What is the collective name for individuals or groups who may be affected by a project?
Answer(s): C
In PRINCE2, the collective name for individuals or groups who may be affected by or can influence a project is "Stakeholders." This includes a wide range of people such as customers, users, team members, and suppliers, each of whom has an interest in the project's successful execution and outcomes.
PRINCE2 Foundation manual, PRINCE2 official resources
Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?
To control the size of the Project Board on a project that involves multiple users and suppliers, creating user and supplier groups is an effective strategy. These groups can represent broader interests and provide input to the Project Board, helping to streamline decision-making processes without overloading the board with members.
When should the Project Board refer to corporate or programme management for a decision?
Answer(s): B
The Project Board should refer to corporate or programme management for decisions when it is forecast that the project level tolerance will be exceeded. This scenario typically triggers an exception process as the predefined tolerances are fundamental limits within which the Project Board allows the Project Manager to manage the project.
PRINCE2® Foundation official study guide and materials.
Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.
The Communication Management Strategy should be referred to at the end of a stage to check whether there is a requirement to send copies of the End Stage Report to external interested parties. This document outlines how, when, and by whom information will be disseminated throughout the project, including communication with external stakeholders.
Which is NOT a purpose of the Organization theme?
The Organization theme does not include defining the level of tolerance for each level of the project management team. Tolerance levels are typically set within the Plans theme, which deals with how the project is structured in terms of stages and the delegation of authority within those tolerances. The Organization theme primarily focuses on defining roles and responsibilities.
Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
Answer(s): A
PRINCE2® identifies three primary categories of stakeholders: 1) those who will specify the desired outputs (customers/users), 2) those who will manage the project on a day-to-day basis (suppliers), and 3) those who use the project's outputs. Those with a financial interest in the project are not explicitly categorized as one of the primary stakeholder types in PRINCE2®.
Which does the Executive need to ensure is in place before the project is initiated?
Before initiating a project, the Executive in PRINCE2 needs to ensure there is a clear understanding of how the project will contribute to the corporate objectives. This alignment is crucial for justifying the project's existence and ensuring it has a clear business purpose and expected benefits that support the organization's strategic goals.
Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?
The Senior User within the PRINCE2 project management team represents the interests of those who will use the project's products and benefit from their operation after the project is complete. This role is responsible for specifying the needs of users, ensuring the solution meets these needs, and is capable of delivering the anticipated benefits.
Share your comments for PRINCE2 PRINCE2-7-Foundation exam with other users:
is this dump still valid???
question 205 answer is b
question 39, should be answer b, directions stated is being sudneted from /21 to a /23. a /23 has 512 ips so 510 hosts. and can make 4 subnets out of the /21
beautiful test engine software and very helpful. questions are same as in the real exam. i passed my paper.
the questions are exactly the same in real exam. just make sure not to answer all them correct or else they suspect you are cheating.
question: 78 the right answer i think is d not a
very helpful
i am writing this exam tomorrow and have dumps
can i have the icdl excel exam
please upload it
hye when will post again the past year question for this h13-311_v3 part since i have to for my test tommorow…thank you very much
on question 22, option b-once per session is also valid.
this website is very helpful
its my first time exam
correct answers are device configuration-enable the automatic installation of webview2 runtime. & policy management- prevent users from submitting feedback.
is this dump still valid? today is 9-july-2023
i need this exam.. please upload these are really helpful
please upload the oracle 1z0-1059-22 dumps
very good questions
nice, first step to exams
is this valid for chfiv9 as well... as i am reker 3rd time...
great exam for people taking 220-1101
this is very helpfull for me
just started preparing for the exam
these are the type of questions i need.
does this actually work? are they the exam questions and answers word for word?
thanks for providing these questions
interesting
these dumps are pretty good.
good questions
dbua is used for upgrading oracle database
i am thrilled to say that i passed my amazon web services mls-c01 exam, thanks to study materials. they were comprehensive and well-structured, making my preparation efficient.
please upload latest ibm ace c1000-056 dumps
if only explanations were provided...