Karen is the business analyst for her organization and she's reviewing the tasks within her endeavor. Several of the tasks have the characteristic that the activity will be completed with the project stakeholders, consultants, and business analyst, though this hasn't yet been approved. What is this condition of believing some things to be true about an activity without proving the validity of the belief called?
Answer(s): B
An assumption is something that you believe to be true, but it's not been proven to be true or false. The assumption in this scenario is that the stakeholders will be available to complete activities. Answer C is incorrect. A constraint is something that limits your options. Answer D is incorrect. A boundary defines what's in and out of the domain of business analysis, project management, or any other endeavor.Answer A is incorrect. A risk is an uncertain event or condition that may have a positive or negative effect on the project.
All of the following are examples of elicitation techniques that are used as part of the business analyst elicitation task except for which one?
Answer(s): C
Decomposition describes the process of taking the product or project scope and breaking it down into smaller, more manageable units.Decomposition is not an elicitation technique.Answer A is incorrect. Brainstorming is an elicitation technique that's useful for requirements gathering. Answer B is incorrect. Observation allows the stakeholder to actively or passively observe the work to better understand the requirements of the solution. Answer D is incorrect. Prototyping allows the business analyst and team to create mockups of the deliverable for solution testing and requirements approval.
You are the business analyst for your organization and you're preparing to elicit requirements from the stakeholders. You've gathered several inputs to help with the elicitation process. Which input(s) will be used to ensure that you understand the type of information that should be elicited from the stakeholders?
The business need and the solution scope are the two inputs which help the business analyst understand what should be elicited from the stakeholders. Answer A is incorrect. Stakeholder list, roles, and responsibilities help the business analyst understand from whom the requirements should be elicited. Answer D is incorrect. Stakeholder list, roles, and responsibilities help the business analyst understand from whom the requirements should be elicited. Answer B is incorrect. Risk assessment is a review of the risks in the project and isn't an input to elicitation business analyst tasks.
You are a business analyst for your organization and you're working with the stakeholders to identify the primary inputs to the business analysis approach. Which one of the following is a primary input to the business analysis approach?
Answer(s): A
A primary input to the business analysis approach is to consider the problem or opportunity faced by the organization.Answer C is incorrect. The time allowed for business analysis planning does have an effect on the thoroughness of the business analysis activities, but this isn't the best answer for the Question. Answer D is incorrect. While risk and reward are considerations, consideration of the problem or opportunity is a better choice for this Question.Answer B is incorrect. This answer doesn't consider the reward of the opportunity or acknowledge,as there may also be problems to be solved, not just opportunities to seize.
Your organization is using a plan-driven approach to business analysis. What must you do with all of the communication documents created as part of this high-priority project that you are serving as the business analyst for?
Communications in a plan-driven approach to business analysis must use formal communication. Formal communications should be archived as part of the organizational process assets. Answer A is incorrect. The communications management plan may dictate that the communications be archived, but this is not a requirement of the communications management plan. Answer D is incorrect. The project manager may want to reference the communication but doesn't always need. If the communications are archived, then the project manager can access them as needed.Answer B is incorrect. Communication documents are not destroyed; they are archived as part of the organizational process assets.
Share your comments for IIBA CCBA exam with other users:
very helpful!
question #18s answer should be a, not d. this should be corrected. it should be minvalidityperiod
thanks for the exact solution
need to refer the questions and have to give the exam
i need it right now if it was possible please
i need it very much please share it in the fastest time.
correct answer is d for student.java program
q:37 c is correct
q6 exam topic: terramearth, c: correct answer: copy 1petabyte to encrypted usb device ???
explained answers
plan to take theaws certified developer - associate dva-c02 in the next few weeks
very helpfull
good questions
help to practice csa exam
nice tip and well documented
i need the exam
please upload
prepping for fsc exam
pd1 with great experience
@t it seems like azure service bus message quesues could be the best solution
helpful to check your understanding.
question 128 the answer should be static not auto
more comments here
great support to appear for exams
useful dumps
making progress
q31 answer should be d i think
is this real?
q10: c and f are also true. q11: this is outdated. you no longer need ownership on a pipe to operate it
good questions with simple explanation
admin guide (windows) respond to malicious causality chains. when the cortex xdr agent identifies a remote network connection that attempts to perform malicious activity—such as encrypting endpoint files—the agent can automatically block the ip address to close all existing communication and block new connections from this ip address to the endpoint. when cortex xdrblocks an ip address per endpoint, that address remains blocked throughout all agent profiles and policies, including any host-firewall policy rules. you can view the list of all blocked ip addresses per endpoint from the action center, as well as unblock them to re-enable communication as appropriate. this module is supported with cortex xdr agent 7.3.0 and later. select the action mode to take when the cortex xdr agent detects remote malicious causality chains: enabled (default)—terminate connection and block ip address of the remote connection. disabled—do not block remote ip addresses. to allow specific and known s
very inciting
question 5, it seems a instead of d, because: - care plan = case - patient = person account - product = product2;
it look like real one