In a theory of constraints (TOC) analysis, the bottleneck operation (the constraint) corresponds to which part of the drum-buffer-rope model?
Answer(s): B
Production flow through a constraint is managed using the drum-buffer-rope (DBR) system. The drum (i.e., the beat to which a production process marches) is the bottleneck operation. The constraint sets the pace for the entire process. The buffer is a minimal amount of work-in-process input to the drum that is maintained to ensure that it is always in operation. The rope is the sequence of activities preceding and including the bottleneck operation that must be coordinated to avoid inventory buildup.
The process model used in a theory of constraints (TOC) analysis is called:
Production flow through a constraint is managed using the drum-buffer-rope (DBR) system. The drum (i.e.. the beat to which a production process marches) is the bottleneck operation. The constraint sets the pace for the entire process. The buffer is a minimal amount of work-in-process input to the drum that is maintained to ensure that it is always in operation. The rope is the sequence of activities preceding and including the bottleneck operation that must be coordinated to avoid inventory buildup.
The following steps make up the stages of a theory of constraints (TOC) analysis.I). Determine the most profitable product mix given the constraint.II). Increase capacity at the constraint.Ill). Identify the constraint.IV). Redesign the manufacturing process.V). Maximize the flow through the constraint.If executed in the correct order, the sequence is
Answer(s): D
The steps in a TOC analysis are (1) identify the constraint. (2) determine the most profitable product mix given the constraint, (3) maximize the flow through the constraint, (4) increase capacity at the constraint, and (5) redesign the manufacturing process for greater flexibility and speed.
A manufacturer can sell its single product for US $660. Below are the cost data for the product:Direct materials US$170Direct labor 225Manufacturing overhead 90The relevant margin amount when beginning a theory of constraints (TOC) analysis is:
Answer(s): A
A theory of constraints (TOC) analysis proceeds from the assumption that only direct materials costs are truly variable in the short run. This is called throughput, or super variable, costing. The relevant margin amount is throughput margin, which equals price minus direct materials. Thus, the relevant margin amount for this manufacturer is US $490 (US $660-US $170).
Below are data concerning the hours spent by a manufacturer's two products in its two processes.The constraint is:
Answer(s): C
In theory of constraints (TOC) analysis, the constraint (bottleneck) operation is the slowest part of the process. It can usually be identified as the one where work-in-process backs up the most of this manufacturer's two operations, the one that requires the most total time is assembly.
Share your comments for IIA IIA-CIA-Part3 exam with other users:
nice questions
i need ielts general training audio guide questions
please make this content available
content is good
latest dumps please
aside from pdf the test engine software is helpful. the interface is user-friendly and intuitive, making it easy to navigate and find the questions.
questions and options are correct, but the answers are wrong sometimes. so please check twice or refer some other platform for the right answer
90% of questions was there but i failed the exam, i marked the answers as per the guide but looks like they are not accurate , if not i would have passed the exam given that i saw about 45 of 50 questions from dump
answer to this question "what administrative safeguards should be implemented to protect the collected data while in use by manasa and her product management team? " it should be (c) for the following reasons: this administrative safeguard involves controlling access to collected data by ensuring that only individuals who need the data for their job responsibilities have access to it. this helps minimize the risk of unauthorized access and potential misuse of sensitive information. while other options such as (a) documenting data flows and (b) conducting a privacy impact assessment (pia) are important steps in data protection, implementing a "need to know" access policy directly addresses the issue of protecting data while in use by limiting access to those who require it for legitimate purposes. (d) is not directly related to safeguarding data during use; it focuses on data transfers and location.
password lockout being the correct answer for question 37 does not make sense. it should be geofencing.
for question 4, the righr answer is :recover automatically from failures
question number 4s answer is 3, option c. i
very good questions
i am confused about the answers to the questions. are the answers correct?
very usefull
need certification.
great exam prep
i require dump
good morning, could you please upload this exam again,
hi can you please upload the dumps for sap contingent module. thanks
good questions
looking forward to the real exam
good ones for exam preparation
this is a good experience
hi everyone
waiting for the dump. please upload.
upload cks exam questions
awesome training material
where is dump
q. 289 - the correct answer should be b not d, since the question asks for the most secure way to provide access to a s3 bucket (a single one), and by principle of the least privilege you should not be giving access to all buckets.
please i need if possible h12-831,
good collection of questions and solution for pl500 certification
i would like to appear the exam.
i am very happy as i cleared my comptia a+ 220-1101 exam. i studied from as it has all exam dumps and mock tests available. i got 91% on the test.