Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?

  1. Organizational process updates
  2. Quality metrics
  3. Change requests
  4. Quality control measurements

Answer(s): B

Explanation:

8.1.3.3 Quality Metrics
A quality metric specifically describes a project or product attribute and how the control quality process will measure it. A measurement is an actual value. The tolerance defines the allowable variations to the metric. For example, if the quality objective is to stay within the approved budget by ± 10%, the specific quality metric is used to measure the cost of every deliverable and determine the percent variance from the approved budget for that deliverable. Quality metrics are used in the perform quality assurance and control quality processes.
Some examples of quality metrics include on-time performance, cost control, defect frequency, failure rate, availability, reliability, and test coverage.

Process: 8.1 Plan Quality Management

Definition: The process of identifying quality requirements and/or standards for the project and its deliverables and documenting how the project will demonstrate compliance with quality requirements and/or standards.
Key Benefit: The key benefit of this process is that it provides guidance and direction on how quality will be managed and validated throughout the project.

Inputs
1. Project management plan
2. Stakeholder register
3. Risk register
4. Requirements documentation
5. Enterprise environmental factors
6. Organizational process assets

1. Tools & Techniques
2. Cost-benefit analysis
3. Cost of quality
4. Seven basic quality tools
5. Benchmarking
6. Design of experiments
7. Statistical sampling
8. Additional quality planning tools
9. Meetings

Outputs
1. Quality management plan
2. Process improvement plan
3. Quality metrics
4. Quality checklists
5. Project documents updates

Process: 8.2 Perform Quality Assurance
Definition: The process of auditing the quality requirements and the results from quality control measurements to ensure that appropriate quality standards and operational definitions are used.
Key Benefit: The key benefit of this process is that it facilitates the improvement of quality processes.

Inputs
1. Quality management plan
2. Process improvement plan
3. Quality metrics
4. Quality control measurements
5. Project documents

Tools & Techniques
1. Quality management and control tools
2. Quality audits
3. Process analysis

Outputs
1. Change requests
2. Project management plan updates
3. Project documents updates
4. Organizational process assets updates



A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?

  1. Urgent information need
  2. Sensitivity of information
  3. Project environment
  4. Ease of use

Answer(s): C

Explanation:

Project environment. There is a need to determine if the team will meet and operate on a face-to-face basis or in a virtual environment; whether they will be located in one or multiple time zones; whether they will use multiple languages for communication; and finally, whether there are any other project environmental factors, such as culture, which may affect communications.



The number of potential communication channels for a project with 5 stakeholders is:

  1. 10.
  2. 12.
  3. 20.
  4. 24.

Answer(s): A

Explanation:

Number of communication channels within a project. N (N – 1) / 2, where N represents the number of identified stakeholders.



The process of prioritizing risks for further analysis or action is known as:

  1. Plan Risk Management.
  2. Plan Risk Responses.
  3. Perform Qualitative Risk Analysis.
  4. Perform Quantitative Risk Analysis.

Answer(s): C

Explanation:

Process: 11.3 Perform Qualitative Risk Analysis
Definition: The process of prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact.
Key Benefit: The key benefit of this process is that it enables project managers to reduce the level of uncertainty and to focus on high-priority risks.

Inputs
1. Risk management plan
2. Scope baseline
3. Risk register
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Risk probability and impact assessment
2. Probability and impact matrix
3. Risk data quality assessment
4. Risk categorization
5. Risk urgency assessment
6. Expert judgment

Outputs
1. Project documents updates



Which tool or technique is used in validating the scope of a project?

  1. Facilitated workshops
  2. Interviews
  3. Inspection
  4. Meetings

Answer(s): C

Explanation:

5.5.2 Validate Scope: Tools and Techniques
5.5.2.1 Inspection
Inspection includes activities such as measuring, examining, and validating to determine whether work and deliverables meet requirements and product acceptance criteria. Inspections are sometimes called reviews, product reviews, audits, and walkthroughs. In some application areas, these different terms have unique and specific meanings.

