You and your project team are identifying the risks that may exist within your project. Some of the risks are small risks that won't affect your project much if they happen. What should you do with these identified risk events?

  1. These risks can be dismissed.
  2. These risks can be accepted.
  3. These risks can be added to a low priority risk watch list.
  4. All risks must have a valid, documented risk response.

Answer(s): C

Explanation:

Low-impact, low-probability risks can be added to the low priority risk watch list. Incorrect Answers:
A: These risks are not dismissed; they are still documented on the low priority risk watch list.

B: While these risks may be accepted, they should be documented on the low priority risk watch list. This list will be periodically reviewed and the status of the risks may change.

D: Not every risk demands a risk response, so this choice is incorrect.



You are the project manager of your enterprise. You have introduced an intrusion detection system for the control. You have identified a warning of violation of security policies of your enterprise. What type of control is an intrusion detection system (IDS)?

  1. Detective
  2. Corrective
  3. Preventative
  4. Recovery

Answer(s): A

Explanation:

An intrusion detection system (IDS) is a device or software application that monitors network and/or system activities for malicious activities or policy violations and produces reports to a Management Station. Some systems may attempt to stop an intrusion attempt but this is neither required nor expected of a monitoring system. Intrusion detection and prevention systems (IDPS) are primarily focused on identifying possible incidents, logging information about them, and reporting attempts. In addition, organizations use IDPS for other purposes, such as identifying problems with security policies, documenting existing threats, and deterring individuals from violating security policies.

As IDS detects and gives warning when the violation of security policies of the enterprise occurs, it is a detective control.

Incorrect Answers:
B: These controls make effort to reduce the impact of a threat from problems discovered by detective controls. As IDS only detects but not reduce the impact, hence it is not a corrective control.

C: As IDS only detects the problem when it occurs and not prior of its occurrence, it is not preventive control.

D: These controls make efforts to overcome the impact of the incident on the business, hence IDS is not a recovery control.



What are the functions of audit and accountability control?
Each correct answer represents a complete solution. (Choose three.)

  1. Provides details on how to protect the audit logs
  2. Implement effective access control
  3. Implement an effective audit program
  4. Provides details on how to determine what to audit

Answer(s): A,C,D

Explanation:

Audit and accountability family of controls helps an organization implement an effective audit program. It provides details on how to determine what to audit. It provides details on how to protect the audit logs. It also includes information on using audit logs for non-repudiation.

Incorrect Answers:
B: Access Control is the family of controls that helps an organization implement effective access control. They ensure that users have the rights and permissions they need to perform their jobs, and no more. It includes principles such as least privilege and separation of duties.
Audit and accountability family of controls do not help in implementing effective access control.



Which among the following acts as a trigger for risk response process?

  1. Risk level increases above risk appetite
  2. Risk level increase above risk tolerance
  3. Risk level equates risk appetite
  4. Risk level equates the risk tolerance

Answer(s): B

Explanation:

The risk response process is triggered when a risk exceeds the enterprise's risk tolerance level. The acceptable variation relative to the achievement of an objective is termed as risk tolerance. In other words, risk tolerance is the acceptable deviation from the level set by the risk appetite and business objectives.

Risk tolerance is defined at the enterprise level by the board and clearly communicated to all stakeholders. A process should be in place to review and approve any exceptions to such standards.

Incorrect Answers:
A, C: Risk appetite level is not relevant in triggering of risk response process. Risk appetite is the amount of risk a company or other entity is willing to accept in pursuit of its mission. This is the responsibility of the board to decide risk appetite of an enterprise. When considering the risk appetite levels for the enterprise, the following two major factors should be taken into account:
The enterprise's objective capacity to absorb loss, e.g., financial loss, reputation damage, etc.
The culture towards risk taking-cautious or aggressive. In other words, the amount of loss the enterprise wants to accept in pursue of its objective fulfillment.

D: Risk response process is triggered when the risk level increases the risk tolerance level of the enterprise, and not when it just equates the risk tolerance level.



What is the value of exposure factor if the asset is lost completely?

