A project team meets to estimate user stories for a sprint. While an important non-functional requirement must be delivered in the sprint, the estimate exceeds sprint capacity.
What should the team do?

  1. Estimate only functional requirements that will impact product quality
  2. Add team resources
  3. Refer the issue tot eh product owner
  4. Break non-functional requirements into those that can be delivered in the given sprint

Answer(s): C



A development team and product owner disagrees on a user story in the product backlog.
What should the agile practitioner do?

  1. Have the development team follow the product owner's direction
  2. Openly challenge the product owner in the effort to poke holes in their approach
  3. Facilitate a conversation about the user story between the development team and the product owner
  4. Serve as a nonpartisan evaluator of each option, and provide direction to the development team and product owner

Answer(s): C



During a planning session, four out of five team members vote to include eight story points in a particular story, while the fifth member votes for five story points.
How should this be handled?

  1. The story should be assigned eight story points as per the majority vote
  2. The story should be added to the backlog and reassessed later
  3. The story should be assigned points after a discussion with the fifth team member to see if a consensus can be reached
  4. The decision for the number of story points should be made by the customer

Answer(s): C



A project is starting and the type of work is complex and suitable for agile. In assessing the team members, it appears that co-location would be a challenge.
What should the agile practitioner do?

  1. Select and implement collaboration tools to augment team interactions
  2. Provide each geographical area with their own product owner and divide the work between the teams
  3. Increase the number of requirements documents and ensure they are clearly communicated
  4. After several sprints, calculate velocity based on primary team location and use secondary team as reserve

Answer(s): A



Team A is working on the second sprint of a product release. Team B, which is an interdependent team located on the same floor, requires exclusive and frequent information to complete its sprint goal.
What should the agile team do?

  1. Create a central repository for information, and provide access to team B
  2. Use an information board that will be visible to all passing through the workspace
  3. Email all stakeholders with status updates
  4. Provide team B with the information on an ג€as neededג€ basis

Answer(s): B



Share your comments for PMI PMI-ACP exam with other users:

S
sk
5/13/2023 2:10:00 AM

ecellent materil for unserstanding

G
Gerard
6/29/2023 11:14:00 AM

good so far

L
Limbo
10/9/2023 3:08:00 AM

this is way too informative

T
Tejasree
8/26/2023 1:46:00 AM

very helpfull

Y
Yolostar Again
10/12/2023 3:02:00 PM

q.189 - answers are incorrect.

S
Shikha Bakra
9/10/2023 5:16:00 PM

awesome job in getting these questions

K
Kevin
10/20/2023 2:01:00 AM

i cant find aws certified practitioner clf-c01 exam in aws website but i found aws certified practitioner clf-c02 exam. can everyone please verify the difference between the two clf-c01 and clf-c02? thank you

D
D Mario
6/19/2023 10:38:00 PM

grazie mille. i got a satisfactory mark in my exam test today because of this exam dumps. sorry for my english.

B
Bharat Kumar Saraf
10/31/2023 4:36:00 AM

some of the answers are incorrect. need to be reviewed.

J
JP
7/13/2023 12:21:00 PM

so far so good

K
Kiky V
8/8/2023 6:32:00 PM

i am really liking it

T
trying
7/28/2023 12:37:00 PM

thanks good stuff

E
exampei
10/4/2023 2:40:00 PM

need dump c_tadm_23

E
Eman Sawalha
6/10/2023 6:18:00 AM

next time i will write a full review

J
johnpaul
11/15/2023 7:55:00 AM

first time using this site

O
omiornil@gmail.com
7/25/2023 9:36:00 AM

please sent me oracle 1z0-1105-22 pdf

J
John
8/29/2023 8:59:00 PM

very helpful

K
Kvana
9/28/2023 12:08:00 PM

good info about oml

C
Checo Lee
7/3/2023 5:45:00 PM

very useful to practice

D
dixitdnoh@gmail.com
8/27/2023 2:58:00 PM

this website is very helpful.

S
Sanjay
8/14/2023 8:07:00 AM

good content

B
Blessious Phiri
8/12/2023 2:19:00 PM

so challenging

P
PAYAL
10/17/2023 7:14:00 AM

17 should be d ,for morequery its scale out

K
Karthik
10/12/2023 10:51:00 AM

nice question

G
Godmode
5/7/2023 10:52:00 AM

yes.

B
Bhuddhiman
7/30/2023 1:18:00 AM

good mateial

K
KJ
11/17/2023 3:50:00 PM

good practice exam

S
sowm
10/29/2023 2:44:00 PM

impressivre qustion

C
CW
7/6/2023 7:06:00 PM

questions seem helpful

L
luke
9/26/2023 10:52:00 AM

good content

Z
zazza
6/16/2023 9:08:00 AM

question 21 answer is alerts

A
Abwoch Peter
7/4/2023 3:08:00 AM

am preparing for exam

M
mohamed
9/12/2023 5:26:00 AM

good one thanks

M
Mfc
10/23/2023 3:35:00 PM

only got thru 5 questions, need more to evaluate

AI Tutor 👋 I’m here to help!