CompTIA Project+ PK0-002 Dumps in PDF

Free CompTIA PK0-002 Real Questions (page: 2)

As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?

  1. Update the work breakdown structure.
  2. Review the backlog.
  3. Seek baseline approval.
  4. Establish the resource pool.

Answer(s): C



A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

  1. Trigger the contingency plan and communicate with the stakeholders.
  2. Work with the functional managers to create a work-around.
  3. Submit a change request to the change control board.
  4. Transfer the risk by hiring a new vendor who was successful on a previous project.
  5. Set up an escalation meeting with the sponsor.

Answer(s): C



By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?

  1. Allocate resources.
  2. Determine the project budget.
  3. Develop a communication plan.
  4. Establish baselines.

Answer(s): A



A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

  1. RFI
  2. RACI
  3. WBS
  4. SOW

Answer(s): B



During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer. Which of the following documents would the project manager need in order to find this information?

  1. SLA
  2. TOR
  3. SOW
  4. NDA

Answer(s): C



Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?

  1. Approving the change request
  2. Developing a rollback plan
  3. Gathering necessary resources
  4. Defining requirements

Answer(s): B



During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

  1. Issue log
  2. Defect log
  3. Change log
  4. Task board

Answer(s): B



A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?

  1. ESG
  2. PHI
  3. PII
  4. ROI

Answer(s): A



Share your comments for CompTIA PK0-002 exam with other users:

H
Harjinder Singh
8/9/2023 4:16:00 AM

its very helpful

S
SD
7/13/2023 12:56:00 AM

good questions

K
kanjoe
7/2/2023 11:40:00 AM

good questons

M
Mahmoud
7/6/2023 4:24:00 AM

i need the dumb of the hcip security v4.0 exam

W
Wei
8/3/2023 4:18:00 AM

upload the dump please

S
Stephen
10/3/2023 6:24:00 PM

yes, iam looking this

S
Stephen
8/4/2023 9:08:00 PM

please upload cima e2 managing performance dumps

H
hp
6/16/2023 12:44:00 AM

wonderful questions

P
Priyo
11/14/2023 2:23:00 AM

i used this site since 2000, still great to support my career

J
Jude
8/29/2023 1:56:00 PM

why is the answer to "which of the following is required by scrum?" all of the following stated below since most of them are not mandatory? sprint retrospective. members must be stand up at the daily scrum. sprint burndown chart. release planning.

M
Marc blue
9/15/2023 4:11:00 AM

great job. hope this helps out.

A
Anne
9/13/2023 2:33:00 AM

upload please. many thanks!

P
pepe el toro
9/12/2023 7:55:00 PM

this is so interesting

A
Antony
11/28/2023 12:13:00 AM

great material thanks

T
Thembelani
5/30/2023 2:22:00 AM

anyone who wrote this exam recently

P
P
9/16/2023 1:27:00 AM

ok they re good

J
Jorn
7/13/2023 5:05:00 AM

relevant questions

A
AM
6/20/2023 7:54:00 PM

please post

N
Nagendra Pedipina
7/13/2023 2:22:00 AM

q:42 there has to be a image in the question to choose what does it mean from the options

B
BrainDumpee
11/18/2023 1:36:00 PM

looking for cphq dumps, where can i find these for free? please and thank you.

S
sheik
10/14/2023 11:37:00 AM

@aarun , thanks for the information. it would be great help if you share your email

R
Random user
12/11/2023 1:34:00 AM

1z0-1078-23 need this dumps

L
labuschanka
11/16/2023 6:06:00 PM

i gave the microsoft azure az-500 tests and prepared from this site as it has latest mock tests available which helped me evaluate my performance and score 919/1000

M
Marianne
10/22/2023 11:57:00 PM

i cannot see the button to go to the questions

S
sushant
6/28/2023 4:52:00 AM

good questions

A
A\MAM
6/27/2023 5:17:00 PM

q-6 ans-b correct. https://docs.paloaltonetworks.com/pan-os/9-1/pan-os-cli-quick-start/use-the-cli/commit-configuration-changes

U
unanimous
12/15/2023 6:38:00 AM

very nice very nice

A
akminocha
9/28/2023 10:36:00 AM

please help us with 1z0-1107-2 dumps

J
Jefi
9/4/2023 8:15:00 AM

please upload the practice questions

T
Thembelani
5/30/2023 2:45:00 AM

need this dumps

A
Abduraimov
4/19/2023 12:43:00 AM

preparing for this exam is overwhelming. you cannot pass without the help of these exam dumps.

P
Puneeth
10/5/2023 2:06:00 AM

new to this site but i feel it is good

A
Ashok Kumar
1/2/2024 6:53:00 AM

the correct answer to q8 is b. explanation since the mule app has a dependency, it is necessary to include project modules and dependencies to make sure the app will run successfully on the runtime on any other machine. source code of the component that the mule app is dependent of does not need to be included in the exported jar file, because the source code is not being used while executing an app. compiled code is being used instead.

M
Merry
7/30/2023 6:57:00 AM

good questions

AI Tutor 👋 I’m here to help!