You are the business analyst for your organization and you are completing the manage requirements traceability process. You are tracking the requirements to determine how the requirements are interrelated with one another and with the actual delivery of the project scope.
There are actually three reasons why the business analyst should trace requirements. Which one of the following is not one of the three reasons why trace requirements is useful?

  1. Impact analysis
  2. Requirements coverage
  3. Requirements allocation
  4. Quality control

Answer(s): D



Ned is the business analyst for the NHQ Company. He is working with Stan on completing the requirements prioritization of all the identified requirements.
Why would Stan and Ned complete requirements prioritization?

  1. To determine which requirements should be completed first
  2. To determine which requirements should not be completed at all
  3. To determine which requirements carry the most risk
  4. To determine who created what requirement based on their position in the organization

Answer(s): A



You are the business analyst for your organization. You are coaching Tom about the different approaches to business analysis.

Which type of business analysis approach has the most business analysis work at the beginning of the project or during the start of a project phase?

  1. Change-driven approach
  2. Value-driven approach
  3. Plan-driven approach
  4. Requirements-driven approach

Answer(s): C



You are the business analyst for your organization. You are currently identifying opportunities for a customer to improve their business processes. The customer wants to streamline their business efforts either through new technologies, better processes, or a combination of both. The customer demands, however, that the solution should not cost more than $300,000 to implement and support for one year.

What does the $300,000 represent?

  1. Solution cost
  2. Budget
  3. Requirements
  4. Constraint

Answer(s): D



You are the business analyst for your organization and are with another business analyst, Steve, on the requirements elicitation for a new solution. You warn Steve that you'll need to be tracing the requirements in an effort to prevent scope creep.

What is scope creep?

  1. The scope grows slightly larger as more requirements, often unneeded, are added to the scope
  2. The scope slips on the schedule which in turn delays the project delivery date
  3. Gold plating
  4. The scope shifts from the original intent of the business case

Answer(s): A



Viewing Page 15 of 101



Share your comments for IIBA CBAP exam with other users:

Ajay 10/3/2023 12:17:00 PM

could you please re-upload this exam? thanks a lot!
Anonymous


vikas 10/28/2023 6:57:00 AM

provide access
EUROPEAN UNION