ISTQB - Certified Tester Foundation Level ISTQB-CTFL Dumps in PDF

Free ISTQB ISTQB-CTFL Real Questions (page: 5)


The project situation after 11 months is:
- The first increment was released one week late but contained sufficient functionality to be declared fit for purpose'. However, there were 20 outstanding incidents deferred to increment two.
- The amount of voluntary overtime worked PV the test team has reduced the second Increment slippage to just 3 weeks.
- There is talk of reducing the scope of requirements. The purpose of this is to first deliver the application with support for manual testing and then to provide a delivery * weeks later to resolve any remaining points and provide support for automated testing (i.e. the link to the capture-replay tool).
- Concerns have been expressed by a section of the user community, that in some places the usability is very poor.

Which test management control option is most appropriate to adopt under these circumstances?

  1. Introduce mandatory evening and weekend working to retrieve the 3 week slippage.
  2. Reconsider the exit criteria and review the test plan in the context of the current situation.
  3. Advise the user community regarding the reduced scope of requirements and the additional incremental delivery.
  4. Arrange a meeting with the user community representatives to discuss the user interface.

Answer(s): B




The project situation after 11 months is:
- The first increment was released one week late but contained sufficient functionality to be declared fit for purpose'. However, there were 20 outstanding incidents deferred to increment two.
- The amount of voluntary overtime worked PV the test team has reduced the second Increment slippage to just 3 weeks.
- There is talk of reducing the scope of requirements. The purpose of this is to first deliver the application with support for manual testing and then to provide a delivery * weeks later to resolve any remaining points and provide support for automated testing (i.e. the link to the capture-replay tool).
- Concerns have been expressed by a section of the user community, that in some places the usability is very poor.

Risks should be constantly reviewed. Given the current situation, which one of the following factors is most likely to lead to a revised view of product risk?

  1. The concerns over the user interface may lead to changes to the interface which cannot be implemented by development in time for the second test iteration.
  2. The concerns over the user interface raises the likelihood of a risk in that area and increases the amount of test effort needed for the user interface, thereby limiting the test effort available for other parts of the test management tool.
  3. The delivery of the application without the interface changes may upset the user community.
  4. The method used for test estimation is not accurate enough and hence the money spent on testing exceeded its budget.

Answer(s): B




The project situation after 11 months is:
- The first increment was released one week late but contained sufficient functionality to be declared fit for purpose'. However, there were 20 outstanding incidents deferred to increment two.
- The amount of voluntary overtime worked PV the test team has reduced the second Increment slippage to just 3 weeks.
- There is talk of reducing the scope of requirements. The purpose of this is to first deliver the application with support for manual testing and then to provide a delivery * weeks later to resolve any remaining points and provide support for automated testing (i.e. the link to the capture-replay tool).
- Concerns have been expressed by a section of the user community, that in some places the usability is very poor.

Which of the following is least likely to be used as a technique to identify project and product risks?

  1. Brainstorming
  2. Inspections
  3. Expert interviews
  4. Independent assessments

Answer(s): B




The project situation after 11 months is:
- The first increment was released one week late but contained sufficient functionality to be declared fit for purpose'. However, there were 20 outstanding incidents deferred to increment two.
- The amount of voluntary overtime worked PV the test team has reduced the second Increment slippage to just 3 weeks.
- There is talk of reducing the scope of requirements. The purpose of this is to first deliver the application with support for manual testing and then to provide a delivery * weeks later to resolve any remaining points and provide support for automated testing (i.e. the link to the capture-replay tool).
- Concerns have been expressed by a section of the user community, that in some places the usability is very poor.

Which of the following is a project risk mitigation step you might take as test manager?

  1. Testing for performance problems
  2. Hiring a contractor after a test analyst leaves the company
  3. Arranging a back-up test environment in case the existing one fails during testing
  4. Performing a project retrospective meeting using the test results after each increment

Answer(s): C




For the first increment of the new enterprise HR product you have performed a product risk analysis using the FMEA method. Five risk items have been identified and the likelihood and impact have been scored using scoring tables. This has resulted in the following scores:


You have been asked to write a testing strategy for the company. Which statement best explains how risk can be addressed within the testing strategy?

