The project situation after 11 months is:
- The first increment was released one week late but contained sufficient functionality to be declared fit for purpose'. However, there were 20 outstanding incidents deferred to increment two.
- The amount of voluntary overtime worked PV the test team has reduced the second Increment slippage to just 3 weeks.
- There is talk of reducing the scope of requirements. The purpose of this is to first deliver the application with support for manual testing and then to provide a delivery * weeks later to resolve any remaining points and provide support for automated testing (i.e. the link to the capture-replay tool).
- Concerns have been expressed by a section of the user community, that in some places the usability is very poor.

Which of the following are valid reasons for adopting a different life cycle (from the V model), for increments after the first year?

(i). We do not have a clear understanding of the requirements from a customer perspective.
(ii). We see the risk of delivering requested functionality late as being higher than the risk of delivering a lower quality product.
(iii). We do not have a budget for additional regression testing which is needed to ensure that existing functionality is not compromised by future iterations.
(iv). The company test strategy does not fit well within the V life cycle model.

  1. (i) and (ii)
  2. (i) and (iv)
  3. (ii) and (iii)
  4. (ii) and (iv)

Answer(s): A




The project situation after 11 months is:
- The first increment was released one week late but contained sufficient functionality to be declared fit for purpose'. However, there were 20 outstanding incidents deferred to increment two.
- The amount of voluntary overtime worked PV the test team has reduced the second Increment slippage to just 3 weeks.
- There is talk of reducing the scope of requirements. The purpose of this is to first deliver the application with support for manual testing and then to provide a delivery * weeks later to resolve any remaining points and provide support for automated testing (i.e. the link to the capture-replay tool).
- Concerns have been expressed by a section of the user community, that in some places the usability is very poor.

Which of the following is a characteristic of good testing in any life cycle model?

  1. Analysis and design of tests begins as soon as development is completed.
  2. Some, but not all, development activities have corresponding test activities.
  3. Each test level has test objectives specific to that level.
  4. All document reviews involve the development team.

Answer(s): C




The project situation after 11 months is:
- The first increment was released one week late but contained sufficient functionality to be declared fit for purpose'. However, there were 20 outstanding incidents deferred to increment two.
- The amount of voluntary overtime worked PV the test team has reduced the second Increment slippage to just 3 weeks.
- There is talk of reducing the scope of requirements. The purpose of this is to first deliver the application with support for manual testing and then to provide a delivery * weeks later to resolve any remaining points and provide support for automated testing (i.e. the link to the capture-replay tool).
- Concerns have been expressed by a section of the user community, that in some places the usability is very poor.

Which of the following would you expect to see in the master test plan?

  1. A description of how the test cases are cross-referenced to requirements in the test management tool.
  2. A detailed identification of the resources that will carry out structural testing in the first iteration.
  3. The test approach that will be applied at system integration testing.
  4. A list of the names of the testers who will carry out the performance testing for the final iteration.

Answer(s): C




The project situation after 11 months is:
- The first increment was released one week late but contained sufficient functionality to be declared fit for purpose'. However, there were 20 outstanding incidents deferred to increment two.
- The amount of voluntary overtime worked PV the test team has reduced the second Increment slippage to just 3 weeks.
- There is talk of reducing the scope of requirements. The purpose of this is to first deliver the application with support for manual testing and then to provide a delivery * weeks later to resolve any remaining points and provide support for automated testing (i.e. the link to the capture-replay tool).
- Concerns have been expressed by a section of the user community, that in some places the usability is very poor.

Which of the following would be the most significant input to estimating the time to carry out the specified testing tasks?

  1. The skills and experience of developers to correct the failures.
  2. The standards used for the requirements specification.
  3. The metrics recorded from testing the capture-replay tool.
  4. The number of testers in the company and their grade.

Answer(s): C




The project situation after 11 months is:
- The first increment was released one week late but contained sufficient functionality to be declared fit for purpose'. However, there were 20 outstanding incidents deferred to increment two.
- The amount of voluntary overtime worked PV the test team has reduced the second Increment slippage to just 3 weeks.
- There is talk of reducing the scope of requirements. The purpose of this is to first deliver the application with support for manual testing and then to provide a delivery * weeks later to resolve any remaining points and provide support for automated testing (i.e. the link to the capture-replay tool).
- Concerns have been expressed by a section of the user community, that in some places the usability is very poor.

