CompTIA Project+ PK0-002 Dumps in PDF

Free CompTIA PK0-002 Real Questions (page: 2)

As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?

  1. Update the work breakdown structure.
  2. Review the backlog.
  3. Seek baseline approval.
  4. Establish the resource pool.

Answer(s): C



A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

  1. Trigger the contingency plan and communicate with the stakeholders.
  2. Work with the functional managers to create a work-around.
  3. Submit a change request to the change control board.
  4. Transfer the risk by hiring a new vendor who was successful on a previous project.
  5. Set up an escalation meeting with the sponsor.

Answer(s): C



By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?

  1. Allocate resources.
  2. Determine the project budget.
  3. Develop a communication plan.
  4. Establish baselines.

Answer(s): A



A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

  1. RFI
  2. RACI
  3. WBS
  4. SOW

Answer(s): B



During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer. Which of the following documents would the project manager need in order to find this information?

  1. SLA
  2. TOR
  3. SOW
  4. NDA

Answer(s): C



Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?

  1. Approving the change request
  2. Developing a rollback plan
  3. Gathering necessary resources
  4. Defining requirements

Answer(s): B



During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

  1. Issue log
  2. Defect log
  3. Change log
  4. Task board

Answer(s): B



A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?

  1. ESG
  2. PHI
  3. PII
  4. ROI

Answer(s): A



Share your comments for CompTIA PK0-002 exam with other users:

L
Limbo
10/9/2023 3:08:00 AM

this is way too informative

T
Tejasree
8/26/2023 1:46:00 AM

very helpfull

Y
Yolostar Again
10/12/2023 3:02:00 PM

q.189 - answers are incorrect.

S
Shikha Bakra
9/10/2023 5:16:00 PM

awesome job in getting these questions

K
Kevin
10/20/2023 2:01:00 AM

i cant find aws certified practitioner clf-c01 exam in aws website but i found aws certified practitioner clf-c02 exam. can everyone please verify the difference between the two clf-c01 and clf-c02? thank you

D
D Mario
6/19/2023 10:38:00 PM

grazie mille. i got a satisfactory mark in my exam test today because of this exam dumps. sorry for my english.

B
Bharat Kumar Saraf
10/31/2023 4:36:00 AM

some of the answers are incorrect. need to be reviewed.

J
JP
7/13/2023 12:21:00 PM

so far so good

K
Kiky V
8/8/2023 6:32:00 PM

i am really liking it

T
trying
7/28/2023 12:37:00 PM

thanks good stuff

E
exampei
10/4/2023 2:40:00 PM

need dump c_tadm_23

E
Eman Sawalha
6/10/2023 6:18:00 AM

next time i will write a full review

J
johnpaul
11/15/2023 7:55:00 AM

first time using this site

O
omiornil@gmail.com
7/25/2023 9:36:00 AM

please sent me oracle 1z0-1105-22 pdf

J
John
8/29/2023 8:59:00 PM

very helpful

K
Kvana
9/28/2023 12:08:00 PM

good info about oml

C
Checo Lee
7/3/2023 5:45:00 PM

very useful to practice

D
dixitdnoh@gmail.com
8/27/2023 2:58:00 PM

this website is very helpful.

S
Sanjay
8/14/2023 8:07:00 AM

good content

B
Blessious Phiri
8/12/2023 2:19:00 PM

so challenging

P
PAYAL
10/17/2023 7:14:00 AM

17 should be d ,for morequery its scale out

K
Karthik
10/12/2023 10:51:00 AM

nice question

G
Godmode
5/7/2023 10:52:00 AM

yes.

B
Bhuddhiman
7/30/2023 1:18:00 AM

good mateial

K
KJ
11/17/2023 3:50:00 PM

good practice exam

S
sowm
10/29/2023 2:44:00 PM

impressivre qustion

C
CW
7/6/2023 7:06:00 PM

questions seem helpful

L
luke
9/26/2023 10:52:00 AM

good content

Z
zazza
6/16/2023 9:08:00 AM

question 21 answer is alerts

A
Abwoch Peter
7/4/2023 3:08:00 AM

am preparing for exam

M
mohamed
9/12/2023 5:26:00 AM

good one thanks

M
Mfc
10/23/2023 3:35:00 PM

only got thru 5 questions, need more to evaluate

W
Whizzle
7/24/2023 6:19:00 AM

q26 should be b

S
sarra
1/17/2024 3:44:00 AM

the aaa triad in information security is authentication, accounting and authorisation so the answer should be d 1, 3 and 5.

AI Tutor 👋 I’m here to help!