PMI Program Management Professional PGMP Dumps in PDF

Free PMI PGMP Real Questions (page: 47)

Ned is the program manager for his organization and he's considering some new materials for his program. He and his team have never worked with these materials before and he wants to ask the vendor for some additional information, a demon, and even some samples. What type of a document should Ned send to the vendor?

  1. RFI
  2. RFP
  3. RFQ
  4. IFB

Answer(s): A



If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?

  1. .99
  2. -$2,500
  3. $2,500
  4. 1.02

Answer(s): C



Which benefit measurement method considers the value of each time period's return for a project that will create deliverables over multiple time periods?

  1. Net present value
  2. Future value
  3. Present value
  4. Cost-Benefit ratio

Answer(s): A



Which of the following types of floats are available? Each correct answer represents a complete solution. Choose two.

  1. Half float
  2. Full float
  3. Total float
  4. Free float

Answer(s): C,D



You are the program manager of the YHT Program. You have been working with a vendor in the program but have decided that the contract between your program and the vendor needs to be terminated. What two things must be documented if you wish to terminate a vendor's contract?

  1. Contract and the quality measurements for the vendor's work
  2. The scope verification document and the termination notice
  3. Contract and scope verification process documents
  4. Work that has been completed and uncompleted work

Answer(s): D



In your program you must adhere to Six Sigma as part of your organization's enterprise environmental factors. There is terminology, reports, and measurements that you are expected to use as part of your program. Six Sigma is an example of what program management process?

  1. Quality control
  2. Process improvement
  3. Scope verification
  4. Quality assurance

Answer(s): D



You are the program manager of the NHQ Program. You will need to initiate six projects for your program. When should project initiating happen within a program?

  1. Whenever the program needs to initiate projects, it may, as long as the program has not entered the closing processes of the program.
  2. With program execution
  3. With program initiation
  4. With program planning

Answer(s): A



Joan is the program manager for her organization. Throughout the program life cycle there will be several elements, resources, and benefits that can be transitioned from her program to the organization. What document defines how these things can be transferred from the program to the organization?

  1. Operational transfer alliance plan
  2. Program milestone list
  3. Program transition agreement
  4. Program scope statement

Answer(s): C



Share your comments for PMI PGMP exam with other users:

D
Damien
9/23/2023 8:37:00 AM

i need this exam pls

N
Nani
9/10/2023 12:02:00 PM

its required for me, please make it enable to access. thanks

E
ethiopia
8/2/2023 2:18:00 AM

seems good..

W
whoAreWeReally
12/19/2023 8:29:00 PM

took the test last week, i did have about 15 - 20 word for word from this site on the test. (only was able to cram 600 of the questions from this site so maybe more were there i didnt review) had 4 labs, bgp, lacp, vrf with tunnels and actually had to skip a lab due to time. lots of automation syntax questions.

V
vs
9/2/2023 12:19:00 PM

no comments

J
john adenu
11/14/2023 11:02:00 AM

nice questions bring out the best in you.

O
Osman
11/21/2023 2:27:00 PM

really helpful

E
Edward
9/13/2023 5:27:00 PM

question #50 and question #81 are exactly the same questions, azure site recovery provides________for virtual machines. the first says that it is fault tolerance is the answer and second says disater recovery. from my research, it says it should be disaster recovery. can anybody explain to me why? thank you

M
Monti
5/24/2023 11:14:00 PM

iam thankful for these exam dumps questions, i would not have passed without this exam dumps.

A
Anon
10/25/2023 10:48:00 PM

some of the answers seem to be inaccurate. q10 for example shouldnt it be an m custom column?

P
PeterPan
10/18/2023 10:22:00 AM

are the question real or fake?

C
CW
7/11/2023 3:19:00 PM

thank you for providing such assistance.

M
Mn8300
11/9/2023 8:53:00 AM

nice questions

N
Nico
4/23/2023 11:41:00 PM

my 3rd purcahse from this site. these exam dumps are helpful. very helpful.

C
Chere
9/15/2023 4:21:00 AM

found it good

T
Thembelani
5/30/2023 2:47:00 AM

excellent material

V
vinesh phale
9/11/2023 2:51:00 AM

very helpfull

B
Bhagiii
11/4/2023 7:04:00 AM

well explained.

R
Rahul
8/8/2023 9:40:00 PM

i need the pdf, please.

C
CW
7/11/2023 2:51:00 PM

a good source for exam preparation

A
Anchal
10/23/2023 4:01:00 PM

nice questions

J
J Nunes
9/29/2023 8:19:00 AM

i need ielts general training audio guide questions

A
Ananya
9/14/2023 5:16:00 AM

please make this content available

S
Swathi
6/4/2023 2:18:00 PM

content is good

L
Leo
7/29/2023 8:45:00 AM

latest dumps please

L
Laolu
2/15/2023 11:04:00 PM

aside from pdf the test engine software is helpful. the interface is user-friendly and intuitive, making it easy to navigate and find the questions.

Z
Zaynik
9/17/2023 5:36:00 AM

questions and options are correct, but the answers are wrong sometimes. so please check twice or refer some other platform for the right answer

M
Massam
6/11/2022 5:55:00 PM

90% of questions was there but i failed the exam, i marked the answers as per the guide but looks like they are not accurate , if not i would have passed the exam given that i saw about 45 of 50 questions from dump

A
Anonymous
12/27/2023 12:47:00 AM

answer to this question "what administrative safeguards should be implemented to protect the collected data while in use by manasa and her product management team? " it should be (c) for the following reasons: this administrative safeguard involves controlling access to collected data by ensuring that only individuals who need the data for their job responsibilities have access to it. this helps minimize the risk of unauthorized access and potential misuse of sensitive information. while other options such as (a) documenting data flows and (b) conducting a privacy impact assessment (pia) are important steps in data protection, implementing a "need to know" access policy directly addresses the issue of protecting data while in use by limiting access to those who require it for legitimate purposes. (d) is not directly related to safeguarding data during use; it focuses on data transfers and location.

J
Japles
5/23/2023 9:46:00 PM

password lockout being the correct answer for question 37 does not make sense. it should be geofencing.

F
Faritha
8/10/2023 6:00:00 PM

for question 4, the righr answer is :recover automatically from failures

A
Anonymous
9/14/2023 4:27:00 AM

question number 4s answer is 3, option c. i

P
p das
12/7/2023 11:41:00 PM

very good questions

A
Anna
1/5/2024 1:12:00 AM

i am confused about the answers to the questions. are the answers correct?

AI Tutor 👋 I’m here to help!