What needs to happen when new detailed requirements are added to a timebox?

  1. Requirements of a similar level of effort should be removed
  2. More people should be added to the delivery team
  3. The delivery milestones should be reviewed and re-planned
  4. Formal change control should be applied

Answer(s): A



Which statement about the `accept that the customer doesn't need everything' target is correct?

  1. It gives confidence on the progress of the project
  2. It can result in the early delivery of a minimum viable product
  3. It allows misunderstandings to be dealt with appropriately
  4. It is achieved by managing the culture of the team carefully

Answer(s): C



Which statement about velocity is CORRECT?

  1. It is based on the concept of rationalism
  2. It is shown by the ideal line on a bum-down chart
  3. It describes how much work is getting done
  4. It tracks the time and cost of a timebox

Answer(s): C


Reference:

https://worldofagile.com/blog/velocity/



Which is a purpose of the `controlling stage' process?

  1. To execute and deliver the project product
  2. To establish whether the project is complete
  3. To report stage progress to the project board
  4. To draft the plan for the next stage's work

Answer(s): C


Reference:

https://publications.axelos.com/PRINCE2Agile2016/content.aspx?page=pra_117&showNav=true&ex pandNav=true#:~:text=The%20purpose%20of%20the%20Controlling,the%20stage

%20remains%20within%20tolerance.&text=Risks%20and%20issues%20are%20kept%20under%20co ntrol



Which is a typical characteristic of `business as usual' work?

  1. It requires a specific dedicated project manager
  2. It is executed by program management
  3. It is delivered by a temporary team
  4. It is delivered by an established team

Answer(s): D


Reference:

https://www.prince2primer.com/prince2-agile-overview-part-1/



Viewing Page 4 of 20



Share your comments for PRINCE2 PRINCE2-Agile-Foundation exam with other users:

Harjinder Singh 8/9/2023 4:16:00 AM

its very helpful
HONG KONG


SD 7/13/2023 12:56:00 AM

good questions
UNITED STATES


kanjoe 7/2/2023 11:40:00 AM

good questons
UNITED STATES


Mahmoud 7/6/2023 4:24:00 AM

i need the dumb of the hcip security v4.0 exam
EGYPT


Wei 8/3/2023 4:18:00 AM

upload the dump please
HONG KONG


Stephen 10/3/2023 6:24:00 PM

yes, iam looking this
AUSTRALIA


Stephen 8/4/2023 9:08:00 PM

please upload cima e2 managing performance dumps
Anonymous


hp 6/16/2023 12:44:00 AM

wonderful questions
Anonymous


Priyo 11/14/2023 2:23:00 AM

i used this site since 2000, still great to support my career
INDONESIA


Jude 8/29/2023 1:56:00 PM

why is the answer to "which of the following is required by scrum?" all of the following stated below since most of them are not mandatory? sprint retrospective. members must be stand up at the daily scrum. sprint burndown chart. release planning.
UNITED STATES


Marc blue 9/15/2023 4:11:00 AM

great job. hope this helps out.
UNITED STATES


Anne 9/13/2023 2:33:00 AM

upload please. many thanks!
Anonymous


pepe el toro 9/12/2023 7:55:00 PM

this is so interesting
Anonymous


Antony 11/28/2023 12:13:00 AM

great material thanks
AUSTRALIA


Thembelani 5/30/2023 2:22:00 AM

anyone who wrote this exam recently
Anonymous


P 9/16/2023 1:27:00 AM

ok they re good
Anonymous


Jorn 7/13/2023 5:05:00 AM

relevant questions
UNITED KINGDOM


AM 6/20/2023 7:54:00 PM

please post
UNITED STATES


Nagendra Pedipina 7/13/2023 2:22:00 AM

q:42 there has to be a image in the question to choose what does it mean from the options
INDIA


BrainDumpee 11/18/2023 1:36:00 PM

looking for cphq dumps, where can i find these for free? please and thank you.
UNITED STATES


sheik 10/14/2023 11:37:00 AM

@aarun , thanks for the information. it would be great help if you share your email
Anonymous


Random user 12/11/2023 1:34:00 AM

1z0-1078-23 need this dumps
Anonymous


labuschanka 11/16/2023 6:06:00 PM

i gave the microsoft azure az-500 tests and prepared from this site as it has latest mock tests available which helped me evaluate my performance and score 919/1000
Anonymous


Marianne 10/22/2023 11:57:00 PM

i cannot see the button to go to the questions
Anonymous


sushant 6/28/2023 4:52:00 AM

good questions
EUROPEAN UNION


A\MAM 6/27/2023 5:17:00 PM

q-6 ans-b correct. https://docs.paloaltonetworks.com/pan-os/9-1/pan-os-cli-quick-start/use-the-cli/commit-configuration-changes
UNITED STATES


unanimous 12/15/2023 6:38:00 AM

very nice very nice
Anonymous


akminocha 9/28/2023 10:36:00 AM

please help us with 1z0-1107-2 dumps
INDIA


Jefi 9/4/2023 8:15:00 AM

please upload the practice questions
Anonymous


Thembelani 5/30/2023 2:45:00 AM

need this dumps
Anonymous


Abduraimov 4/19/2023 12:43:00 AM

preparing for this exam is overwhelming. you cannot pass without the help of these exam dumps.
UNITED KINGDOM


Puneeth 10/5/2023 2:06:00 AM

new to this site but i feel it is good
EUROPEAN UNION


Ashok Kumar 1/2/2024 6:53:00 AM

the correct answer to q8 is b. explanation since the mule app has a dependency, it is necessary to include project modules and dependencies to make sure the app will run successfully on the runtime on any other machine. source code of the component that the mule app is dependent of does not need to be included in the exported jar file, because the source code is not being used while executing an app. compiled code is being used instead.
Anonymous


Merry 7/30/2023 6:57:00 AM

good questions
Anonymous