Process: 5.5 Validate Scope
Definition: The process of formalizing acceptance of the completed project deliverables.
Key Benefit: The key benefit of this process is that it brings objectivity to the acceptance process and increases the chance of final product, service, or result acceptance by validating each deliverable.

Inputs
1. Project management plan
2. Requirements documentation
3. Requirements traceability matrix
4. Verified deliverables
5. Work performance data

Tools & Techniques
1. Inspection
2. Group decision-making techniques

Outputs
1. Accepted deliverables
2. Change requests
3. Work performance information
4. Project documents updates



Share your comments for PMI PMI-100 exam with other users:

E
ethan
9/24/2023 12:38:00 PM

could you please upload practice questions for scr exam ?

V
vijay joshi
8/19/2023 3:15:00 AM

please upload free oracle cloud infrastructure 2023 foundations associate exam braindumps

A
Ayodele Talabi
8/25/2023 9:25:00 PM

sweating! they are tricky

R
Romero
3/23/2022 4:20:00 PM

i never use these dumps sites but i had to do it for this exam as it is impossible to pass without using these question dumps.

J
John Kennedy
9/20/2023 3:33:00 AM

good practice and well sites.

N
Nenad
7/12/2022 11:05:00 PM

passed my first exam last week and pass the second exam this morning. thank you sir for all the help and these brian dumps.

L
Lucky
10/31/2023 2:01:00 PM

does anyone who attended exam csa 8.8, can confirm these questions are really coming ? or these are just for practicing?

P
Prateek
9/18/2023 11:13:00 AM

kindly share the dumps

I
Irfan
11/25/2023 1:26:00 AM

very nice content

P
php
6/16/2023 12:49:00 AM

passed today

D
Durga
6/23/2023 1:22:00 AM

hi can you please upload questions

J
JJ
5/28/2023 4:32:00 AM

please upload quetions

N
Norris
1/3/2023 8:06:00 PM

i passed my exam thanks to this braindumps questions. these questions are valid in us and i highly recommend it!

A
abuti
7/21/2023 6:10:00 PM

are they truely latest

C
Curtis Nakawaki
7/5/2023 8:46:00 PM

questions appear contemporary.

V
Vv
12/2/2023 6:31:00 AM

good to prepare in this site

P
praveenkumar
11/20/2023 11:57:00 AM

very helpful to crack first attempt

A
asad Raza
5/15/2023 5:38:00 AM

please upload this exam

R
Reeta
7/17/2023 5:22:00 PM

please upload the c_activate22 dump questions with answer

W
Wong
12/20/2023 11:34:00 AM

q10 - the answer should be a. if its c, the criteria will meet if either the prospect is not part of the suppression lists or if the job title contains vice president

D
david
12/12/2023 12:38:00 PM

this was on the exam as of 1211/2023

T
Tink
7/24/2023 9:23:00 AM

great for prep

J
Jaro
12/18/2023 3:12:00 PM

i think in question 7 the first answer should be power bi portal (not power bi)

9
9eagles
4/7/2023 10:04:00 AM

on question 10 and so far 2 wrong answers as evident in the included reference link.

T
Tai
8/28/2023 5:28:00 AM

wonderful material

V
VoiceofMidnight
12/29/2023 4:48:00 PM

i passed!! ...but barely! got 728, but needed 720 to pass. the exam hit me with labs right out of the gate! then it went to multiple choice. protip: study the labs!

A
A K
8/3/2023 11:56:00 AM

correct answer for question 92 is c -aws shield

N
Nitin Mindhe
11/27/2023 6:12:00 AM

great !! it is really good

B
BailleyOne
11/22/2023 1:45:00 AM

explanations for the answers are to the point.

P
patel
10/25/2023 8:17:00 AM

how can rea next

M
MortonG
10/19/2023 6:32:00 PM

question: 128 d is the wrong answer...should be c

J
Jayant
11/2/2023 3:15:00 AM

thanks for az 700 dumps

B
Bipul Mishra
12/14/2023 7:12:00 AM

thank you for this tableau dumps . it will helpfull for tableau certification

H
hello
10/31/2023 12:07:00 PM

good content

AI Tutor 👋 I’m here to help!