Is PERT analysis a control tool or a planning tool?
Answer(s): B
PERT Program Evaluation and Review Technique) is applied in the management of complex projects. It analyzes the project in terms of its component activities and determines their sequencing and timing. Thus, it systematically combines planning with control.
Various tools are employed to control large scale projects. They include all of the following except:
Answer(s): C
Statistical process quality) control is not used to control large scale projects. Statistical quality control is a method of determining whether the shipment or production run of units lies within acceptable limits. It is also used to determine whether production processes are out of control.
Which of the following statements is false regarding the efficient and economical achievement of the organization's objectives?
Answer(s): A
Efficient performance accomplishes objectives and goals in an accurate, timely, and economical fashion. Economical performance accomplishes objectives and goals with minimal use of resources i.e., cost) commensurate with risk exposure. Thus, to achieve economical performance when accomplishing objectives, the minimal cost should correspond to the degree of risk exposure.
Business process reengineering is most likely to:
Reengineering and TQM techniques eliminate many traditional controls. They exploit modern technology to improve productivity and decrease the number of clerical workers. Thus, controls should be automated and self-correcting and require minimal human intervention. Moreover, auditors must be prepared to encounter and use) new technologies.The emphasis therefore shifts to monitoring so management can determine when an operation may be out of control and corrective action is needed.
Monitoring is an important component of internal control.Which of the following is not an example of monitoring?
Monitoring assesses the quality of internal control over time. Management considers whether internal control is properly designed and operating as intended and modifies it to reflect changing conditions. Monitoring may be in the form of separate, periodic evaluations or of ongoing monitoring. Ongoing monitoring occurs as part of routine operations. It includes management and supervisory review, comparisons, reconciliations, and other actions by personnel as part of their regular activities. However, reconciling batch control totals is a processing control. This information is relevant to a theory of constraints TOC) analysis. A manufacturer that can sell all of its output produces its sole product using three operations. Each unit sells for US $120, and direct materials costing US $48 per unit are added at the start of the first operation. Other variable costs are immaterial. The following annual cost and capacity information is available concerning those operations:
Share your comments for Financial CIA-III-2012 exam with other users:
thank you for the test materials!
its very helpful
good questions
good questons
i need the dumb of the hcip security v4.0 exam
upload the dump please
yes, iam looking this
please upload cima e2 managing performance dumps
wonderful questions
i used this site since 2000, still great to support my career
why is the answer to "which of the following is required by scrum?" all of the following stated below since most of them are not mandatory? sprint retrospective. members must be stand up at the daily scrum. sprint burndown chart. release planning.
great job. hope this helps out.
upload please. many thanks!
this is so interesting
great material thanks
anyone who wrote this exam recently
ok they re good
relevant questions
please post
q:42 there has to be a image in the question to choose what does it mean from the options
looking for cphq dumps, where can i find these for free? please and thank you.
@aarun , thanks for the information. it would be great help if you share your email
1z0-1078-23 need this dumps
i gave the microsoft azure az-500 tests and prepared from this site as it has latest mock tests available which helped me evaluate my performance and score 919/1000
i cannot see the button to go to the questions
q-6 ans-b correct. https://docs.paloaltonetworks.com/pan-os/9-1/pan-os-cli-quick-start/use-the-cli/commit-configuration-changes
very nice very nice
please help us with 1z0-1107-2 dumps
please upload the practice questions
need this dumps
preparing for this exam is overwhelming. you cannot pass without the help of these exam dumps.
new to this site but i feel it is good
the correct answer to q8 is b. explanation since the mule app has a dependency, it is necessary to include project modules and dependencies to make sure the app will run successfully on the runtime on any other machine. source code of the component that the mule app is dependent of does not need to be included in the exported jar file, because the source code is not being used while executing an app. compiled code is being used instead.