The following information and diagram apply to a project:The earliest completion time for the project is:
Answer(s): C
The two paths through the network are A-C-E 5 + 4 + 6 = 15 days) and B-D-E 3 +2 + 6 = 11 days). The critical or longest path is thus A-C-E. Hence, the earliest completion time is 15 days.
Which of the following terms is not used in project management?
Answer(s): D
Project management concerns managing teams assigned to special projects. Lumpy demand refers to periodic demand for a product or service that increases in large, lumpy increments.
Activity scheduling information for the installation of a new computer system is given belowThe earliest completion time for the project is:
The critical path is the longest path because it defines the minimum duration of the project.A-D-E 4 + 6 + 5 = 15) is the critical path.
In a critical path analysis, if slack time in an activity exists, the activity:
Slack is the free time associated with each activity. In other words, paths that are not critical have slack time. Slack represents unused resources that can be diverted to the critical path.
The primary difference between PERT and CPM is that:
Both PERT and CPM are network analysis techniques. But CPM was developed independently of PERT and is widely used in the construction industry. CPM may be thought of as a subset of PERT. Like PERT, it is a network technique, but, unlike PERT, it uses deterministic time and cost estimates. Its advantages include cost estimates plus the concept of "crash" efforts and costs. Activity times are estimated for normal effort and crash effort. Crash time is the time to complete an activity assuming that all available resources were devoted to the task overtime, extra crew, etc.). Activity costs are also estimated for normal and crash efforts. These estimates allow the project manager to estimate the costs of completing the project if some of the activities are completed on a crash basis. The network diagram is constructed in the same manner as PERT diagrams. Once the diagram is constructed, the critical paths are found for normal and crash times. More than one critical path may exist for each diagram.
Share your comments for Financial CIA-III-2012 exam with other users:
this is great
please i want the questions to pass the exam
i need to pass exam
great, i appreciate it.
please could you upload (isc)2 certified in cybersecurity (cc) exam questions
good questions, wrong answers
im preparing for exams
question no: 42 isnt azure vm an iaas solution? so, shouldnt the answer be "no"?
im study azure
i need this now
i took the aws saa-c03 test and scored 935/1000. it has all the exam dumps and important info.
good questions
well explained
i got the full version and it helped me pass the exam. pdf version is very good.
provide the download link, please
please upload thank.
please can you share 1z0-1055-22 dump pls
i will wait impatiently. thank youu
is it possible to clear the exam if we focus on only these 156 questions instead of 623 questions? kindly help!
really helped with preparation of my scrum exam
very informative and through explanations
prep for exam
thanks for helping us
i prepared for the eccouncil 350-401 exam. i scored 92% on the test.
aba questions to practice
great content
how do i get the remaining questions?
well formatted pdf and the test engine software is free. well worth the money i sept.
looking for 1z0-116
in question 22, shouldnt be in the data (option a) layer?
the questions are incredibly close to real exam. you people are amazing.
q15. answer is b. simple
great practice
thanks to this exam dumps, i felt confident and passed my exam with ease.