PMI Agile Certified Practitioner PMI-ACP Dumps in PDF

Free PMI PMI-ACP Real Questions (page: 32)

A project team meets to estimate user stories for a sprint. While an important non-functional requirement must be delivered in the sprint, the estimate exceeds sprint capacity.
What should the team do?

  1. Estimate only functional requirements that will impact product quality
  2. Add team resources
  3. Refer the issue tot eh product owner
  4. Break non-functional requirements into those that can be delivered in the given sprint

Answer(s): C



A development team and product owner disagrees on a user story in the product backlog.
What should the agile practitioner do?

  1. Have the development team follow the product owner's direction
  2. Openly challenge the product owner in the effort to poke holes in their approach
  3. Facilitate a conversation about the user story between the development team and the product owner
  4. Serve as a nonpartisan evaluator of each option, and provide direction to the development team and product owner

Answer(s): C



During a planning session, four out of five team members vote to include eight story points in a particular story, while the fifth member votes for five story points.
How should this be handled?

  1. The story should be assigned eight story points as per the majority vote
  2. The story should be added to the backlog and reassessed later
  3. The story should be assigned points after a discussion with the fifth team member to see if a consensus can be reached
  4. The decision for the number of story points should be made by the customer

Answer(s): C



A project is starting and the type of work is complex and suitable for agile. In assessing the team members, it appears that co-location would be a challenge.
What should the agile practitioner do?

  1. Select and implement collaboration tools to augment team interactions
  2. Provide each geographical area with their own product owner and divide the work between the teams
  3. Increase the number of requirements documents and ensure they are clearly communicated
  4. After several sprints, calculate velocity based on primary team location and use secondary team as reserve

Answer(s): A



Team A is working on the second sprint of a product release. Team B, which is an interdependent team located on the same floor, requires exclusive and frequent information to complete its sprint goal.
What should the agile team do?

  1. Create a central repository for information, and provide access to team B
  2. Use an information board that will be visible to all passing through the workspace
  3. Email all stakeholders with status updates
  4. Provide team B with the information on an ג€as neededג€ basis

Answer(s): B



Share your comments for PMI PMI-ACP exam with other users:

M
Muhammad Rawish Siddiqui
11/29/2023 12:14:00 PM

wrong answer. it is true not false.

J
Josh
7/10/2023 1:54:00 PM

please i need the mo-100 questions

V
VINNY
6/2/2023 11:59:00 AM

very good use full

A
Andy
12/6/2023 5:56:00 AM

very valid questions

M
Mamo
8/12/2023 7:46:00 AM

will these question help me to clear pl-300 exam?

M
Marial Manyang
7/26/2023 10:13:00 AM

please provide me with these dumps questions. thanks

A
Amel Mhamdi
12/16/2022 10:10:00 AM

in the pdf downloaded is write google cloud database engineer i think that it isnt the correct exam

A
Angel
8/30/2023 10:58:00 PM

i think you have the answers wrong regarding question: "what are three core principles of web content accessibility guidelines (wcag)? answer: robust, operable, understandable

S
SH
5/16/2023 1:43:00 PM

these questions are not valid , they dont come for the exam now

S
sudhagar
9/6/2023 3:02:00 PM

question looks valid

V
Van
11/24/2023 4:02:00 AM

good for practice

D
Divya
8/2/2023 6:54:00 AM

need more q&a to go ahead

R
Rakesh
10/6/2023 3:06:00 AM

question 59 - a newly-created role is not assigned to any user, nor granted to any other role. answer is b https://docs.snowflake.com/en/user-guide/security-access-control-overview

N
Nik
11/10/2023 4:57:00 AM

just passed my exam today. i saw all of these questions in my text today. so i can confirm this is a valid dump.

D
Deep
6/12/2023 7:22:00 AM

needed dumps

T
tumz
1/16/2024 10:30:00 AM

very helpful

N
NRI
8/27/2023 10:05:00 AM

will post once the exam is finished

K
kent
11/3/2023 10:45:00 AM

relevant questions

Q
Qasim
6/11/2022 9:43:00 AM

just clear exam on 10/06/2202 dumps is valid all questions are came same in dumps only 2 new questions total 46 questions 1 case study with 5 question no lab/simulation in my exam please check the answers best of luck

C
Cath
10/10/2023 10:09:00 AM

q.112 - correct answer is c - the event registry is a module that provides event definitions. answer a - not correct as it is the definition of event log

S
Shiji
10/15/2023 1:31:00 PM

good and useful.

A
Ade
6/25/2023 1:14:00 PM

good questions

P
Praveen P
11/8/2023 5:18:00 AM

good content

A
Anastasiia
12/28/2023 9:06:00 AM

totally not correct answers. 21. you have one gcp account running in your default region and zone and another account running in a non-default region and zone. you want to start a new compute engine instance in these two google cloud platform accounts using the command line interface. what should you do? correct: create two configurations using gcloud config configurations create [name]. run gcloud config configurations activate [name] to switch between accounts when running the commands to start the compute engine instances.

P
Priyanka
7/24/2023 2:26:00 AM

kindly upload the dumps

N
Nabeel
7/25/2023 4:11:00 PM

still learning

G
gure
7/26/2023 5:10:00 PM

excellent way to learn

C
ciken
8/24/2023 2:55:00 PM

help so much

B
Biswa
11/20/2023 9:28:00 AM

understand sql col.

S
Saint Pierre
10/24/2023 6:21:00 AM

i would give 5 stars to this website as i studied for az-800 exam from here. it has all the relevant material available for preparation. i got 890/1000 on the test.

R
Rose
7/24/2023 2:16:00 PM

this is nice.

A
anon
10/15/2023 12:21:00 PM

q55- the ridac workflow can be modified using flow designer, correct answer is d not a

N
NanoTek3
6/13/2022 10:44:00 PM

by far this is the most accurate exam dumps i have ever purchased. all questions are in the exam. i saw almost 90% of the questions word by word.

E
eriy
11/9/2023 5:12:00 AM

i cleared the az-104 exam by scoring 930/1000 on the exam. it was all possible due to this platform as it provides premium quality service. thank you!