Ned is the program manager for his organization and he's considering some new materials for his program. He and his team have never worked with these materials before and he wants to ask the vendor for some additional information, a demon, and even some samples. What type of a document should Ned send to the vendor?

  1. RFI
  2. RFP
  3. RFQ
  4. IFB

Answer(s): A



If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?

  1. .99
  2. -$2,500
  3. $2,500
  4. 1.02

Answer(s): C



Which benefit measurement method considers the value of each time period's return for a project that will create deliverables over multiple time periods?

  1. Net present value
  2. Future value
  3. Present value
  4. Cost-Benefit ratio

Answer(s): A



Which of the following types of floats are available? Each correct answer represents a complete solution. Choose two.

  1. Half float
  2. Full float
  3. Total float
  4. Free float

Answer(s): C,D



You are the program manager of the YHT Program. You have been working with a vendor in the program but have decided that the contract between your program and the vendor needs to be terminated. What two things must be documented if you wish to terminate a vendor's contract?

  1. Contract and the quality measurements for the vendor's work
  2. The scope verification document and the termination notice
  3. Contract and scope verification process documents
  4. Work that has been completed and uncompleted work

Answer(s): D



In your program you must adhere to Six Sigma as part of your organization's enterprise environmental factors. There is terminology, reports, and measurements that you are expected to use as part of your program. Six Sigma is an example of what program management process?

  1. Quality control
  2. Process improvement
  3. Scope verification
  4. Quality assurance

Answer(s): D



You are the program manager of the NHQ Program. You will need to initiate six projects for your program. When should project initiating happen within a program?

  1. Whenever the program needs to initiate projects, it may, as long as the program has not entered the closing processes of the program.
  2. With program execution
  3. With program initiation
  4. With program planning

Answer(s): A



Joan is the program manager for her organization. Throughout the program life cycle there will be several elements, resources, and benefits that can be transitioned from her program to the organization. What document defines how these things can be transferred from the program to the organization?

  1. Operational transfer alliance plan
  2. Program milestone list
  3. Program transition agreement
  4. Program scope statement

Answer(s): C



Share your comments for PMI PGMP exam with other users:

T
Tai
8/28/2023 5:28:00 AM

wonderful material

V
VoiceofMidnight
12/29/2023 4:48:00 PM

i passed!! ...but barely! got 728, but needed 720 to pass. the exam hit me with labs right out of the gate! then it went to multiple choice. protip: study the labs!

A
A K
8/3/2023 11:56:00 AM

correct answer for question 92 is c -aws shield

N
Nitin Mindhe
11/27/2023 6:12:00 AM

great !! it is really good

B
BailleyOne
11/22/2023 1:45:00 AM

explanations for the answers are to the point.

P
patel
10/25/2023 8:17:00 AM

how can rea next

M
MortonG
10/19/2023 6:32:00 PM

question: 128 d is the wrong answer...should be c

J
Jayant
11/2/2023 3:15:00 AM

thanks for az 700 dumps

B
Bipul Mishra
12/14/2023 7:12:00 AM

thank you for this tableau dumps . it will helpfull for tableau certification

H
hello
10/31/2023 12:07:00 PM

good content

M
Matheus
9/3/2023 2:14:00 PM

just testing if the comments are real

Y
yenvti2@gmail.com
8/12/2023 7:56:00 PM

very helpful for exam preparation

M
Miguel
10/5/2023 12:16:00 PM

question 11: https://help.salesforce.com/s/articleview?id=sf.admin_lead_to_patient_setup_overview.htm&type=5

N
Noushin
11/28/2023 4:52:00 PM

i think the answer to question 42 is b not c

S
susan sandivore
8/28/2023 1:00:00 AM

thanks for the dump

A
Aderonke
10/31/2023 12:51:00 AM

fantastic assessments

P
Priscila
7/22/2022 9:59:00 AM

i find the xengine test engine simulator to be more fun than reading from pdf.

S
suresh
12/16/2023 10:54:00 PM

nice document

W
Wali
6/4/2023 10:07:00 PM

thank you for making the questions and answers intractive and selectable.

N
Nawaz
7/18/2023 1:10:00 AM

answers are correct?

D
das
6/23/2023 7:57:00 AM

can i belive this dump

S
Sanjay
10/15/2023 1:34:00 PM

great site to practice for sitecore exam

J
jaya
12/17/2023 8:36:00 AM

good for students

B
Bsmaind
8/20/2023 9:23:00 AM

nice practice dumps

K
kumar
11/15/2023 11:24:00 AM

nokia 4a0-114 dumps

V
Vetri
10/3/2023 12:59:00 AM

great content and wonderful to have the answers with explanation

R
Ranjith
8/21/2023 3:39:00 PM

for question #118, the answer is option c. the screen shot is showing the drop down, but the answer is marked incorrectly please update . thanks for sharing such nice questions.

E
Eduardo Ramírez
12/11/2023 9:55:00 PM

the correct answer for the question 29 is d.

D
Dass
11/2/2023 7:43:00 AM

question no 22: correct answers: bc, 1 per session 1 per page 1 per component always

R
Reddy
12/14/2023 2:42:00 AM

these are pretty useful

D
Daisy Delgado
1/9/2023 1:05:00 PM

awesome

A
Atif
6/13/2023 4:09:00 AM

yes please upload

X
Xunil
6/12/2023 3:04:00 PM

great job whoever put this together, for the greater good! thanks!

L
Lakshmi
10/2/2023 5:26:00 AM

just started to view all questions for the exam

AI Tutor 👋 I’m here to help!