Which of the following would be the TWO most appropriate examples of entry criteria documented in the system integration test plan?

  1. The percentage of decision coverage achieved during unit testing.
  2. The availability of the latest version of the capture-replay tool (for testing the interface with the newly developed test management tool).
  3. The sign-off of a performance test software release note (test item transmittal report) by both development and testing showing that system performance meets the specified acceptance criteria.
  4. The percentage of acceptance test procedures scheduled for execution.
  5. The percentage of requirements coverage achieved during system integration test.

Answer(s): A,B



Viewing Page 4 of 45



Share your comments for ISTQB® ISTQB-CTFL exam with other users:

Karan 5/17/2023 4:26:00 AM

need this dump
Anonymous


Ramesh Kutumbaka 12/30/2023 11:17:00 PM

its really good to eventuate knowledge before appearing for the actual exam.
Anonymous


anonymous 7/20/2023 10:31:00 PM

this is great
CANADA


Xenofon 6/26/2023 9:35:00 AM

please i want the questions to pass the exam
UNITED STATES


Diego 1/21/2024 8:21:00 PM

i need to pass exam
Anonymous


Vichhai 12/25/2023 3:25:00 AM

great, i appreciate it.
AUSTRALIA


P Simon 8/25/2023 2:39:00 AM

please could you upload (isc)2 certified in cybersecurity (cc) exam questions
SOUTH AFRICA


Karim 10/8/2023 8:34:00 PM

good questions, wrong answers
Anonymous


Itumeleng 1/6/2024 12:53:00 PM

im preparing for exams
Anonymous


MS 1/19/2024 2:56:00 PM

question no: 42 isnt azure vm an iaas solution? so, shouldnt the answer be "no"?
Anonymous


keylly 11/28/2023 10:10:00 AM

im study azure
Anonymous


dorcas 9/22/2023 8:08:00 AM

i need this now
Anonymous


treyf 11/9/2023 5:13:00 AM

i took the aws saa-c03 test and scored 935/1000. it has all the exam dumps and important info.
UNITED STATES


anonymous 1/11/2024 4:50:00 AM

good questions
Anonymous


Anjum 9/23/2023 6:22:00 PM

well explained
Anonymous


Thakor 6/7/2023 11:52:00 PM

i got the full version and it helped me pass the exam. pdf version is very good.
INDIA


sartaj 7/18/2023 11:36:00 AM

provide the download link, please
INDIA


loso 7/25/2023 5:18:00 AM

please upload thank.
THAILAND


Paul 6/23/2023 7:12:00 AM

please can you share 1z0-1055-22 dump pls
UNITED STATES


exampei 10/7/2023 8:14:00 AM

i will wait impatiently. thank youu
Anonymous


Prince 10/31/2023 9:09:00 PM

is it possible to clear the exam if we focus on only these 156 questions instead of 623 questions? kindly help!
Anonymous


Ali Azam 12/7/2023 1:51:00 AM

really helped with preparation of my scrum exam
Anonymous


Jerman 9/29/2023 8:46:00 AM

very informative and through explanations
Anonymous


Jimmy 11/4/2023 12:11:00 PM

prep for exam
INDONESIA


Abhi 9/19/2023 1:22:00 PM

thanks for helping us
Anonymous


mrtom33 11/20/2023 4:51:00 AM

i prepared for the eccouncil 350-401 exam. i scored 92% on the test.
Anonymous


JUAN 6/28/2023 2:12:00 AM

aba questions to practice
UNITED STATES


LK 1/2/2024 11:56:00 AM

great content
Anonymous


Srijeeta 10/8/2023 6:24:00 AM

how do i get the remaining questions?
INDIA


Jovanne 7/26/2022 11:42:00 PM

well formatted pdf and the test engine software is free. well worth the money i sept.
ITALY


CHINIMILLI SATISH 8/29/2023 6:22:00 AM

looking for 1z0-116
Anonymous


Pedro Afonso 1/15/2024 8:01:00 AM

in question 22, shouldnt be in the data (option a) layer?
Anonymous


Pushkar 11/7/2022 12:12:00 AM

the questions are incredibly close to real exam. you people are amazing.
INDIA


Ankit S 11/13/2023 3:58:00 AM

q15. answer is b. simple
UNITED STATES