Ned is the program manager for his organization and he's considering some new materials for his program. He and his team have never worked with these materials before and he wants to ask the vendor for some additional information, a demon, and even some samples. What type of a document should Ned send to the vendor?

  1. RFI
  2. RFP
  3. RFQ
  4. IFB

Answer(s): A



If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?

  1. .99
  2. -$2,500
  3. $2,500
  4. 1.02

Answer(s): C



Which benefit measurement method considers the value of each time period's return for a project that will create deliverables over multiple time periods?

  1. Net present value
  2. Future value
  3. Present value
  4. Cost-Benefit ratio

Answer(s): A



Which of the following types of floats are available? Each correct answer represents a complete solution. Choose two.

  1. Half float
  2. Full float
  3. Total float
  4. Free float

Answer(s): C,D



You are the program manager of the YHT Program. You have been working with a vendor in the program but have decided that the contract between your program and the vendor needs to be terminated. What two things must be documented if you wish to terminate a vendor's contract?

  1. Contract and the quality measurements for the vendor's work
  2. The scope verification document and the termination notice
  3. Contract and scope verification process documents
  4. Work that has been completed and uncompleted work

Answer(s): D



In your program you must adhere to Six Sigma as part of your organization's enterprise environmental factors. There is terminology, reports, and measurements that you are expected to use as part of your program. Six Sigma is an example of what program management process?

  1. Quality control
  2. Process improvement
  3. Scope verification
  4. Quality assurance

Answer(s): D



You are the program manager of the NHQ Program. You will need to initiate six projects for your program. When should project initiating happen within a program?

  1. Whenever the program needs to initiate projects, it may, as long as the program has not entered the closing processes of the program.
  2. With program execution
  3. With program initiation
  4. With program planning

Answer(s): A



Joan is the program manager for her organization. Throughout the program life cycle there will be several elements, resources, and benefits that can be transitioned from her program to the organization. What document defines how these things can be transferred from the program to the organization?

  1. Operational transfer alliance plan
  2. Program milestone list
  3. Program transition agreement
  4. Program scope statement

Answer(s): C



Share your comments for PMI PGMP exam with other users:

M
Miguel
10/5/2023 12:21:00 PM

question 16: https://help.salesforce.com/s/articleview?id=sf.care_console_overview.htm&type=5

H
Hiren Ladva
7/8/2023 10:34:00 PM

yes i m prepared exam

O
oliverjames
10/24/2023 5:37:00 AM

my experience was great with this site as i studied for the ms-900 from here and got 900/1000 on the test. my main focus was on the tutorials which were provided and practice questions. thanks!

B
Bhuddhiman
7/20/2023 11:52:00 AM

great course

A
Anuj
1/14/2024 4:07:00 PM

very good question

S
Saravana Kumar TS
12/8/2023 9:49:00 AM

question: 93 which statement is true regarding the result? sales contain 6 columns and values contain 7 columns so c is not right answer.

L
Lue
3/30/2023 11:43:00 PM

highly recommend just passed my exam.

D
DC
1/7/2024 10:17:00 AM

great practice! thanks

A
Anonymus
11/9/2023 5:41:00 AM

anyone who wrote this exam recently?

K
Khalid Javid
11/17/2023 3:46:00 PM

kindly share the dump

N
Na
8/9/2023 8:39:00 AM

could you please upload cfe fraud prevention and deterrence questions? it will be very much helpful.

S
shime
10/23/2023 10:03:00 AM

this is really very very helpful for mcd level 1

V
Vnu
6/3/2023 2:39:00 AM

very helpful!

S
Steve
8/17/2023 2:19:00 PM

question #18s answer should be a, not d. this should be corrected. it should be minvalidityperiod

R
RITEISH
12/24/2023 4:33:00 AM

thanks for the exact solution

S
SB
10/15/2023 7:58:00 AM

need to refer the questions and have to give the exam

M
Mike Derfalem
7/16/2023 7:59:00 PM

i need it right now if it was possible please

I
Isak
7/6/2023 3:21:00 AM

i need it very much please share it in the fastest time.

M
Maria
6/23/2023 11:40:00 AM

correct answer is d for student.java program

N
Nagendra Pedipina
7/12/2023 9:10:00 AM

q:37 c is correct

J
John
9/16/2023 9:37:00 PM

q6 exam topic: terramearth, c: correct answer: copy 1petabyte to encrypted usb device ???

S
SAM
12/4/2023 12:56:00 AM

explained answers

A
Andy
12/26/2023 9:35:00 PM

plan to take theaws certified developer - associate dva-c02 in the next few weeks

S
siva
5/17/2023 12:32:00 AM

very helpfull

M
mouna
9/27/2023 8:53:00 AM

good questions

B
Bhavya
9/12/2023 7:18:00 AM

help to practice csa exam

M
Malik
9/28/2023 1:09:00 PM

nice tip and well documented

R
rodrigo
6/22/2023 7:55:00 AM

i need the exam

D
Dan
6/29/2023 1:53:00 PM

please upload

A
Ale M
11/22/2023 6:38:00 PM

prepping for fsc exam

A
ahmad hassan
9/6/2023 3:26:00 AM

pd1 with great experience

Ž
Žarko
9/5/2023 3:35:00 AM

@t it seems like azure service bus message quesues could be the best solution

S
Shiji
10/15/2023 1:08:00 PM

helpful to check your understanding.

D
Da Costa
8/27/2023 11:43:00 AM

question 128 the answer should be static not auto

AI Tutor 👋 I’m here to help!