  1. 1
  2. Infinity
  3. 10
  4. 0

Answer(s): A

Explanation:

Exposure Factor represents the impact of the risk over the asset, or percentage of asset lost. For example, if the Asset Value is reduced to two third, the exposure factor value is 0.66.
Therefore, when the asset is completely lost, the Exposure Factor is 1.0.

Incorrect Answers:
B, C, D: These are not the values of exposure factor for zero assets.



Share your comments for ISACA CRISC exam with other users:

B
Blessious Phiri
8/14/2023 9:53:00 AM

cbd and pdb are key to the database

A
Alkaed
10/19/2022 10:41:00 AM

the purchase and download process is very much streamlined. the xengine application is very nice and user-friendly but there is always room for improvement.

D
Dave Gregen
9/4/2023 3:17:00 PM

please upload p_sapea_2023

S
Sarah
6/13/2023 1:42:00 PM

anyone use this? the question dont seem to follow other formats and terminology i have been studying im getting worried

S
Shuv
10/3/2023 8:19:00 AM

good questions

R
Reb974
8/5/2023 1:44:00 AM

hello are these questions valid for ms-102

M
Mchal
7/20/2023 3:38:00 AM

some questions are wrongly answered but its good nonetheless

S
Sonbir
8/8/2023 1:04:00 PM

how to get system serial number using intune

M
Manju
10/19/2023 1:19:00 PM

is it really helpful to pass the exam

L
LeAnne Hair
8/24/2023 12:47:00 PM

#229 in incorrect - all the customers require an annual review

A
Abdul SK
9/28/2023 11:42:00 PM

kindy upload

A
Aderonke
10/23/2023 12:53:00 PM

fantastic assessment on psm 1

S
SAJI
7/20/2023 2:51:00 AM

56 question correct answer a,b

R
Raj Kumar
10/23/2023 8:52:00 PM

thank you for providing the q bank

P
piyush keshari
7/7/2023 9:46:00 PM

true quesstions

B
B.A.J
11/6/2023 7:01:00 AM

i can´t believe ms asks things like this, seems to be only marketing material.

G
Guss
5/23/2023 12:28:00 PM

hi, could you please add the last update of ns0-527

R
Rond65
8/22/2023 4:39:00 PM

question #3 refers to vnet4 and vnet5. however, there is no vnet5 listed in the case study (testlet 2).

C
Cheers
12/13/2023 9:55:00 AM

sometimes it may be good some times it may be

S
Sumita Bose
7/21/2023 1:01:00 AM

qs 4 answer seems wrong- please check

A
Amit
9/7/2023 12:53:00 AM

very detailed explanation !

F
FisherGirl
5/16/2022 10:36:00 PM

the interactive nature of the test engine application makes the preparation process less boring.

C
Chiranthaka
9/20/2023 11:15:00 AM

very useful.

S
SK
7/15/2023 3:51:00 AM

complete question dump should be made available for practice.

G
Gamerrr420
5/25/2022 9:38:00 PM

i just passed my first exam. i got 2 exam dumps as part of the 50% sale. my second exam is under work. once i write that exam i report my result. but so far i am confident.

K
Kudu hgeur
9/21/2023 5:58:00 PM

nice create dewey stefen

A
Anorag
9/6/2023 9:24:00 AM

i just wrote this exam and it is still valid. the questions are exactly the same but there are about 4 or 5 questions that are answered incorrectly. so watch out for those. best of luck with your exam.

N
Nathan
1/10/2023 3:54:00 PM

passed my exam today. this is a good start to 2023.

1
1
10/28/2023 7:32:00 AM

great sharing

A
Anand
1/20/2024 10:36:00 AM

very helpful

K
Kumar
6/23/2023 1:07:00 PM

thanks.. very helpful

U
User random
11/15/2023 3:01:00 AM

i registered for 1z0-1047-23 but dumps qre available for 1z0-1047-22. help me with this...

K
kk
1/17/2024 3:00:00 PM

very helpful

R
Raj
7/24/2023 10:20:00 AM

please upload oracle 1z0-1110-22 exam pdf

AI Tutor 👋 I’m here to help!