  1. A test strategy should address identified generic product risks and present a process for mitigating those risks in line with the testing policy.
  2. A test strategy identifies the specific product for a project risk and defines the approach for the test project.
  3. A test strategy is derived from the test policy and describes the way risk assessments are performed in projects.
  4. A test strategy is the result of a project risk analysis and defines the approach and resources for testing.

Answer(s): A



Share your comments for ISTQB ISTQB-CTFL exam with other users:

V
Vv
12/2/2023 6:31:00 AM

good to prepare in this site

P
praveenkumar
11/20/2023 11:57:00 AM

very helpful to crack first attempt

A
asad Raza
5/15/2023 5:38:00 AM

please upload this exam

R
Reeta
7/17/2023 5:22:00 PM

please upload the c_activate22 dump questions with answer

W
Wong
12/20/2023 11:34:00 AM

q10 - the answer should be a. if its c, the criteria will meet if either the prospect is not part of the suppression lists or if the job title contains vice president

D
david
12/12/2023 12:38:00 PM

this was on the exam as of 1211/2023

T
Tink
7/24/2023 9:23:00 AM

great for prep

J
Jaro
12/18/2023 3:12:00 PM

i think in question 7 the first answer should be power bi portal (not power bi)

9
9eagles
4/7/2023 10:04:00 AM

on question 10 and so far 2 wrong answers as evident in the included reference link.

T
Tai
8/28/2023 5:28:00 AM

wonderful material

V
VoiceofMidnight
12/29/2023 4:48:00 PM

i passed!! ...but barely! got 728, but needed 720 to pass. the exam hit me with labs right out of the gate! then it went to multiple choice. protip: study the labs!

A
A K
8/3/2023 11:56:00 AM

correct answer for question 92 is c -aws shield

N
Nitin Mindhe
11/27/2023 6:12:00 AM

great !! it is really good

B
BailleyOne
11/22/2023 1:45:00 AM

explanations for the answers are to the point.

P
patel
10/25/2023 8:17:00 AM

how can rea next

M
MortonG
10/19/2023 6:32:00 PM

question: 128 d is the wrong answer...should be c

J
Jayant
11/2/2023 3:15:00 AM

thanks for az 700 dumps

B
Bipul Mishra
12/14/2023 7:12:00 AM

thank you for this tableau dumps . it will helpfull for tableau certification

H
hello
10/31/2023 12:07:00 PM

good content

M
Matheus
9/3/2023 2:14:00 PM

just testing if the comments are real

Y
yenvti2@gmail.com
8/12/2023 7:56:00 PM

very helpful for exam preparation

M
Miguel
10/5/2023 12:16:00 PM

question 11: https://help.salesforce.com/s/articleview?id=sf.admin_lead_to_patient_setup_overview.htm&type=5

N
Noushin
11/28/2023 4:52:00 PM

i think the answer to question 42 is b not c

S
susan sandivore
8/28/2023 1:00:00 AM

thanks for the dump

A
Aderonke
10/31/2023 12:51:00 AM

fantastic assessments

P
Priscila
7/22/2022 9:59:00 AM

i find the xengine test engine simulator to be more fun than reading from pdf.

S
suresh
12/16/2023 10:54:00 PM

nice document

W
Wali
6/4/2023 10:07:00 PM

thank you for making the questions and answers intractive and selectable.

N
Nawaz
7/18/2023 1:10:00 AM

answers are correct?

D
das
6/23/2023 7:57:00 AM

can i belive this dump

S
Sanjay
10/15/2023 1:34:00 PM

great site to practice for sitecore exam

J
jaya
12/17/2023 8:36:00 AM

good for students

B
Bsmaind
8/20/2023 9:23:00 AM

nice practice dumps

K
kumar
11/15/2023 11:24:00 AM

nokia 4a0-114 dumps

AI Tutor 👋 I’m here to help!