all the answers

M
Muhammad Rawish Siddiqui
12/9/2023 7:40:00 AM

question # 267: federated operating model is also correct.

M
Mayar
9/22/2023 4:58:00 AM

its helpful alot.

S
Sandeep
7/25/2022 11:58:00 PM

the questiosn from this braindumps are same as in the real exam. my passing mark was 84%.

E
Eman Sawalha
6/10/2023 6:09:00 AM

it is an exam that measures your understanding of cloud computing resources provided by aws. these resources are aligned under 6 categories: storage, compute, database, infrastructure, pricing and network. with all of the services and typees of services under each category

M
Mars
11/16/2023 1:53:00 AM

good and very useful

R
ronaldo7
10/24/2023 5:34:00 AM

i cleared the az-104 exam by scoring 930/1000 on the exam. it was all possible due to this platform as it provides premium quality service. thank you!

AI Tutor 👋 I’m here to help!