ISACA CRISC Exam (page: 49)
ISACA Certified in Risk and Information Systems Control
Updated on: 17-Feb-2026

Viewing Page 49 of 361

Tom works as a project manager for BlueWell Inc. He is determining which risks can affect the project. Which of the following inputs of the identify risks process is useful in identifying risks, and provides a quantitative assessment of the likely cost to complete the scheduled activities?

  1. Activity duration estimates
  2. Risk management plan
  3. Cost management plan
  4. Activity cost estimates

Answer(s): D

Explanation:

The activity cost estimates review is valuable in identifying risks as it provides a quantitative assessment of the expected cost to complete the scheduled activities and is expressed as a range, with a width of the range indicating the degrees of risk.

Incorrect Answers:
A: The activity duration estimates review is valuable in identifying risks associated to the time allowances for the activities or projects as a whole, with a width of the range indicating the degrees of risk.

B: This is the output of plan risk management process. A Risk management plan is a document arranged by a project manager to estimate the effectiveness, predict risks, and build response plans to mitigate them. It also consists of the risk assessment matrix.

C: The cost management plan sets how the costs on a project are managed during the project's lifecycle. It defines the format and principles by which the project costs are measured, reported, and controlled. The cost management plan identifies the person responsible for managing costs, those who have the authority to approve changes to the project or its budget, and how cost performance is quantitatively calculated and reported upon.



Which of the following baselines identifies the specifications required by the resource that meet the approved requirements?

  1. Functional baseline
  2. Allocated baseline
  3. Product baseline
  4. Developmental baseline

Answer(s): B

Explanation:

Allocated baseline identifies the specifications that meet the approved requirements. Incorrect Answers:
A: Functional baseline identifies the initial specifications before any changes are made.

C: Product baseline identifies the minimal specification required by the resource to meet business outcomes.

D: Developmental baseline identifies the state of the resources as it is developed to meet or exceed expectations and requirements.



Which of the following nodes of the decision tree analysis represents the start point of decision tree?

  1. Decision node
  2. End node
  3. Event node
  4. Root node

Answer(s): D

Explanation:

Root node is the starting node in the decision tree. Incorrect Answers:
A: Decision nodes represents the choice available to the decision maker, usually between a risky choice and its non-risky counterpart.

C: Event node represents the possible uncertain outcomes of a risky decision, with at least two nodes to illustrate the positive and negative range of events.

B: End node represents the outcomes of risk and decisions.



You are the project manager of the NHH Project. You are working with the project team to create a plan to document the procedures to manage risks throughout the project. This document will define how risks will be identified and quantified. It will also define how contingency plans will be implemented by the project team.
What document do you and your team is creating in this scenario?

  1. Project plan
  2. Resource management plan
  3. Project management plan
  4. Risk management plan

Answer(s): D

Explanation:

The risk management plan, part of the comprehensive management plan, defines how risks will be identified, analyzed, monitored and controlled, and even responded to.

A Risk management plan is a document arranged by a project manager to estimate the effectiveness, predict risks, and build response plans to mitigate them. It also consists of the risk assessment matrix.
Risks are built in with any project, and project managers evaluate risks repeatedly and build plans to address them. The risk management plan consists of analysis of possible risks with both high and low impacts, and the mitigation strategies to facilitate the project and avoid being derailed through which the common problems arise. Risk management plans should be timely reviewed by the project team in order to avoid having the analysis become stale and not reflective of actual potential project risks. Most critically, risk management plans include a risk strategy for project execution.

Incorrect Answers:
A: The project plan is not an official PMBOK project management plan.

B: The resource management plan defines the management of project resources, such as project team members, facilities, equipment, and contractors.

C: The project management plan is a comprehensive plan that communicates the intent of the project for all project management knowledge areas.



Where are all risks and risk responses documented as the project progresses?

  1. Risk management plan
  2. Project management plan
  3. Risk response plan
  4. Risk register

Answer(s): D

Explanation:

All risks, their responses, and other characteristics are documented in the risk register. As the project progresses and the conditions of the risk events change, the risk register should be updated to reflect the risk conditions.

Incorrect Answers:
A: The risk management plan addresses the project management's approach to risk management, risk identification, analysis, response, and control.

B: The project management plan is the overarching plan for the project, not the specifics of the risk responses and risk identification.

C: The risk response plan only addresses the planned risk responses for the identified risk events in the risk register.



