Financial The Certified Internal Auditor-Part3 New(CIA-III) CIA-III-2012 Dumps in PDF

Free Financial CIA-III-2012 Real Questions (page: 58)

The following information and diagram apply to a project:



The earliest completion time for the project is:

  1. 11 days.
  2. 14 days.
  3. 15 days.
  4. 20 days.

Answer(s): C

Explanation:

The two paths through the network are A-C-E 5 + 4 + 6 = 15 days) and B-D-E 3 +2 + 6 = 11 days). The critical or longest path is thus A-C-E. Hence, the earliest completion time is 15 days.



Which of the following terms is not used in project management?

  1. Dummy activity.
  2. Latest finish.
  3. Optimistic time.
  4. Lumpy demand.

Answer(s): D

Explanation:

Project management concerns managing teams assigned to special projects. Lumpy demand refers to periodic demand for a product or service that increases in large, lumpy increments.



Activity scheduling information for the installation of a new computer system is given below



The earliest completion time for the project is:

  1. A-C.
  2. B-E.
  3. A-D-E.
  4. B-D-C.

Answer(s): C

Explanation:

The critical path is the longest path because it defines the minimum duration of the project.
A-D-E 4 + 6 + 5 = 15) is the critical path.



In a critical path analysis, if slack time in an activity exists, the activity:

  1. Is not essential to the overall project.
  2. Is a backup activity to replace a main activity should it fail.
  3. Could be delayed without delaying the overall project.
  4. Involves essentially no time to complete.

Answer(s): C

Explanation:

Slack is the free time associated with each activity. In other words, paths that are not critical have slack time. Slack represents unused resources that can be diverted to the critical path.



The primary difference between PERT and CPM is that:

  1. CPM uses probabilities on the activity times and PERT does not.
  2. PERT considers activity costs and CPM does not.
  3. PERT can assign probabilities to activity times and CPM does not.
  4. CPM considers activity costs and PERT does not.

Answer(s): D

Explanation:

Both PERT and CPM are network analysis techniques. But CPM was developed independently of PERT and is widely used in the construction industry. CPM may be thought of as a subset of PERT. Like PERT, it is a network technique, but, unlike PERT, it uses deterministic time and cost estimates. Its advantages include cost estimates plus the concept of "crash" efforts and costs. Activity times are estimated for normal effort and crash effort. Crash time is the time to complete an activity assuming that all available resources were devoted to the task overtime, extra crew, etc.). Activity costs are also estimated for normal and crash efforts. These estimates allow the project manager to estimate the costs of completing the project if some of the activities are completed on a crash basis. The network diagram is constructed in the same manner as PERT diagrams. Once the diagram is constructed, the critical paths are found for normal and crash times. More than one critical path may exist for each diagram.



Share your comments for Financial CIA-III-2012 exam with other users:

A
anonymous
7/20/2023 10:31:00 PM

this is great

X
Xenofon
6/26/2023 9:35:00 AM

please i want the questions to pass the exam

D
Diego
1/21/2024 8:21:00 PM

i need to pass exam

V
Vichhai
12/25/2023 3:25:00 AM

great, i appreciate it.

P
P Simon
8/25/2023 2:39:00 AM

please could you upload (isc)2 certified in cybersecurity (cc) exam questions

K
Karim
10/8/2023 8:34:00 PM

good questions, wrong answers

I
Itumeleng
1/6/2024 12:53:00 PM

im preparing for exams

M
MS
1/19/2024 2:56:00 PM

question no: 42 isnt azure vm an iaas solution? so, shouldnt the answer be "no"?

K
keylly
11/28/2023 10:10:00 AM

im study azure

D
dorcas
9/22/2023 8:08:00 AM

i need this now

T
treyf
11/9/2023 5:13:00 AM

i took the aws saa-c03 test and scored 935/1000. it has all the exam dumps and important info.

A
anonymous
1/11/2024 4:50:00 AM

good questions

A
Anjum
9/23/2023 6:22:00 PM

well explained

T
Thakor
6/7/2023 11:52:00 PM

i got the full version and it helped me pass the exam. pdf version is very good.

S
sartaj
7/18/2023 11:36:00 AM

provide the download link, please

L
loso
7/25/2023 5:18:00 AM

please upload thank.

P
Paul
6/23/2023 7:12:00 AM

please can you share 1z0-1055-22 dump pls

E
exampei
10/7/2023 8:14:00 AM

i will wait impatiently. thank youu

P
Prince
10/31/2023 9:09:00 PM

is it possible to clear the exam if we focus on only these 156 questions instead of 623 questions? kindly help!

A
Ali Azam
12/7/2023 1:51:00 AM

really helped with preparation of my scrum exam

J
Jerman
9/29/2023 8:46:00 AM

very informative and through explanations

J
Jimmy
11/4/2023 12:11:00 PM

prep for exam

A
Abhi
9/19/2023 1:22:00 PM

thanks for helping us

M
mrtom33
11/20/2023 4:51:00 AM

i prepared for the eccouncil 350-401 exam. i scored 92% on the test.

J
JUAN
6/28/2023 2:12:00 AM

aba questions to practice

L
LK
1/2/2024 11:56:00 AM

great content

S
Srijeeta
10/8/2023 6:24:00 AM

how do i get the remaining questions?

J
Jovanne
7/26/2022 11:42:00 PM

well formatted pdf and the test engine software is free. well worth the money i sept.

C
CHINIMILLI SATISH
8/29/2023 6:22:00 AM

looking for 1z0-116

P
Pedro Afonso
1/15/2024 8:01:00 AM

in question 22, shouldnt be in the data (option a) layer?

P
Pushkar
11/7/2022 12:12:00 AM

the questions are incredibly close to real exam. you people are amazing.

A
Ankit S
11/13/2023 3:58:00 AM

q15. answer is b. simple

S
S. R
12/8/2023 9:41:00 AM

great practice

M
Mungara
3/14/2023 12:10:00 AM

thanks to this exam dumps, i felt confident and passed my exam with ease.

AI Tutor 👋 I’m here to help!