The difference between the latest event time and the earliest event time in a project network analysis is referred to as:

  1. Critical Activity
  2. Float
  3. Critical Path
  4. Node

Answer(s): B



The Board of organisation Y has authorised an upgrade to its computerised finance system.

The Finance Director, X, has been tasked with managing this project. X has been requested to consult with stakeholders, in order that a Project Initiation Document (PID) may be produced.

What are the TWO main uses of a PID?

  1. To ensure that the project is broken down into work packages and a Work Breakdown Structure be produced.
  2. To produce a risk assessment of both internal and external risks that are likely to effect the project, and alternative actions to reduce the risks.
  3. To ensure that the project has a complete sound basis before any major commitment to
    the project.
  4. To act as a base document against which the project can be managed for progress, change management issues, and ongoing viability issues.

Answer(s): C,D



A highly complex IT project is being tackled by a self-managing team of three technical specialists who had never met each other before.

At first they argued constantly for nearly two days over the best way to tackle the work and what technical software tools to use. Finally these issues were resolved, the team went out for dinner together and they agreed how best to share the workload between them.

After this point, the productivity improved dramatically and good work progress was made. All was going well until two days later when another IT specialist turned up unexpectedly. This person was far less experienced than the other three.

The new arrival explained that he would be taking over as project manager and immediately started to give explicit orders to the team.

In the context of Tuckman's team development theory, which interpretation fits the facts of the scenario.

  1. The team had reached the performing stage but the arrival of the new specialist may result in the team reverting to the storming stage.
  2. The team had reached the norming stage and instructions from the new arrival will quickly help the team reach the performing stage.
  3. The team had already formed and were moving into the storming stage when the new arrival turned up and reset development at the forming stage.
  4. The new arrival will mean that the team will move forward from norming through storming into the final performing stage.

Answer(s): A



Q has been appointed as the Commercial Director of a medium-sized publishing company that is facing strong competitive pressures in difficult trading conditions. Q is surprised to find that the firm is pursuing the formal/rational approach to strategy development.

Q is now preparing a presentation to the Board to change the basis of strategy development to an emergent approach.

Which THREE arguments could Q use in the presentation?

  1. The rational approach takes up significant organisational resources, can be very expensive, time consuming and complicated.
  2. The rational process can end up as a bureaucratic, top-down process focusing on plans, systems and targets, leading to a loss of entrepreneurial spirit.
  3. Given an uncertain business environment, it is impossible for rational strategy makers to make reliable assumptions about the future.
  4. An emergent approach encourages managers to take a longer term view of the development of the business, rather than being short-term and reactive.
  5. From a stakeholder perspective, the emergent approach could be viewed as demonstrating that the organisation has a very clear sense of where it is going.

Answer(s): A,B,C



James argues that performance appraisal has its roots in three substantiated psychological principles, meaning that people work / learn / achieve more when they are given the opportunities.

Which of the following does NOT apply?

  1. Information for human resource planning.
  2. Involvement in the setting of tasks and goals.
  3. Adequate feedback as to how they are performing, in other words knowledge of results.
  4. Clear attainable goals so they know what to strive for.

Answer(s): A



Viewing Page 5 of 43



Share your comments for CIMA E2 exam with other users:

Eduardo Ramírez 12/11/2023 9:55:00 PM

the correct answer for the question 29 is d.
Anonymous


Dass 11/2/2023 7:43:00 AM

question no 22: correct answers: bc, 1 per session 1 per page 1 per component always
UNITED STATES


Reddy 12/14/2023 2:42:00 AM

these are pretty useful
Anonymous


Daisy Delgado 1/9/2023 1:05:00 PM

awesome
UNITED STATES


Atif 6/13/2023 4:09:00 AM

yes please upload
UNITED STATES


Xunil 6/12/2023 3:04:00 PM

great job whoever put this together, for the greater good! thanks!
Anonymous


Lakshmi 10/2/2023 5:26:00 AM

just started to view all questions for the exam
NETHERLANDS


rani 1/19/2024 11:52:00 AM

helpful material
Anonymous


Greg 11/16/2023 6:59:00 AM

hope for the best
UNITED STATES


hi 10/5/2023 4:00:00 AM

will post exam has finished
UNITED STATES


Vmotu 8/24/2023 11:14:00 AM

really correct and good analyze!
AZERBAIJAN


hicham 5/30/2023 8:57:00 AM

excellent thanks a lot
FRANCE


Suman C 7/7/2023 8:13:00 AM

will post once pass the cka exam
INDIA


Ram 11/3/2023 5:10:00 AM

good content
Anonymous


Nagendra Pedipina 7/13/2023 2:12:00 AM

q:32 answer has to be option c
INDIA


Tamer Barakat 12/7/2023 5:17:00 PM

nice questions
Anonymous


Daryl 8/1/2022 11:33:00 PM

i really like the support team in this website. they are fast in communication and very helpful.
UNITED KINGDOM


Curtis Nakawaki 6/29/2023 9:13:00 PM

a good contemporary exam review
UNITED STATES


x-men 5/23/2023 1:02:00 AM

q23, its an array, isnt it? starts with [ and end with ]. its an array of objects, not object.
UNITED STATES


abuti 7/21/2023 6:24:00 PM

cool very helpfull
Anonymous


Krishneel 3/17/2023 10:34:00 AM

i just passed. this exam dumps is the same one from prepaway and examcollection. it has all the real test questions.
INDIA


Regor 12/4/2023 2:01:00 PM

is this a valid prince2 practitioner dumps?
UNITED KINGDOM


asl 9/14/2023 3:59:00 PM

all are relatable questions
CANADA


Siyya 1/19/2024 8:30:00 PM

might help me to prepare for the exam
Anonymous


Ted 6/21/2023 11:11:00 PM

just paid and downlaod the 2 exams using the 50% sale discount. so far i was able to download the pdf and the test engine. all looks good.
GERMANY


Paul K 11/27/2023 2:28:00 AM

i think it should be a,c. option d goes against the principle of building anything custom unless there are no work arounds available
INDIA


ph 6/16/2023 12:41:00 AM

very legible
Anonymous


sephs2001 7/31/2023 10:42:00 PM

is this exam accurate or helpful?
Anonymous


ash 7/11/2023 3:00:00 AM

please upload dump, i have exam in 2 days
INDIA


Sneha 8/17/2023 6:29:00 PM

this is useful
CANADA


sachin 12/27/2023 2:45:00 PM

question 232 answer should be perimeter not netowrk layer. wrong answer selected
Anonymous


tomAws 7/18/2023 5:05:00 AM

nice questions
BRAZIL


Rahul 6/11/2023 2:07:00 AM

hi team, could you please provide this dump ?
INDIA


TeamOraTech 12/5/2023 9:49:00 AM

very helpful to clear the exam and understand the concept.
Anonymous