Viewing Page 49 of 361



Share your comments for ISACA CRISC exam with other users:

NISHAD 11/7/2023 11:28:00 AM

how many questions are there in these dumps?
UNITED STATES


Pankaj 7/3/2023 3:57:00 AM

hi team, please upload this , i need it.
UNITED STATES


DN 9/4/2023 11:19:00 PM

question 14 - run terraform import: this is the recommended best practice for bringing manually created or destroyed resources under terraform management. you use terraform import to associate an existing resource with a terraform resource configuration. this ensures that terraform is aware of the resource, and you can subsequently manage it with terraform.
Anonymous


Zhiguang 8/19/2023 11:37:00 PM

please upload dump. thanks in advance.
Anonymous


deedee 12/23/2023 5:51:00 PM

great great
UNITED STATES


Asad Khan 11/1/2023 3:10:00 AM

answer 16 should be b your organizational policies require you to use virtual machines directly
Anonymous


Sale Danasabe 10/24/2023 5:21:00 PM

the question are kind of tricky of you didnt get the hnag on it.
Anonymous


Luis 11/16/2023 1:39:00 PM

can anyone tell me if this is for rhel8 or rhel9?
UNITED STATES


hik 1/19/2024 1:47:00 PM

good content
UNITED STATES


Blessious Phiri 8/15/2023 2:18:00 PM

pdb and cdb are critical to the database
Anonymous


Zuned 10/22/2023 4:39:00 AM

till 104 questions are free, lets see how it helps me in my exam today.
UNITED STATES


Muhammad Rawish Siddiqui 12/3/2023 12:11:00 PM

question # 56, answer is true not false.
SAUDI ARABIA


Amaresh Vashishtha 8/27/2023 1:33:00 AM

i would be requiring dumps to prepare for certification exam
Anonymous


Asad 9/8/2023 1:01:00 AM

very helpful
PAKISTAN


Blessious Phiri 8/13/2023 3:10:00 PM

control file is the heart of rman backup
Anonymous


Senthil 9/19/2023 5:47:00 AM

hi could you please upload the ibm c2090-543 dumps
Anonymous


Harry 6/27/2023 7:20:00 AM

appriciate if you could upload this again
AUSTRALIA


Anonymous 7/10/2023 4:10:00 AM

please upload the dump
SWEDEN


Raja 6/20/2023 5:30:00 AM

i found some questions answers mismatch with explanation answers. please properly update
UNITED STATES


Doora 11/30/2023 4:20:00 AM

nothing to mention
Anonymous


deally 1/19/2024 3:41:00 PM

knowable questions
UNITED STATES


Sonia 7/23/2023 4:03:00 PM

very helpfull
UNITED STATES


binEY 10/6/2023 5:15:00 AM

good questions
Anonymous


Neha 9/28/2023 1:58:00 PM

its helpful
Anonymous


Desmond 1/5/2023 9:11:00 PM

i just took my oracle exam and let me tell you, this exam dumps was a lifesaver! without them, iam not sure i would have passed. the questions were tricky and the answers were obscure, but the exam dumps had everything i needed. i would recommend to anyone looking to pass their oracle exams with flying colors (and a little bit of cheating) lol.
SINGAPORE


Davidson OZ 9/9/2023 6:37:00 PM

22. if you need to make sure that one computer in your hot-spot network can access the internet without hot-spot authentication, which menu allows you to do this? answer is ip binding and not wall garden. wall garden allows specified websites to be accessed with users authentication to the hotspot
Anonymous


381 9/2/2023 4:31:00 PM

is question 1 correct?
Anonymous


Laurent 10/6/2023 5:09:00 PM

good content
Anonymous


Sniper69 5/9/2022 11:04:00 PM

manged to pass the exam with this exam dumps.
UNITED STATES


Deepak 12/27/2023 2:37:00 AM

good questions
SINGAPORE


dba 9/23/2023 3:10:00 AM

can we please have the latest exam questions?
Anonymous


Prasad 9/29/2023 7:27:00 AM

please help with jn0-649 latest dumps
HONG KONG


GTI9982 7/31/2023 10:15:00 PM

please i need this dump. thanks
CANADA


Elton Riva 12/12/2023 8:20:00 PM

i have to take the aws certified developer - associate dva-c02 in the next few weeks and i wanted to know if the questions on your website are the same as the official exam.
Anonymous