A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?

  1. Responsibility assignment matrix
  2. Acceptable communication channels
  3. Risk registry
  4. Staff directory

Answer(s): B



A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.



Which of the following is the current status of the process?

  1. Based on the rule of seven, the process is under control.
  2. The amount of data is insufficient to determine if quality is low.
  3. The process is out of control and should be revised.
  4. The goal should be adjusted since most of the data points are close to the lower limit.

Answer(s): C



After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?

  1. Continuous integration
  2. Rollback plan
  3. Customer notification
  4. Automated testing

Answer(s): C



Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move

forward?

  1. Communicate with the affected stakeholders.
  2. Initiate a formal change request to modify the cost.
  3. Adjust the scope to stay within the cost.
  4. Set a new cost using a lightweight estimation method.

Answer(s): A



As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?

  1. Document the request in the change control log.
  2. Communicate the change deployment.
  3. Conduct an impact assessment.
  4. Implement the change.

Answer(s): D



An IT intern was assigned to set up workstations as part of a project. The IT intern was very careful to do the task well and initially referred to notes while performing the task. By the end of the two-week rotation, the IT intern no longer needed the notes and completed more set-ups in less time. Which of the following MOST likely represents the observed relationship in this scenario?





Answer(s): A



An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?

  1. Exploit the risk.
  2. Accept the risk.
  3. Avoid the risk.
  4. Transfer the risk.

Answer(s): A



The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?

  1. Data warehouse
  2. SQL database
  3. Multitier architecture
  4. Content management system

Answer(s): C



Share your comments for CompTIA PK0-002 exam with other users:

M
Meg
10/12/2023 8:02:00 AM

q 105 . ans is d

N
Navaneeth S
7/14/2023 7:57:00 AM

i have interest to get a sybase iq dba certification

A
Aish
10/11/2023 5:27:00 AM

want to pass exm.

A
Anonymous
6/12/2023 7:23:00 AM

are the answers correct?

K
Kris
7/7/2023 9:43:00 AM

good morning, could you please upload this exam again, i need it to test my knowledge in sd-wan with version 7.0.

M
Meghraj mali
10/7/2023 1:47:00 PM

very nice question

N
Noel
11/1/2022 9:14:00 PM

i have learning disability and this exam dumps allowed me to focus on the actual questions and not worry about notes and the those other study materials.

J
Jas
10/25/2023 6:01:00 PM

165 should be apt

N
Neetu
6/22/2023 8:41:00 AM

please upload the dumps, real need of them

M
Mark
10/24/2023 1:34:00 AM

any recent feeedback?

G
Gopinadh
8/9/2023 4:05:00 AM

question number 2 is indicating you are giving proper questions. observe and change properly.

S
Santhi
1/1/2024 8:23:00 AM

passed today.40% questions were new.litwere case study,lots of new questions on afd,ratelimit,tm,lb,app gatway.got 2 set series of questions which are not present here.questions on azure cyclecloud, no.of vnet/vms required for implimentation,blueprints assignment/management group etc

R
Raviraj Magadum
1/12/2024 11:39:00 AM

practice test

S
sivaramakrishnan
7/27/2023 8:12:00 AM

want the dumps for emc content management server programming(cmsp)

A
Aderonke
10/23/2023 1:52:00 PM

brilliant and helpful

A
Az
9/16/2023 2:43:00 PM

q75. azure files is pass

K
ketty
11/9/2023 8:10:00 AM

very helpful

S
Sonail
5/2/2022 1:36:00 PM

thank you for these questions. it helped a lot.

S
Shariq
7/28/2023 8:00:00 AM

how do i get the h12-724 dumps

A
adi
10/30/2023 11:51:00 PM

nice data dumps

E
EDITH NCUBE
7/25/2023 7:28:00 AM

answers are correct

R
Raja
6/20/2023 4:38:00 AM

good explanation

B
BigMouthDog
1/22/2022 8:17:00 PM

hi team just want to know if there is any update version of the exam 350-401

F
francesco
10/30/2023 11:08:00 AM

helpful on 2017 scrum guide

A
Amitabha Roy
10/5/2023 3:16:00 AM

planning to attempt for the exam.

P
Prem Yadav
7/29/2023 6:20:00 AM

pleaseee upload

A
Ahmed Hashi
7/6/2023 5:40:00 PM

thanks ly so i have information cia

M
mansi
5/31/2023 7:58:00 AM

hello team, i need sap qm dumps for practice

J
Jamil aljamil
12/4/2023 4:47:00 AM

it’s good but not senatios based

C
Cath
10/10/2023 10:19:00 AM

q.119 - the correct answer is b - they are not captured in an update set as theyre data.

P
P
1/6/2024 11:22:00 AM

good matter

S
surya
7/30/2023 2:02:00 PM

please upload c_sacp_2308

S
Sasuke
7/11/2023 10:30:00 PM

please upload the dump. thanks very much !!

V
V
7/4/2023 8:57:00 AM

good questions

AI Tutor 👋 I’m here to help!